41 Application for acceptance of field development plan
(1) A person (the FDP applicant) may apply to the Titles Administrator for the acceptance of a field development plan by the Joint Authority, if the FDP applicant is:
(a) a petroleum production licensee; or
(b) an applicant for a petroleum production licence.
(c) be accompanied by the field development plan.
(3) The Titles Administrator must publish on the Titles Administrator’s website any form approved for the purposes of paragraph (2)(b).
(4) For the purposes of paragraph (2)(c), an application under this section is taken to be accompanied by a field development plan if the plan is given to the Titles Administrator before the end of the 10 day period that began on the day after the application was made.
Amendment of submitted field development plan before decision
(5) At any time before the Joint Authority makes a decision on a field development plan under section 43, the FDP applicant may:
(a) amend the application or plan; and
(b) resubmit the application and plan in accordance with subsection (2) of this section.
(6) If an FDP applicant amends and resubmits a field development plan under subsection (5), a reference in this Division to the field development plan is a reference to the plan as amended.