Offshore Petroleum and Greenhouse Gas Storage (Resource Management and Administration) Regulations 2025
52Objection to requirement for varied field development plan
Start here
Get a plain-English read of 52
Turn the raw legal text into a practical explanation grounded in Offshore Petroleum and Greenhouse Gas Storage (Resource Management and Administration) Regulations 2025.
52 Objection to requirement for varied field development plan
(1) If the Titles Administrator gives a petroleum production licensee a notice under section 51 requiring the licensee to vary an accepted field development plan, the licensee may give an objection, in writing, to the Titles Administrator:
(a) stating either or both of the following:
(i) that the licensee should not be required to vary the accepted varied field development plan;
(ii) that the accepted field development plan should be varied differently to how the Joint Authority requires the accepted field development plan to be varied; and
(b) giving reasons for the objection.
(2) The licensee must give the objection to the Titles Administrator:
(a) within 21 days after receiving the notice; or
(b) if the Titles Administrator agrees, in writing, to a longer period—within that longer period.