This Plan sets the local planning rules for Orange: it maps zones, lists permitted/prohibited uses, and fixes key development standards (lot sizes, building heights, floor space ratios) and environmental overlays that trigger consent or constraints (e.g. heritage, flood, biodiversity) (cls 1.3, 2.3, 4.1, 4.3, 5.10, 5.21). Landowners and developers pay compliance costs and seek consent from the Council (cl 1.6); the Plan allocates decision‑making discretion to the consent authority and embeds technical requirements and infrastructure controls that shape what can be built and when.
This instrument is a local environmental plan for the City of Orange that sets the planning framework for land use, subdivision, development standards, environmental protections and several locally specific controls. It identifies the land to which it applies (cl 1.3, the Land Application Map), the Council as the consent authority (cl 1.6), and the maps and schedules that give effect to zoning, lot sizes, heritage listings and other locational controls (cl 1.7; Land Zoning Map; Lot Size Map; Height of Buildings Map; Floor Space Ratio Map; Terrestrial Biodiversity Map; Heritage Map; Drinking Water Catchment Map; Watercourse Map; Affordable Housing Map; Buffer Zone Map and others referenced throughout).
Mechanically, the Plan does the following:
Establishes the zones that apply to land in Orange and the objectives for each zone (cl 2.1; cl 2.3(1) and the Land Use Table at the end of Part 2). The Land Use Table specifies, for each zone, what development is permitted without consent, permitted only with consent, and prohibited (cl 2.3(1)).
Requires development consent for a range of activities identified in the Plan, including subdivision (cl 2.6), demolition (cl 2.7) and temporary uses subject to limits (cl 2.8). It also sets out detailed development standards such as minimum lot sizes (cl 4.1 and related clauses 4.1AA-4.1D), height limits (cl 4.3) and floor space ratios (cl 4.4), with the relevant maxima shown on the Plan's maps.
Identifies categories of exempt and complying development, and the criteria that must be met for those categories (Part 3: cl 3.1 and cl 3.2; Schedule 2; Schedule 3).
Contains environmental and heritage controls that must be considered when assessing development: heritage conservation (cl 5.10 and Schedule 5), terrestrial biodiversity (cl 7.4), riparian land and watercourses (cl 7.5), groundwater vulnerability (cl 7.6), drinking water catchments (cl 7.7), stormwater management (cl 7.3) and flood planning (cl 5.21, cl 5.22).
Current sections
Direct links to the current provisions in Orange Local Environmental Plan 2011.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Agriculture; Airstrips; Animal boarding or training establishments; Aquaculture; Bed and breakfast accommodation; Business identification signs; Cellar door premises; Community facilities; Dual occupancies; Dwelling houses; Eco-tourist facilities; Environmental facilities; Extractive industries; Farm buildings; Farm stay accommodation; Forestry; Helipads; Home businesses; Home industries; Information and education facilities; Intensive livestock agriculture; Intensive plant agriculture; Landscaping material supplies; Open cut mining; Recreation areas; Recreation facilities (major); Recreation facilities (outdoor); Roads; Roadside stalls; Rural industries; Secondary dwellings; Veterinary hospitals; Water supply systems
4
Prohibited
4 Prohibited
4 Prohibited
Any development not specified in item 2 or 3
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Note.
If land, other than land specified in the Table to subclause (2), is required to be acquired under the owner-initiated acquisition provisions, the Minister for Planning and Infrastructure is required to take action to enable the designation of the acquiring authority under this clause. Pending the designation of the acquiring authority for that land, the acquiring authority is to be the authority determined by order of the Minister for Planning and Infrastructure (see section 21 of the Land Acquisition (Just Terms Compensation) Act 1991).
Part 6
Urban release areas
Part 6 Urban release areas
Part 6 Urban release areas
6
Arrangements for designated State public infrastructure
6 Arrangements for designated State public infrastructure
6.1 Arrangements for designated State public infrastructure
(1) The objective of this clause is to require satisfactory arrangements to be made for the provision of designated State public infrastructure before the subdivision of land in an urban release area to satisfy needs that arise from development on the land, but only if the land is developed intensively for urban purposes.
(2) Development consent must not be granted for the subdivision of land in an urban release area if the subdivision would create a lot smaller than the minimum lot size permitted on the land immediately before the land became, or became part of, an urban release area, unless the Director-General has certified in writing to the consent authority that satisfactory arrangements have been made to contribute to the provision of designated State public infrastructure in relation to that lot.
(3) Subclause (2) does not apply to—
(a) any lot identified in the certificate as a residue lot, or
(b) any lot to be created by a subdivision of land that was the subject of a previous development consent granted in accordance with this clause, or
(c) any lot that is proposed in the development application to be reserved or dedicated for public open space, public roads, public utility undertakings, educational facilities or any other public purpose, or
(d) a subdivision for the purpose only of rectifying an encroachment on any existing lot.
(4) This clause does not apply to land in an urban release area if all or any part of the land is in a region within the meaning of the Act, Division 7.1, Subdivision 4.
(a) to ensure that earthworks for which development consent is required will not have a detrimental impact on environmental functions and processes, neighbouring uses, cultural or heritage items or features of the surrounding land,
(b) to allow earthworks of a minor nature without requiring separate development consent.
(2) Development consent is required for earthworks unless—
(a) the earthworks are exempt development under this Plan or another applicable environmental planning instrument, or
(b) the earthworks are ancillary to other development for which development consent has been given.
(3) Before granting development consent for earthworks, the consent authority must consider the following matters—
(a) the likely disruption of, or any detrimental effect on, existing drainage patterns and soil stability in the locality of the development,
(b) the effect of the development on the likely future use or redevelopment of the land,
(c) the quality of the fill or the soil to be excavated, or both,
(d) the effect of the development on the existing and likely amenity of adjoining properties,
(e) the source of any fill material and the destination of any excavated material,
(f) the likelihood of disturbing relics,
(g) the proximity to and potential for adverse impacts on any waterway, drinking water catchment or environmentally sensitive area,
(h) any measures proposed to minimise or mitigate the impacts referred to in paragraph (g).
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
sch 2: Am 2022 (831), Sch 1.21[8] [9].
sch.2-sec
Advertising signage (business identification signs in Zone E4)
sch.2-sec Advertising signage (business identification signs in Zone E4)
Advertising signage (business identification signs in Zone E4)
(1) Pole or pylon signs—
(a) Only one pole or pylon sign (which may include a directory board for multiple occupancies on the land) per site.
