Penrith Local Environmental Plan 2010
sch.3-secDemolition or removal of dwelling houses or ancillary development (in Zones C3 and C4)
Start here
Get a plain-English read of sch.3-sec
Turn the raw legal text into a practical explanation grounded in Penrith Local Environmental Plan 2010.
sch.3-sec Demolition or removal of dwelling houses or ancillary development (in Zones C3 and C4)
Demolition or removal of dwelling houses or ancillary development (in Zones C3 and C4)
(1) Application and general
(a) Must be carried out in accordance with AS 2601—2001, The demolition of structures.
(b) Must be completed in accordance with the requirements of the WorkCover Authority.
(c) Maximum height of structure to be demolished—2 storeys above ground level (existing).
(d) Must not be a heritage item or a building in a heritage conservation area.
(e) All services must be suitably disconnected and capped off or sealed.
(2) Asbestos
(a) The removal of asbestos material must be carried out by a licensed asbestos removal contractor.
(b) All asbestos laden waste must be disposed of at a tipping facility licensed by the Environmental Protection Authority to receive asbestos waste.
(3) Dust control Dust suppression techniques must be used to reduce any potential nuisance to surrounding properties.
(4) Waste management A waste management plan including details of the proposed locations for the disposal of all excavated material and waste from the site must be prepared.
(5) Noise Demolition works to be restricted to the hours permitted in accordance with the NSW Government’s Interim Construction Noise Guideline published in July 2009.
cll 6.5–6.7: Rep 2015 (21), Sch 1 [43].