Offshore Electricity Infrastructure Regulations 2022
48Requirements for application
Start here
Get a plain-English read of 48
Turn the raw legal text into a practical explanation grounded in Offshore Electricity Infrastructure Regulations 2022.
48 Requirements for application
(1) An initial plan approval application: (a) must be made in the manner and form that is: (i) approved by the Regulator; and (ii) published on the Regulator’s website; and (b) must be accompanied by the plan; and (c) must be accompanied by any other information or documents required by the form. (2) Before making an initial plan approval application, a licence holder must carry out consultation under Subdivision D.
Note 1: For application fees, see section 146. An application is taken to have been made only if the fee for dealing with the application has been paid (see section 147).
Note 2: The licence holder may be required to give the Regulator a design notification before making the initial plan approval application (see section 96).