332 Notice of route followed by pipeline
A pipeline licensee who constructs a pipeline in the offshore area must inform both the Minister and the Australian Hydrographic Office, in writing, of the exact route followed by the pipeline by the earlier of—
(a) 14 days after the day on which construction of the pipeline is completed; and
(b) the day before the pipeline is operated.