(b) Maximum area—5.0m2.
(c) Maximum height—4.6m.
(d) Must not obscure sight distance for vehicles approaching, entering or leaving the site.
(2) Flush wall signs—
(a) For a multiple occupancy site—must not exceed 2.5m2.
(b) For a single occupancy site—must not exceed 20% of the area of the front elevation of the building.
(c) If in relation to an industrial building or unit—must be attached to the building or unit.
(3) Projecting wall signs—
(a) For a single occupancy site—must not exceed 5m2.
(b) If in relation to an industrial building or unit—must be attached to the building or unit.
sch.2-sec-oc.2
Advertising signage (business identification signs in Zone R1, R2, R3 and R5)
sch.2-sec-oc.2 Advertising signage (business identification signs in Zone R1, R2, R3 and R5)
Advertising signage (business identification signs in Zone R1, R2, R3 and R5)
Internal signs—
(a) Must not comprise an item of environmental heritage as detailed in Schedule 5.
(b) Must not be visible from outside the premises on which it is displayed.
(c) If attached to a glass display window—must be behind the glass.
sch.2-sec-oc.3
Advertising signage (other signs)
sch.2-sec-oc.3 Advertising signage (other signs)
Advertising signage (other signs)
(1) Internal signs—
(a) Must not comprise an item of environmental heritage as detailed in Schedule 5.
(b) Must not be visible from outside the premises on which it is displayed.
(c) If attached to a glass display window—must be behind the glass.
(2) Real estate signs—
(a) In rural or residential zones—maximum area of 2.5m2.
(b) In employment or mixed use zones—maximum area of 4.5m2.
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Orange Local Environmental Plan 2011.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Orange in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to encourage development that complements and enhances the unique character of Orange as a major regional centre boasting a diverse economy and offering an attractive regional lifestyle,
(b) to provide for a range of development opportunities that contribute to the social, economic and environmental resources of Orange in a way that allows the needs of present and future generations to be met by implementing the principles of ecologically sustainable development,
(c) to conserve and enhance the water resources on which Orange depends, particularly water supply catchments,
(d) to manage rural land as an environmental resource that provides economic and social benefits for Orange,
(e) to provide a range of housing choices in planned urban and rural locations to meet population growth,
(f) to recognise and manage valued environmental heritage, landscape and scenic features of Orange.
1 Land to which Plan applies
1 Land to which Plan applies
1.3 Land to which Plan applies
This Plan applies to the land identified on the Land Application Map.
Provides local exceptions, additions and precinct-specific rules: Additional permitted uses for particular parcels (Schedule 1, cl 2.5), special provisions for urban release areas including infrastructure arrangements (Part 6: cl 6.1-6.3), public land classification (cl 5.2 and Schedule 4) and precinct controls such as Redmond Place (cl 7.16-7.17) and Shiralee Hilltop Park buffer (cl 7.15).
Places constraints on how development standards can be varied. Clause 4.6 allows consent authorities discretion to grant consent despite contravening a development standard, but only if the applicant demonstrates that compliance is unreasonable or unnecessary and there are sufficient environmental planning grounds; the clause lists standards it does not apply to (cl 4.6).
The Plan also signals its relationship with State instruments and laws. It is subject to any State environmental planning policy that prevails (cl 1.9(1)), cross-references the Environmental Planning and Assessment Act 1979 and several other Acts (for example the Heritage Act 1977, the Local Government Act 1993, the Rural Fires Act 1997, Fisheries Management Act 1994 and various water Acts) where their regimes intersect with planning outcomes. It contains savings and transitional provisions for development applications lodged before amendments or commencement (cl 1.8A).
Taken together, the Plan is the local statutory specification of permitted land uses and development controls for Orange, implemented by maps and a detailed Land Use Table, supplemented by local schedules and standardised development requirements for environmental, heritage, servicing and infrastructure matters.
Main concepts
The Plan organises its regulatory scheme around a small set of recurring legal and spatial concepts that govern permitted activity, assessment and outcomes.
Zoning and Land Use Table (cl 2.1, cl 2.3)
The Plan is zone-based. It lists rural, residential, employment, mixed-use, special purpose, recreation and conservation zones (cl 2.1) and locates land on a Land Zoning Map (cl 2.2). The Land Use Table specifies permitted without consent, permitted with consent, and prohibited development in each zone (cl 2.3(1)-(2)). Consent authorities must have regard to zone objectives when determining applications (cl 2.3(2)).
Maps as operative controls (cl 1.7)
Named maps adopted by the Plan (Zoning Map, Lot Size Map, Height Map, FSR Map, Terrestrial Biodiversity Map, Heritage Map, Watercourse Map, Affordable Housing Map, Buffer Zone Map and others) are adopted as the spatial source of many standards and restrictions; they may be amended as provided (cl 1.7(1)-(3)). The Plan tells users where to access these maps (Planning Portal).
Development consent, exempt and complying development (Part 3)
The Plan distinguishes development requiring development consent from exempt development (cl 3.1; Schedule 2) and complying development (cl 3.2; Schedule 3). Exempt development is defined by Schedule 2 and must meet the Building Code and other criteria (cl 3.1(2)-(5)). Complying development follows the State policy plus local schedules; a complying development certificate is subject to conditions (cl 3.2(4)).
Principal development standards (Part 4)
Key measurable standards are set by maps and clauses: minimum lot sizes for subdivision (cl 4.1 and linked Lot Size Map), minimum lot sizes for community title/strata (cl 4.1AA, 4.1A), minimum lot sizes for dual occupancy and multi-dwelling housing (cl 4.1B) and exceptions (cl 4.1C-4.1D). Maximum heights and floor space ratios are map-based (cl 4.3, cl 4.4), with detailed rules for calculating site area and FSR (cl 4.5). Clause 4.6 permits limited exceptions to development standards subject to specified tests.
Environmental and heritage overlays (Part 5; Part 7)
The Plan embeds overlay-style controls: heritage items/areas are listed in Schedule 5 and require consent for demolition, alteration and certain works (cl 5.10). Ecological and water protections are expressed as location-based obligations: terrestrial biodiversity (cl 7.4), riparian buffers and watercourse protections (cl 7.5), groundwater vulnerability (cl 7.6) and drinking water catchments (cl 7.7). Flood planning and special flood considerations are governed by objectives and tests that must be satisfied before consent (cl 5.21, cl 5.22).
