27Checking completeness of submitted environment plan
Start here
Get a plain-English read of 27
Turn the raw legal text into a practical explanation grounded in Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2023.
27 Checking completeness of submitted environment plan
Within 5 business days after an environment plan is submitted to NOPSEMA under section 26, resubmitted in response to an invitation under section 29 or resubmitted under subsection 31(2), NOPSEMA must decide provisionally whether the plan includes material apparently addressing all the provisions of Division 2 (Contents of an environment plan).
Note: The provisional decision is not a decision whether to accept the plan.