247 Notice to submit variation of field development plan
If:
(a) under regulation 4.11 of the old regulations, the Titles Administrator had given a petroleum production licensee a notice advising the licensee that the Joint Authority requires the licensee to vary a field development plan; and
(b) the licensee had not submitted a variation of the plan before the commencement day; and
(c) the notice had not been withdrawn before the commencement day;
the notice is taken to have been given by the Titles Administrator under section 51 of this instrument.
248 Applications for variations of field development plans submitted before commencement day to be dealt with under old regulations
If:
(a) a petroleum production licensee applied for the acceptance of a variation of a field development plan under regulation 4.08 of the old regulations before the commencement day; and
(b) the Joint Authority had not decided before the commencement day to either accept or reject the variation; and
(c) the licensee had not withdrawn the application before the commencement day;
the Joint Authority must deal with the proposed revision under the old regulations.