Localised and technical controls
The Plan contains a range of specific operational limits: controls for bed and breakfast, home businesses/industries, retail floor area caps (cl 5.4), secondary dwelling size/distance controls (cl 5.4(9); cl 5.5), aquaculture design and site location requirements (cl 5.19 and Schedule 6), aircraft noise and airspace operations (cl 7.9-7.10), stormwater management and essential services (cl 7.3; cl 7.11), and special precinct requirements (Part 6, cl 6.1-6.4 for urban release areas and cl 7.14-7.17 for local precincts).
Interactions with other regulation
The Plan explicitly defers to State environmental planning policies where they prevail (cl 1.9(1)). It cross-references other Acts for particular matters: the Heritage Act for heritage listings (cl 5.10), the Rural Fires Act for hazard reduction works (cl 5.11), the Land Acquisition (Just Terms Compensation) Act for owner‑initiated acquisitions and acquisition authorities (cl 5.1), the Crown Land Management Act and the National Parks and Wildlife Act for certain covenant suspensions (cl 1.9A(2)), and BASIX-related commitments which the Plan disqualifies from variation under cl 4.6(8).
Administrative dynamics
The Council is the statutory consent authority except where the Act provides otherwise (cl 1.6). Certain state authorities are specified as the acquiring authority for particular reserved land (cl 5.1(2) table). The Plan gives the Minister/Director-General roles in infrastructure certification for urban release areas (cl 6.1(2)) and requires consultation with Commonwealth bodies where airspace/airport surfaces are affected (cl 7.9).
Taken together, these concepts create a two‑part compliance architecture: first, identify applicable maps and zone rules to determine if a proposed use is permitted, permitted-with-consent, complying or exempt; second, apply location-specific overlays and standards (heritage, biodiversity, water, flood risk, essential services), prepare the necessary documentation and satisfy the consent authority’s matters for consideration.
Who it affects
Owners, applicants and developers
Landowners, prospective purchasers and developers are the primary subjects of the Plan. The Plan controls what development they can carry out without consent (Schedule 2 or the Land Use Table), what requires development consent (for example subdivision cl 2.6; demolition cl 2.7), and the numerical and design constraints on development (minimum lot sizes cl 4.1; height cl 4.3; FSR cl 4.4; various caps at cl 5.4). Applicants proposing development that contravenes a development standard must prepare justification material under cl 4.6 and the Regulation referenced in the note to cl 4.6.
Local government and consent authorities
The Council is the consent authority for matters under the Plan (cl 1.6) and must apply the Plan’s zone objectives, maps and local clauses when determining applications (cl 2.3(2); cl 5.2). The consent authority also has specific procedural duties: it must notify and consider responses from the Heritage Council when archaeological sites are involved (cl 5.10(7)); consult with local Aboriginal communities where Aboriginal heritage significance may be affected (cl 5.10(8)); and consult relevant Commonwealth bodies where airspace surfaces will be penetrated (cl 7.9(2)-(4)).
State agencies and prescribed authorities
State policies and agencies are implicated. State environmental planning policies prevail where they conflict (cl 1.9(1)). Specific agencies are named as acquiring authorities for reserved land (cl 5.1(2) table: e.g. Transport for NSW for classified roads, the corporation constituted under s 2.5 of the Act for regional open space). Fire and Rescue NSW appears in the context of fire alarm monitoring conversions (cl 5.8). The Department of Primary Industries and Planning Secretary are referred to in intensive livestock/agriculture guidance (cl 5.18(3)(h)). Commonwealth aviation bodies must be consulted on airspace penetrations (cl 7.9(2)).
Heritage and Aboriginal stakeholders
Owners and applicants whose land contains heritage items, conservation areas, archaeological sites or Aboriginal places of heritage significance are affected by the consent requirements at cl 5.10 and Schedule 5 (heritage list). The Plan requires notification and consultation steps and allows the consent authority to require heritage management documents or conservation management plans (cl 5.10(4)-(6), (7)-(9)).
Neighbours and the local community
The Plan restricts or conditions development to protect amenity, environmental values and community assets: measures address noise management for music at licensed premises (cl 5.20), stormwater impacts on downstream land (cl 7.3), biodiversity and riparian protection (cl 7.4-7.5) and flood risk and evacuation safety (cl 5.21-5.22). Local community groups and adjoining landowners will be affected by development applications and by the operation of exempt/compliant categories (cl 3.1-3.3).
Special interest sectors
Agriculture and aquaculture sectors: cl 4.2-4.2C provide specific subdivision and dwelling rules for rural zones and intensive plant agriculture; cl 5.18 and cl 5.19 (Schedule 6) set thresholds, site and operational requirements for intensive livestock and aquaculture, and identify specified small-scale activities that may be carried out without consent subject to location restrictions.
Tourism and hospitality: rules for eco-tourist facilities (cl 5.13), restrictions for farm stay and farm gate premises (cl 5.24-5.25), and the music/noise protection for licensed premises (cl 5.20) will shape business models.
Affordable housing and urban release interests: Part 6 (cl 6.1-6.3) and precinct rules such as Redmond Place (cl 7.16-7.17) impose infrastructure, staging and affordable housing obligations for defined precincts.
Financial and contractual stakeholders
Anyone contracting for development, financing a project, or taking security over land must apply the Plan’s lot size, subdivision, heritage and environmental constraints. Clause 1.9A (suspension of covenants) is particularly material to anyone depending on private covenants, because it suspends private instruments that restrict development to the extent necessary to enable development in accordance with the Plan (subject to listed exclusions and protection of public authority rights) , this affects property title rights and contractual obligations.
Who decides
The Council is the primary decision-maker on consents (cl 1.6), with specified roles for the Director-General (certification for urban release infrastructure, cl 6.1(2)) and consultation obligations to other bodies (Heritage Council, Commonwealth aviation body). The Plan itself does not create new criminal offences; it prescribes development consent pathways and matters for assessment. Enforcement, prosecutions or penalties are administered under the principal Act and regulations cited by the Plan.
Key duties and rights
Consent and assessment duties
Duty to obtain development consent where required: the Plan makes a range of activities subject to consent. Subdivision requires consent (cl 2.6); demolition requires consent (cl 2.7); temporary uses are allowed only for limited periods and subject to the consent authority’s satisfaction (cl 2.8); earthworks need consent unless exempt or ancillary (cl 7.1); many environmental and heritage impacts require consent (cl 5.10; cl 7.4-7.7).
