Offshore Electricity Infrastructure Regulations 2022
90Plan must address removal of relevant structures, equipment and property, and remediation
Start here
Get a plain-English read of 90
Turn the raw legal text into a practical explanation grounded in Offshore Electricity Infrastructure Regulations 2022.
90 Plan must address removal of relevant structures, equipment and property, and remediation
(1) The plan must describe how relevant structures, equipment and property in relation to the relevant licence are to be removed from the licence area if: (a) they are neither used nor intended to be used in connection with the activities: (i) in which the licence holder is or will be engaged; and (ii) that are authorised or required by or under the Act; and (b) section 116 of the Act (subject to subsection (6) of that section) requires them to be removed from the licence area.
Note: See also paragraph 74(3)(e) of the Act (about how equipment and other property is to be dealt with before a licence may be surrendered).
(2) The plan must describe how the licence area is to be remediated in relation to the removal of relevant structures, equipment and property. (3) The plan must require the licence holder to give effect to: (a) provisions included in the plan under subsection (1); and (b) any arrangements set out in the plan under subsection (2).
Note 1: In considering whether to approve the plan, the Regulator must have regard to the stage that the offshore infrastructure project is at (see paragraph 72(2)(c)). This may result in the matters included in the plan under this section becoming more detailed as the project progresses.
Note 2: A significant change in the relevant structures, equipment or property may result in the plan needing to be revised (see paragraph 60(2)(b)), and the matters addressed in the plan under this section may need to be updated.