Duty on the consent authority to consider zone objectives and specific matters: the consent authority must have regard to objectives for a zone when deciding development applications (cl 2.3(2)); in special clauses the consent authority must be satisfied of specific tests before granting consent (for example cl 5.19(2) for pond/tank aquaculture site requirements; cl 5.21 for flood‑compatible development; cl 7.9 for airspace penetrations).
Rights to carry out exempt or complying development
The Plan identifies exempt development that may be carried out without development consent if specific standards are met (cl 3.1; Schedule 2) and complying development that may be undertaken under a complying development certificate if the local and State conditions are met (cl 3.2; Schedule 3). Exempt development remains subject to other approvals under other Acts and to the Building Code (cl 3.1(3)-(5) and the Schedule 2 note).
Rights to request variations to standards
Applicants may seek consent despite contravening a development standard under cl 4.6, but must satisfy the consent authority that compliance is unreasonable or unnecessary and provide sufficient environmental planning grounds. The consent authority must keep a record of its assessment (cl 4.6(3)-(4)). Clause 4.6(8) lists development standards that cannot be varied under this clause, including standards for complying development and certain BASIX commitments.
Specific local rights and obligations
Suspension of private covenants to enable development under the Plan: cl 1.9A suspends agreements, covenants or similar instruments to the extent necessary to allow development in accordance with the Plan, but expressly excludes covenants imposed by the Council and various conservation and Crown instruments (cl 1.9A(1)-(2)). The clause preserves rights and interests of public authorities under registered instruments (cl 1.9A(3)).
Heritage procedures and conservation incentives: consent is required for demolition/alteration of heritage items (cl 5.10(2)); the consent authority may require heritage management documents (cl 5.10(5)) or conservation management plans (cl 5.10(6)); the consent authority may permit development outside the Plan to facilitate conservation if conservation work will be carried out under conditions (cl 5.10(10)).
Music and licensed premises: the Plan prohibits refusal of development to licensed premises on specified aesthetic and entertainment grounds (cl 5.20(1)), and prohibits refusal on the grounds of noise from music if the consent authority is satisfied noise can be managed to an acceptable level (cl 5.20(2)). That creates a right for licensed premises applicants to have music-related activity considered within the Plan’s management tests rather than being an automatic ground for refusal.
Infrastructure and staging obligations in urban release areas: cl 6.1 prevents granting consent for subdivision that creates smaller lots than permitted immediately before release, unless the Director‑General certifies satisfactory arrangements for designated State public infrastructure; cl 6.2 requires the Council be satisfied essential public utilities are available or arrangements made.
Affordable housing obligations in Redmond Place: cl 7.17 requires the consent authority to be satisfied the Redmond Place affordable housing principles have been considered and that at least 20% of dwellings in the Redmond Place affordable housing area will be used for affordable housing for at least 15 years and managed by a registered community housing provider.
Procedural obligations and evidentiary duties
The Plan repeatedly requires consent authorities to be satisfied of facts before granting consent (for flood compatibility cl 5.21(2), for eco-tourist facilities cl 5.13(3), for aquaculture cl 5.19(2), for intensive livestock cl 5.18(3) etc). These requirements place a duty on applicants to provide adequate supporting documentation (statements of environmental effects, EIS, heritage management documents, flood and evacuation analysis, species/site suitability materials).
For contraventions of development standards, the Environmental Planning and Assessment Regulation 2021 requires a development application to be accompanied by a document setting out the grounds relied on (note to cl 4.6). The consent authority must keep a record of its assessment under cl 4.6(4).
Limitations on rights
The Plan lists specific prohibitions: certain development is outright prohibited in particular zones (the Land Use Table); canal estate development is explicitly prohibited (cl 2.9); some kinds of development cannot be approved via cl 4.6 (cl 4.6(8)). Exempt and complying development are not available in environmentally sensitive areas identified in cl 3.3.
Rights preserved and transitional protections
A savings clause (cl 1.8A) requires that development applications made but not finally determined before the commencement of the Plan are determined as if the Plan had not commenced, and lists further savings related to particular State policies and amendments.
Recording and land title effects
The consent authority may require covenants preventing “double dipping” for floor space calculations (cl 4.5(9)-(10)). Classification and reclassification of public land is authorised under cl 5.2 and Schedule 4, and the Plan records instances where public reserves are to be discharged from trusts when reclassified (cl 5.2(5)).
In short, duties rest on applicants to identify applicable maps and clauses, supply evidence addressing the Plan’s locational and environmental tests, and on the Council to apply zone objectives and specified satisfaction thresholds. Rights include the ability to carry out exempt or complying development where criteria are met, to apply for consent despite non-compliance with a standard subject to the cl 4.6 test, and procedural protections for applications lodged before commencement.
Penalties and enforcement
The Plan itself is a statutory environmental planning instrument that sets development rules, assessment matters and local requirements; it does not, in the text provided, specify monetary penalties or criminal sanctions. Enforcement and penalties are matters handled by the Environmental Planning and Assessment Act 1979 and the regulations referenced by the Plan; the Plan repeatedly assumes the Act’s framework for development consent, designation and compliance (see the Plan’s many cross‑references to “development consent” and to the Act). Specific enforcement mechanics therefore operate as follows based on the Plan’s structure and references:
Enforcement through the Act’s consent process: the Plan makes the carrying out of various forms of development contingent on development consent (e.g. subdivision cl 2.6; demolition cl 2.7; many heritage‑sensitive acts cl 5.10). Failure to obtain consent where required will place an activity outside the Plan and the Act, which triggers the enforcement and compliance powers in the principal Act and regulation (the Plan itself does not list the enforcement powers; it relies on the Act).
Conditions and statutory records: where the consent authority grants development consent subject to conditions, compliance is monitored by the issuing authority and building/occupation certificates. The Plan enables conditions such as covenants on title to prevent re‑creation of floor area where consent authority is satisfied (cl 4.5(9)-(10)). Failure to comply with consent conditions is enforced under the Act’s compliance tools.
Referral and consultation requirements: the Plan attaches procedural duties (e.g. notify Heritage Council, notify Aboriginal communities, consult Commonwealth aviation body). Non‑compliance with those consultation duties when required could affect the validity of a consent decision and may be material in subsequent review or enforcement processes.
Statutory exclusion of some approvals: cl 3.3 excludes exempt/compliant development in environmentally sensitive areas; carrying out development that the Plan excludes in those areas without the required consent or approvals would similarly be subject to enforcement actions under the Act and related laws cited (for example fisheries, biodiversity, heritage or Crown land Acts).
Acquisition and land designation processes: cl 5.1 assigns acquiring authorities for owner‑initiated acquisition under the Land Acquisition (Just Terms Compensation) Act 1991; that Act includes its own compliance and compensation processes and timeframes.
What the Plan does not do in terms of enforcement
It does not create a new special offences schedule or bespoke penalty regime within its text. Instead it integrates with the Act and with other NSW legislation cited (Heritage Act, Rural Fires Act, Fisheries Management Act, Local Government Act, Land Acquisition Act and water Acts) which themselves carry compliance and enforcement provisions. Where the Plan directs consultation with other agencies, it leaves the enforcement mechanics to those agencies and to the principal planning Act.
Practical implication for users
Practitioners and applicants should treat the Plan as prescribing what requires consent and what cannot lawfully occur without the relevant approvals; compliance questions (including breaches) should be addressed through the Environmental Planning and Assessment Act 1979 and the other Acts the Plan references. For contentious decisions, practitioners must check whether the consent authority complied with the Plan’s consultation and notification obligations and whether any consent conditions have been imposed and enforced in accordance with the Act.
How it interacts with other laws
The Plan is drafted to operate within a network of State and Commonwealth laws. It repeatedly cross‑references the Environmental Planning and Assessment Act 1979 (the Act) and an array of other statutes whose regimes intersect with planning, environmental protection, heritage, water, Crown land management, local government, and transport. The interaction mechanisms are explicit in the Plan:
Prevailing State environmental planning policies (SEPPs) and the Act
The Plan is subject to any SEPP that prevails over it (cl 1.9(1)). This means where a SEPP contains a provision that conflicts with the Plan, the State instrument will prevail as provided by s 3.28 of the Act (cl 1.9(1) cross-refers to that principle). Practitioners must therefore check applicable SEPPs in addition to the local Plan.
Cross‑references to specialist Acts and their regulatory regimes
Heritage and Aboriginal heritage: the Plan requires consent for works affecting items on the State Heritage Register and certain Aboriginal heritage places (cl 3.1(3)(d); cl 5.10). It discharges specific notice and consultation obligations that sit alongside the Heritage Act 1977 (cl 5.10(7)-(9)).
Crown land and conservation agreements: clause 1.9A suspends private covenants for the purpose of enabling development under the Plan but excludes relevant instruments under the Crown Land Management Act 2016, conservation agreements under the National Parks and Wildlife Act 1974, Trust agreements under the Nature Conservation Trust Act 2001, property vegetation plans under Native Vegetation Act 2003 and biobanking agreements under the Threatened Species Conservation Act 1995, and excludes planning agreements under the Act (cl 1.9A(2)). This preserves the primacy of certain conservation/Crown instruments and acknowledges separate statutory regimes.
Water regimes and catchments: the Plan interacts with the Water Act 1912 and the Water Management Act 2000 in tests for intensive plant agriculture and dwelling entitlements (cl 4.2A(5A)(f)(ii) and cl 4.2B(4)(e)(i)-(ii)). Drinking water catchment protections require assessment of impacts on water quality and quantity (cl 7.7) and the Plan references the Flood Risk Management Manual and Considering Flooding in Land Use Planning Guideline for flood‑related assessments (cl 5.21(4)-(5)).
Fisheries and aquaculture: cl 5.19 ties permitting and operational criteria for pond/tank aquaculture to the Fisheries Management Act 1994 and aquaculture industry development plans, and cross‑references the NSW Oyster Industry Sustainable Aquaculture Strategy for oyster aquaculture applications (cl 5.19(5)-(6); Schedule 6).
Local Government Act: classification and reclassification of public land is implemented under the Local Government Act 1993 (cl 5.2; Schedule 4) and the Plan records the land to be classified or reclassified. The Plan relies on that Act for operational and community land categories and for trust discharge where specified (cl 5.2(1)-(5)).
Land acquisition: cl 5.1 designates the relevant State acquisition authority for owner‑initiated land acquisitions, cross‑referencing the Land Acquisition (Just Terms Compensation) Act 1991 and its processes.
Building Code and BASIX: exempt development must meet relevant deemed‑to‑satisfy provisions of the Building Code of Australia (cl 3.1(3)(a)). Clause 4.6(8) excludes BASIX certificate commitments from variation under the Plan’s exceptions clause, signalling that BASIX obligations are enforced through their own regulatory route.
Procedural interactions and consultation
The Plan requires consent authorities to notify and consider responses from external statutory bodies in particular circumstances. For archaeological sites the Heritage Council must be notified and any response must be considered (cl 5.10(7)). For Aboriginal places, local Aboriginal communities must be notified and responses considered (cl 5.10(8)). For airspace penetrations the relevant Commonwealth body must be consulted and its advice may be determinative (cl 7.9(2)-(4)).
Statutory exclusions and non‑derogation
The Plan contains clauses that preserve other statutory regimes and prevent the Plan from overriding them: e.g. cl 1.9A(3) protects public authority rights under registered instruments; cl 5.12(1) preserves the operation of State SEPP Chapter 2 (Transport and Infrastructure) for public authorities; cl 3.3 excludes exempt/compliant development in environmentally sensitive areas which are often designated under other statutes (cl 3.3(2) list).
Practical effect for compliance
Users must check the Plan alongside a matrix of external instruments: SEPPs, the Act and its regulations, the Heritage Act and Heritage Council processes, water licensing/management Acts, Crown land and national park regimes, fisheries and aquaculture plans and industry development plans, and the Local Government Act for public land classification. The Plan prescribes many of the planning thresholds and tests (e.g. for flood safety, biodiversity, heritage impact), but these tests are frequently implemented by relying on external technical guidelines and licences set by the other statutes cited (for example the Considering Flooding Guideline and the Flood Risk Management Manual referenced in cl 5.21).
In short, the Plan is not a stand‑alone code: it is designed to be applied in tandem with State policies and specialist Acts, and it embeds multiple procedural checkpoints that bring other statutory regimes into the consent decision process.
Amendment history
The Plan contains inline amendment annotations. Below are the amendments and insertions shown in the instrument text that are explicitly recorded. Each line references the clause and the amendment note as it appears in the Plan.
Clause 1.8A (Savings provision relating to development applications) , annotated: Am 2019 (621), Sch 5[1]; 2023 (609), Sch 1.1[1]. This records amendments to savings rules and a 2023 amendment noting State Environmental Planning Policy Amendment (Flood Planning) 2023 (cl 1.8A(2)).
Clause 1.9A (Suspension of covenants, agreements and instruments) , annotated: Am 2019 (621), Sch 5[2]-[4].
Clause 2.1 (Land use zones) , annotated: Am 2022 (831), Sch 1.21[1].
Land Use Table and related , note at end: multiple amendments recorded: Am 2016 (168), Sch 1 [2] [5]; 2017 (493), Sch 1.1 [1] [2]; 2019 (371), cl 4 (1)-(4); 2019 (621), Sch 3; 2021 (96), Sch 1[1]-[5]; 2022 (314), Sch 1; 2022 (831), Sch 1.21[2]; 2023 (458), Sch 2.64. This indicates a sequence of changes to the Land Use Table over several years.
Clause 4.1AA (Minimum subdivision lot size for community title schemes) , annotated: Am 2022 (831), Sch 1.21[3].
Clause 4.1A (Strata subdivisions in certain rural zones) , annotated: Am 2022 (831), Sch 1.21[3].
Clause 4.1B (Minimum lot sizes for dual occupancy, multi dwelling housing and residential flat buildings) , annotated: Am 2014 (119), Sch 1 [1]; 2015 (652), cl 5; 2025 (155), Sch 1[1]. Shows a 2025 amendment.
Clause 4.1C (Exceptions in Ploughmans Valley) , Ins 2014 (119), Sch 1 [2]; Am 2021 (96), Sch 1[6].
Clause 4.1D (Minimum lot sizes for certain split zones) , Ins 2021 (96), Sch 1[7].
Clause 4.2A (Erection of dwelling houses on land in certain rural and conservation zones) , Am 2014 (119), Sch 1 [3]; 2022 (831), Sch 1.21[3] [4].
Clause 4.2B (Rural subdivision for intensive plant agriculture) , Ins 2014 (119), Sch 1 [4]; Am 2022 (831), Sch 1.21[3].
Clause 4.2C (Subdivision in Zone C3) , Ins 2021 (96), Sch 1[8]; Am 2022 (831), Sch 1.21[3] [5].
Clause 4.6 (Exceptions to development standards) , Am 2023 (256), Sch 1[1].
Clause 5.2 (Classification and reclassification of public land) , Am 2014 (474), cl 4; 2016 (419), cl 4 (1) (2); 2016 (687), cl 5; 2018 (209), cl 5.
Clause 5.4 (Controls relating to miscellaneous permissible uses) , Am 2018 (406), Sch 1.104 [1] [2].
Clause 5.5 (Controls for secondary dwellings in rural zone) , Subst 2021 (714), Sch 11.30.
Clause 5.8 (Conversion of fire alarms) , referenced in cl 3.2 note and appended; specific amending notes not provided in the excerpt.
Clause 5.13 (Eco-tourist facilities) , no amendment note attached in excerpt.
Clause 5.20 (Standards that cannot be used to refuse consent,playing and performing music) , inserted as part of Part 5; no explicit amendment note in excerpt.
Clause 5.21 and 5.22 (Flood planning and special flood considerations) , cl 5.22 Subst 2023 (609), Sch 1.17[1]; cl 5.21 contains references to guideline documents updated 2021 and 2023 in its text; cl 5.21(2) note records update for State Environmental Planning Policy Amendment (Flood Planning) 2023 in savings clause 1.8A(2).
Part 6 (Urban release areas) cl 6.1 , Am 2019 (621), Sch 5[5]; 2023 (554), Sch 1.
Clause 7.2 and 7.2A show repeal and insertion annotations: cl 7.2 Am 2021 (96), Sch 1[9]-[11]; Rep 2021 (225), Sch 1. cl 7.2A Ins 2021 (96), Sch 1[12]; Rep 2023 (609), Sch 1.17[2].
Clause 7.3 (Stormwater management) , Am 2022 (831), Sch 1.21[6].
Clause 7.12 and 7.13 (Retail premises in Zone E1 and Commercial premises in Zone E3) , Ins 2022 (831), Sch 1.21[7].
Clause 7.14 (Use of certain land at Clergate Road and Leeds Parade) , Ins 2024 (256), Sch 1[2].
Clause 7.15 (Shiralee Hilltop Park Buffer Area) , Ins 2024 (429), Sch 1[1]; this clause has an expiry (ceases 1 August 2034).
Clause 7.16-7.17 (Redmond Place Precinct and Affordable housing) , Ins 2025 (155), Sch 1[2] and Sch 1[2] respectively.
Schedule 1 (Additional permitted uses) , amended multiple times and shows list of amendment items with years 2017, 2018, 2021, 2023, 2024, 2025 (sch 1 header annotations).
Schedule 2 and Schedule 3 amendment notes indicate changes up to 2022 (sch 2: Am 2022 (831), Sch 1.21[8][9]; sch 3 general conditions referencing State policy).
This list is a record of the amendment annotations printed in the Plan’s text as supplied. The instrument therefore has been subject to iterative amendment across many years (2014-2025 in the recorded notes). Where a clause in the Plan carries an explicit amendment annotation, practitioners should consult the made/amending instrument cited (e.g. “2022 (831), Sch 1.21[3]”) and the NSW legislation register for the final consolidated drafting history and the operative dates of each amendment.
Litigation history
The Plan text supplied does not include any judicial decisions, case citations or litigation history. No cases are named in the instrument. Where a decision under this Plan has been the subject of judicial review or merits review (for example under the Land and Environment Court or internal review processes), those decisions are not recorded in the Plan document itself. Practitioners seeking litigation history will need to search court databases, the Land and Environment Court decisions index, and case law reporters for decisions that reference Orange Local Environmental Plan 2011 or particular clauses (for example heritage, flood, biodiversity or exceptions clauses). The Plan’s text contains no explicit record of litigation or precedent.
Gotchas
Maps are operative and amendable
The Plan relies heavily on named maps for zoning, lot sizes, heights and overlays (cl 1.7; cl 2.2; cl 4.1(3); cl 4.3; cl 4.4). Map amendments that are “declared by environmental planning instruments” can change entitlements. Practitioners must check the current gateway maps on the NSW Planning Portal before advising on permitted uses, minimum lot sizes or height/FSR limits (cl 1.7(1), note).
Savings and existing DAs
Development applications lodged before commencement and not finally determined must be determined as if this Plan had not commenced (cl 1.8A(1)). That means projects in assessment at the Plan’s commencement may retain rights under the prior instrument. The 1.8A(2) specific saving for a policy amendment (Flood Planning 2023) is an additional example of transitional treatment.
Covenant suspension is limited
Clause 1.9A suspends private covenants to the extent necessary to enable Plan‑compliant development, but it excludes covenants imposed by the Council and a list of conservation and Crown instruments under other Acts (cl 1.9A(2)). It does not affect rights of public authorities under registered instruments (cl 1.9A(3)). Legal advisers should probe any covenant carefully to see whether it is caught by the exclusion list.
Exempt and complying development exclusions
Exempt/compliant development is not available in “environmentally sensitive areas for exempt or complying development” (cl 3.3(1)-(2)). Those areas include World Heritage/Ramsar sites, coastal wetlands, land identified in any environmental planning instrument as high Aboriginal cultural significance or high biodiversity significance, land reserved under the National Parks and Wildlife Act, and other specific designations (cl 3.3(2)(a)-(j)). A development that appears to be low-impact may nonetheless require consent if located in a mapped sensitive area.
Floor space “double dipping” and covenants
Floor space calculations include the gross floor area of existing buildings that fall within the vertical projection of site boundaries (cl 4.5(8)). Consent authorities may require a covenant to prevent creation of floor area on a restricted lot to “double dip” for FSR calculations (cl 4.5(9)-(10)). Parties must therefore verify prior consents, existing buildings and any covenants that might be required as a condition of consent.
Exceptions to development standards are tightly circumscribed
Clause 4.6 allows a consent authority to approve development contrary to a development standard only if the applicant shows why compliance is unreasonable or unnecessary and supplies environmental planning grounds, and the authority must keep a record of its assessment (cl 4.6(2)-(4)). The clause also lists development standards that cannot be varied under this mechanism (cl 4.6(8)), such as development standards for complying development and certain BASIX commitments. The Regulation requires specific material to be lodged with an application that seeks a variation under cl 4.6 (note to cl 4.6).
Heritage: demolition/works require consent and notifications
Consent is required for demolition or alteration of heritage items and for works affecting Aboriginal objects or places and archaeological sites (cl 5.10(2)). The Plan empowers the consent authority to require heritage management documents or conservation management plans (cl 5.10(5)-(6)) and mandates notification to the Heritage Council or local Aboriginal communities with 28‑day response windows (cl 5.10(7)-(9)). These procedural steps can delay applications and require additional consultancy inputs.
Music and licensed premises protection is conditional
Clause 5.20 forbids refusal of development for licensed premises on several specified expressive grounds (genre, live/amplified, number of musicians, dancing, stage orientation and decorations) and bans refusal on noise grounds if the consent authority is satisfied the noise can be managed and minimised to an acceptable level (cl 5.20(1)-(2)). The key risk for applicants is the evidentiary burden of demonstrating that noise will be managed to an “acceptable level” to avoid refusal under cl 5.20(2).
Flood and special flood layers impose procedural and design tests
Clauses 5.21 and 5.22 require the consent authority to be satisfied of flood compatibility, risk to life and evacuation, impacts on flood behaviour, and climate change projections; cl 5.22 adds special considerations for sensitive/hazardous development up to the probable maximum flood. The Plan expressly incorporates external guidance (Considering Flooding guideline and Flood Risk Management Manual) (cl 5.21(4)-(5)). Applicants need flood modelling and evacuation analysis; the Plan’s tests extend beyond simple floor level limits.
Local precinct controls can add unique burdens and expiries
Local clauses add precise constraints: cl 7.14 caps the number of residential lots in a particular area (700 lots); cl 7.15 (Shiralee Hilltop Park Buffer Area) imposes design and interface considerations and expires on 1 August 2034; cl 7.16 requires public open space minimum in Redmond Place and cl 7.17 requires affordable housing arrangements (20% for 15 years) in a defined area. These locationally specific rules can be overlooked unless the precise mapping is checked.
Environmental thresholds for agricultural and aquaculture operations
Intensive livestock has both matters for consideration and explicit small‑scale thresholds that may be carried out without consent provided location limits are satisfied (cl 5.18(4)-(5)). Pond and tank aquaculture have detailed site and operational requirements in Schedule 6, including conservation exclusion zones and discharge/escape controls (cl 5.19; Schedule 6). Developers in agriculture/aquaculture must satisfy both Plan rules and separate licensing regimes under fisheries/water Acts.
Some clauses are recorded as “Not adopted” or “Not applicable”
Certain clauses or subclauses are marked “[Not adopted]” or “[Not applicable]” (for example cl 5.3 Development near zone boundaries [Not adopted]; cl 5.6 Architectural roof features [Not adopted]; cl 5.7 Development below mean high water mark [Not applicable]). Practitioners must not assume uniform applicability of template clauses; the Plan records where a clause was not taken up.
These “gotchas” emphasise the need to check maps, the current consolidated Plan, local schedules, and the suite of State policies and external licensing regimes that operate in parallel.
How to comply
Start with the maps and the Land Use Table
Identify the subject land precisely on the Land Zoning Map and the Lot Size Map (cl 2.2; cl 4.1(2)-(3)). Confirm the applicable Height of Buildings Map and Floor Space Ratio Map (cl 4.3-4.4). The Plan makes these maps the primary source of numerical limits (cl 1.7). Do not advise based on memory , always check the current maps on the NSW Planning Portal as map amendments change entitlements (cl 1.7(1)-(3)).
Determine the category of development
Confirm whether the proposal is permitted without consent (Schedule 2 or Land Use Table), complying development (Schedule 3 and State policy), or requires development consent (Land Use Table; cl 2.3(1)). Exempt/compliant categories have detailed standards that must be met (cl 3.1-3.2). If the site is in an “environmentally sensitive area” mapped by the Plan, exempt/compliant pathways may be unavailable (cl 3.3).
Assess applicable overlays and specific clauses
Check Schedule 5 (heritage items and conservation areas) and cl 5.10 for consent/notification obligations. If the land is in a biodiversity overlay (Terrestrial Biodiversity Map), follow cl 7.4 and supply biodiversity assessments. If the land is within riparian zones (Watercourse Map), follow cl 7.5 and include water quality, bank stability and passage of fish considerations. For drinking water catchments, consult cl 7.7. For flood risk, apply cl 5.21 and 5.22 and use the Considering Flooding guideline and Flood Risk Management Manual as referenced.
Prepare the documentary package to address Plan tests
For development consent applications include statements and technical reports required by the Plan: heritage management documents (cl 5.10(5)), heritage conservation management plans (cl 5.10(6)), statements of environmental effects or environmental impact statements addressing intensive livestock matters (cl 5.18(3)(a)), aquaculture site and operational compliance per Schedule 6 (cl 5.19(2)), flood modelling and evacuation analysis (cl 5.21-5.22), and evidence of service availability for essential services (cl 7.11). If proposing a development that contravenes a standard, prepare the cl 4.6 justification material and the Regulation‑required document demonstrating why compliance is unreasonable or unnecessary.
Engage statutory consultees early where required
Where the Plan mandates notification or consultation, engage early: notify the Heritage Council for archaeological sites as required (cl 5.10(7)), consult local Aboriginal communities where Aboriginal heritage significance may be impacted (cl 5.10(8)), and consult the relevant Commonwealth aviation body if the proposal affects the Limitation or Operations Surface (cl 7.9(2)). For urban release infrastructure matters, obtain the Director‑General certification where needed (cl 6.1(2)).
Address service availability and infrastructure staging
For subdivisions and urban release areas check cl 6.1-6.3: do not expect consent for smaller lots unless required State infrastructure contributions or arrangements are certified (cl 6.1(2)). Ensure essential services will be available or that adequate arrangements exist (cl 6.2; cl 7.11). Prepare servicing plans for sewer, water, electricity, stormwater, and road access consistent with Part 6 and cl 7.11.
Heritage and covenants
If heritage items are present consult Schedule 5 and cl 5.10; supply heritage impact statements and prepare to submit heritage management documents or conservation plans as required. If conditions of consent may require covenants (for example to prevent double counting of FSR per cl 4.5(9)), factor such covenant registration into timing and costs.
Special local obligations (precincts and affordable housing)
For Redmond Place and similar precincts follow cl 7.16-7.17: the consent authority must be satisfied that publicly accessible open space is provided (3 ha requirement cl 7.16(2)) and that affordable housing principles are met, including management by a registered community housing provider and 20% affordable dwellings for at least 15 years (cl 7.17(4)(c)-(d)). Prepare legal instruments and management plans to secure these obligations in a way the consent authority accepts.
Technical environmental controls
For stormwater ensure designs maximise permeable surfaces and provide on‑site retention where practical (cl 7.3). For groundwater and salinity mapping areas, produce hydrogeological and salinity management plans as required (cl 7.6; cl 7.8). For riparian and watercourse impacts provide bank stability, sediment and erosion control and demonstrate no net adverse effect on flows and aquatic species (cl 7.5).
Licences and other statutory approvals
Exempt/compliant development under the Plan does not remove the need for other licences or approvals under different Acts (cl 3.1(5) note; Schedule 2 Note 2). Check fisheries, water extraction, wastewater, Crown land and other regulatory regimes early. For aquaculture, confirm species, discharge and operational compatibility with aquaculture industry development plans and the Fisheries Act/regulations (cl 5.19; Schedule 6).
Noise and entertainment management for licensed premises
If proposing licensed premises, address music/noise management up front. The Plan prevents refusal on the enumerated entertainment grounds, but the consent authority can refuse on noise grounds unless satisfied noise may be managed to an acceptable level (cl 5.20(1)-(2)). Prepare an acoustic report and a management plan that demonstrates how noise will be mitigated.
If seeking a standard variation
If seeking to rely on cl 4.6 to contravene a development standard, prepare the Regulation‑required written justification demonstrating that compliance is unreasonable or unnecessary and that there are sufficient environmental planning grounds; expect the consent authority to keep a written record of its assessment (cl 4.6(3)-(4)).
Timing, conditions and covenants
Anticipate consent conditions such as staged infrastructure provision, dedication of public land, landscape and management strategies (e.g. cl 6.3(3)(a)-(j) for development control plans in urban release areas; cl 5.13(3)(k) for eco‑tourist management strategies). Allow time and budget for registration of covenants and for third‑party agreements (utility providers, community housing providers).
Use the Plan’s own lists and definitions
Consult the Dictionary and the Schedules in the Plan for definitions such as “secondary dwelling,” “existing holding,” “environmentally sensitive area” and definitions invoked from external instruments (cl 1.4; cl 4.2A(6)). Definitions in the Plan and in cited external instruments may differ; use the Plan’s definitions where the Plan applies.
Practical checklist for counsel, planners or advisers
Step 1: Confirm current maps and zoning on the NSW Planning Portal.
Step 2: Classify the development against the Land Use Table and Schedules to identify consent pathway.
Step 3: Identify overlays (heritage, biodiversity, water, flood, drinking catchment, airspace) and applicable local clauses (e.g. precinct controls).
Step 5: If proposing standard variation, prepare cl 4.6 documentation per the Regulation.
Step 6: Engage required external consultees early and factor their timeframes into the program.
Step 7: Prepare and budget for any required covenant registration, infrastructure contributions, or management arrangements (e.g. affordable housing provision and register arrangements for 15 years under cl 7.17).
Step 8: Lodge a complete development application with the Council (consent authority), anticipating conditions and appeals/review if refused.
Following the sequence above aligns with the Plan’s structure (maps → Land Use Table → overlays/clauses → consent pathways → conditions/covenants) and targets the principal informational and documentary deficits that commonly delay consent decisions under this Plan.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Orange Local Environmental Plan 2000
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
(1) If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
(2) A development application made, but not finally determined, before the commencement of State Environmental Planning Policy Amendment (Flood Planning) 2023 must be determined as if that policy had not commenced.
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
cl 1.9A: Am 2019 (621), Sch 5[2]–[4].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
Rural Zones
RU1 Primary Production
RU5 Village
Residential Zones
R1 General Residential
R2 Low Density Residential
R3 Medium Density Residential
R5 Large Lot Residential
Employment Zones
E1 Local Centre
E2 Commercial Centre
E3 Productivity Support
E4 General Industrial
Mixed Use Zones
MU1 Mixed Use
Special Purpose Zones
SP2 Infrastructure
SP3 Tourist
Recreation Zones
RE1 Public Recreation
RE2 Private Recreation
Conservation Zones
C1 National Parks and Nature Reserves
C2 Environmental Conservation
C3 Environmental Management
C4 Environmental Living
cl 2.1: Am 2022 (831), Sch 1.21[1].
2 Zoning of land to which Plan applies
2 Zoning of land to which Plan applies
2.2 Zoning of land to which Plan applies
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate m