These regulations define which activities count as “building services work” and which are excluded, and set licensing duties, notification and 10‑year record‑keeping requirements, owner‑builder eligibility, fees and infringement penalties.
They affect licensed individuals, licensed entities, owner‑builders and councils: licensees pay prescribed fees, must notify specified changes and retain records; non‑compliance attracts fines or infringement notices. The rules rely on cross‑references to the Occupational Licensing Act, the Building Acts and plumbing regulations, creating identifiable compliance and administrative burdens.
These regulations prescribe which kinds of building services work are captured by the Occupational Licensing Act 2005 regime, set fees and infringement penalties, impose notification and record-keeping obligations on licence-holders and owner builders, and make a number of detailed exclusions and procedural rules. Mechanically the instrument does the following.
Identifies work to be treated as prescribed building services work for the purposes of the Act by bringing Schedule 1 Part 1 work within the Act (regulation 4(2)), while excluding certain work listed at Schedule 1 Part 2 from the Act (regulation 4(3)). It also prescribes certain classes of building services work as building services work for the definition in the Act subject to specific carve outs (regulation 4(4)).
Requires licence-holders to notify the Administrator in writing of specified changes within 21 days, with distinct lists and distinct penalties for natural persons and licensed entities (regulation 5(1)-(2)).
Imposes a record-keeping duty on building services providers to retain records in an approved form for at least 10 years after the work is completed, and defines when work is taken to be completed by cross-reference to completion events under the Building Act 2000 and Building Act 2016 or the last attendance or contract termination in other cases (regulation 6(1)-(2)).
Declares that, for the purposes of section 25(2A) of the Act, all building services work is prescribed (regulation 8).
Sets prescribed criteria for who may hold an owner builder permit, including ownership, intent to manage or carry out the work, limits on prior owner builder authorisations in the previous 10 years, and exclusions for certain classes of building (regulation 9; regulation 10).
Current sections
Direct links to the current provisions in Occupational Licensing (Building Services Work) Regulations 2016.
building services work determination means the determination, made under section 30 of the Act, as amended from time to time, in respect of –
(a) building services work; and
(b) the classes of building services work; and
(c) any details relating to the classes of building services work;
specified fee means a fee specified in Schedule 2 .
(2) Unless the contrary intention appears, an expression used in these regulations that is defined in the building services work determination has the same meaning in these regulations as in that determination.
Part 2
Building Services Work
Part 2 Building Services Work
4
Prescribed work
4 Prescribed work
(1) In this regulation –
site plan means a plan of a site, showing site features, boundaries, orientation and access, existing or proposed structures and distribution of services, together with the location of a proposed structure or of proposed work.
(2) For the purposes of the definition of prescribed work in section 3(1) of the Act, work specified in Part 1 of Schedule 1 is determined to be prescribed work, unless exempted under section 99(1)(b) of the Act.
(4) Work referred to in subregulation (2) is prescribed as building services work for the purposes of paragraph (a) of the definition of building services work in section 3(1) of the Act unless –
(a) excluded from the application of the Act under subregulation (3) ; or
(c) the work is the preparation of a site plan, or as-constructed plan, in relation to work, or in association with work, carried out by a plumber practitioner (certifier), within the meaning of the Occupational Licensing (Plumbing Work) Regulations 2010 , working within his or her area of competence; or
(d) the work is the preparation of a site plan in relation to work performed on, or in association with work performed on, Class 10 buildings or Class 7b farm buildings.
5
Administrator to be notified of changes
5 Administrator to be notified of changes
(1) The holder of a building services licence that is not a licensed entity must notify the Administrator in writing within 21 days after any change to the following information:
(a) his or her name;
(b) his or her residential address;
(c) a telephone or fax number used in connection with the licence;
(d) an email address used in connection with the licence.
Penalty: In the case of –
(a) a body corporate, a fine not exceeding 25 penalty units; or
(b) a natural person, a fine not exceeding 10 penalty units.
(2) The holder of a building services licence that is a licensed entity must notify the Administrator in writing within 21 days after a change to the following information, if applicable:
(a) the name of the licensed entity;
(b) a registered business name used in connection with the licence;
(c) a person who is a director or partner of the licensed entity, or a person who is a licensed person for a municipal council;
(d) the address of the holder's registered office;
(e) the address of the holder's principal place of business;
(f) a telephone or fax number used in connection with the licence;
(g) an email address used in connection with the licence.
Penalty: Fine not exceeding 25 penalty units.
6
Records of building services work
6 Records of building services work
(1) A building services provider must keep, for at least 10 years after the work is completed, records, in an approved form, of all building services work, undertaken by the building services provider.
Penalty: In the case of –
(a) a body corporate, a fine not exceeding 50 penalty units; or
(b) an individual, a fine not exceeding 25 penalty units.
(2) For the purposes of this regulation, building services work is completed –
(a) if the building services work is building work or demolition work, other than low-risk work, within the meaning of the Building Act 2016 , on the earlier of the following days:
(i) the day on which a certificate of completion is issued under that Act in respect of the work;
(ii) the day on which the contract to perform the building work, or demolition work, is terminated; or
(b) if the building services work is building work that is covered by a building permit issued under the Building Act 2000 , on the earlier of the following days:
(i) the day on which a certificate of completion is issued under that Act, or the Building Act 2016 , in respect of the work;
(ii) the day on which the contract to perform the building work, or demolition work, is terminated; or
(c) if the building services work is building work that is not covered by paragraph (a) or (b) , on the earlier of the following days:
(i) the day on which the work is last attended to by the building services provider;
(ii) the day on which the contract to perform the building services work is satisfied by both parties to the contract or terminated; or
(d) if the buildings services work is not building work, on the earlier of the following days:
(i) the day on which all of the building services provider's statutory obligations in respect of the work under the Building Act 2000 , or the Building Act 2016 , are discharged;
(ii) the day on which his or her engagement as a building services provider in respect of the work ceases under the Building Act 2000 or the Building Act 2016 .
For the purposes of section 25(2A) of the Act, all building services work is prescribed.
Part 3
Owner Builders
Part 3 Owner Builders
9
Prescribed criteria
9 Prescribed criteria
(1) In this regulation –
building authority includes an authority allowing an accredited building practitioner to carry out or manage building work under the Building Act 2000 , and a building services licence.
(2) For the purposes of section 29B(1)(a) of the Act, the prescribed criteria for a person to hold an owner builder permit are –
(a) the person is a natural person; and
(b) the person owns the premises in respect of which the work to be performed under the proposed permit relates; and
(c) the person intends, or another owner builder in respect of the premises intends, to carry out or manage the building work on the premises under the authority of the proposed permit, whether or not that work has commenced before the proposed permit is issued; and
(d) the person does not intend, or another owner of the premises does not intend, to perform permit demolition work, or notifiable demolition work, within the meaning of the Building Act 2016 , under the authority of the proposed permit; and
(e) [Regulation 9 Subregulation (2) amended by No. 39 of 2018, s. 54, Applied:01 Jan 2017] other than building work carried out or managed under a building authority, the person and each other owner of the premises, in aggregate, have not already carried out or managed building work, under an authorisation as an owner builder, on 2 or more buildings in the 10 years immediately before the person made the application for the proposed permit; and
(f) each other owner of the premises meets the prescribed criteria set out in paragraphs (a) , (b) , (c) , (d) and (e) .
10
Owner builder permit not required
10 Owner builder permit not required
A person does not require an owner builder permit under this Part if the person intends to manage or carry out building work –
(a) that is excluded work under items 1 or 2 of Part 2 of Schedule 1 ; or
(b) in respect of a Class 7b farm building.
11
Obligation to hold insurance, &c.
11 Obligation to hold insurance, &c.
For the avoidance of doubt, an obligation under the Act in respect of a person performing work as an owner builder is in addition to, and not limited by, any obligation in respect of that person that he or she would be required to meet if performing the work other than as an owner builder.
Part 4
Miscellaneous
Part 4 Miscellaneous
Division 1
Fees
Division 1 Fees
12
Fees generally
12 Fees generally
(1) In this regulation –
GST has the same meaning as in the A New Tax System (Goods and Services Tax) Act 1999 of the Commonwealth.
(a) are inclusive of any GST that may be payable in respect of those fees; and
(b) are prescribed as the fees payable to the Administrator in respect of the matter to which they relate.
(3) If an application under these regulations for the issue of a licence is refused, any annual or triennial fee paid in respect of the issue of the licence is to be refunded to the person who paid the fee.
13
Licence fees
13 Licence fees
A person applying for the issue of a building services licence must pay the fee specified in Schedule 2 for that licence.
14
Additional occupations
14 Additional occupations
In addition to any other specified fee required to be paid, a person intending to apply for, or to renew, a licence in respect of more than one occupation must pay, on application, the fee specified in Schedule 2 for each additional occupation to be included, or renewed, on the licence.
15
Owner builder permit fees
15 Owner builder permit fees
A person applying for the issue of an owner builder permit under these regulations must pay the application fee specified in Schedule 2 for that permit.
(a) an offence against a provision of the Act specified in column 1 of the table in Part 1 of Schedule 3 is prescribed as an offence for which an infringement notice may be issued; and
(b) an offence against a provision of these regulations specified in column 1 of the table in Part 2 of Schedule 3 is prescribed as an offence for which an infringement notice may be issued.
(2) A penalty specified in column 2 of a table in Part 1 or 2 of Schedule 3 is prescribed as the penalty for a body corporate for the relevant offence specified in column 1 of the relevant table.
(3) A penalty specified in column 3 of a table in Part 1 or 2 of Schedule 3 is prescribed as the penalty for a natural person for the relevant offence specified in column 1 of the relevant table.
(4) If an infringement notice is served under section 62 of the Act and is not withdrawn, the authorised officer serving the infringement notice is to forward a copy of the notice to the Administrator.
SCHEDULE 1 - Building services
SCHEDULE 1 - Building services work
SCHEDULE 1 - Building services SCHEDULE 1 - Building services work
| | Provision of Act or regulations | Matter | Fee units |
| 1. | Section 45 | Issue of replacement certificate of identification | 25 |
| 2. | Section 29C(c) | Fee for owner builder permit – | |
| | | (a) if work intended to be performed under the permit by the holder of the permit involves work on a Class 1a or 1b building; or | 240 |
| | | (b) if work intended to be performed under the permit by the holder of the permit does not involve work on a Class 1a or 1b building | 120 |
| 3. | Regulation 12 | Annual fee for building services licence in respect of an individual or licensed entity except the occupation of architect | 240 |
| 4. | Regulation 12 | Annual fee for building services licence in respect of an individual or licensed entity for the occupation of architect | 195 |
| 5. | Regulation 12 | Triennial fee for building services licence in respect of an individual or licensed entity except the occupation of architect | 645 |
| 6. | Regulation 12 | Triennial fee for building services licence in respect of an individual or licensed entity for the occupation of architect | 525 |
| 7. | Regulation 14 | Fee for each additional occupation to be included on a licence | 120 |
Sourced from Tasmanian Legislation Online (legislation.tas.gov.au), CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
1 Short title
1 Short title
These regulations may be cited as the Occupational Licensing (Building Services Work) Regulations 2016 .
2 Commencement
2 Commencement
These regulations take effect on the day on which the Occupational Licensing Amendment Act 2016 commences.
3 Interpretation
3 Interpretation
(1) In these regulations –
Act means the Occupational Licensing Act 2005 ;
building services work determination means the determination, made under section 30 of the Act, as amended from time to time, in respect of –
(a) building services work; and
(b) the classes of building services work; and
(c) any details relating to the classes of building services work;
specified fee means a fee specified in Schedule 2 .
(2) Unless the contrary intention appears, an expression used in these regulations that is defined in the building services work determination has the same meaning in these regulations as in that determination.
Part 2 Building Services Work
Part 2 Building Services Work
4 Prescribed work
4 Prescribed work
(1) In this regulation –
site plan means a plan of a site, showing site features, boundaries, orientation and access, existing or proposed structures and distribution of services, together with the location of a proposed structure or of proposed work.
(2) For the purposes of the definition of prescribed work in section 3(1) of the Act, work specified in of is determined to be prescribed work, unless exempted under of the Act.
Prescribes fees and the treatment of GST for fees, specifies the fee units for licences, owner builder permits and additional occupations in Schedule 2, provides for refund of licence fees if an application is refused (regulations 12-15, Schedule 2), and makes an exemption for councils in respect of licences enabling them to act as permit authorities (regulation 15A).
Grants power to issue infringement notices for a list of offences under the Act and these regulations, and prescribes the penalty units for body corporates and natural persons in Schedule 3, and requires authorised officers to forward copies of served infringement notices to the Administrator (regulation 16).
The regulations therefore create compliance rules, reporting obligations, and financial consequences that affect licence-holders, owner builders, licensed entities, councils, and building services providers. The text cross-references the Building Act 2000, Building Act 2016, the Occupational Licensing (Plumbing Work) Regulations 2010, and the building services work determination made under section 30 of the Act (regulation 3(1)-(2)). The instrument also contains amendment notes and rescissions in the marginal notes for several provisions.
Main concepts
The regulations rest on a set of core definitional and structural concepts that determine scope and duties. Understanding these is necessary to apply the substantive obligations.
Building services work, prescribed work and excluded work. Regulation 3 defines that expressions used in the regulations that are defined in the building services work determination have the same meanings here (regulation 3(2)). Regulation 4 and Schedule 1 operate together. Schedule 1 Part 1 lists the types of work determined to be prescribed work for the Act: building or demolition work (item 1), design work (item 2) and assessment or certification work (item 3). Schedule 1 Part 2 lists excluded work, notably low-risk work as defined in the Building Act 2016 and work not required by that Act to be performed by a licensed builder (Schedule 1 Part 2 items 1 and 2).
Interplay with building legislation and plumbing regulations. The definition of when work is "completed" for record-keeping purposes depends on statutory completion events in the Building Act 2000 and the Building Act 2016 (regulation 6(2)(a)-(b)). Regulation 4(4) contains explicit carve outs where design work or site plans prepared by a plumber practitioner (certifier) within the scope of the Occupational Licensing (Plumbing Work) Regulations 2010 are not treated as prescribed building services work.
Administrator. Several operational duties reference the Administrator. Licence-holders must notify the Administrator of specified changes (regulation 5). An authorised officer who serves an infringement notice must forward a copy to the Administrator (regulation 16(4)). The regulations do not detail the Administrator’s broader licensing functions (these sit in the Act), but they create reporting flows to that office.
Notification and record-keeping duties. Licence-holders who are natural persons must notify four kinds of personal contact or identifying detail changes (regulation 5(1)(a)-(d)), while licensed entities must notify a broader set of corporate details (regulation 5(2)(a)-(g)). Building services providers have a 10-year records retention obligation for records kept in an approved form (regulation 6(1)). The regulations define completion triggers with multiple scenarios across building permit regimes so that retention periods begin from specific statutory milestones or the last attendance/contract termination where statutory milestones are absent (regulation 6(2)).
Owner builder regime. Regulation 9 lists the prescribed criteria for an owner builder permit, including natural person status, ownership of premises, intent to carry out or manage the work, limits on prior owner builder authorisations in the preceding 10 years (no more than 2), and that permit demolition or notifiable demolition work will not be performed (regulation 9(2)(a)-(f)). Regulation 10 specifies cases where an owner builder permit is not required.
Fees and penalty units. Regulation 12 clarifies that fees listed in Schedule 2 are inclusive of GST and are payable to the Administrator. Schedule 2 itemises fee units for a range of matters including licence annual and triennial fees, owner builder permit fees and fees for additional occupations. Schedule 3 lists infringement notice penalty units for specified offences under both the Act and these regulations (regulation 16).
These concepts create the structure through which the occupational licensing regime governs who must be licensed, what work is captured, what records and notifications must be made, the financial obligations for licences, and the administrative enforcement via infringement notices.
Who it affects
The regulations affect several categories of actors within the building and construction regulatory ecosystem, with different obligations and costs for each class.
Building services providers and licence-holders. Anyone who holds a building services licence or who provides building services work as defined in Schedule 1 Part 1 will be subject to the record-keeping requirement (regulation 6(1)), the duty to notify the Administrator of specified changes (regulation 5), and will be liable to infringement notices for relevant contraventions listed in Schedule 3 and under the Act (regulation 16). The duties apply both to individuals and corporate licence-holders, but penalties differ by entity type (see Schedule 3 and the penalty clauses in regulation 5).
Licensed entities and bodies corporate. Licensed entities must notify a broader set of corporate changes (regulation 5(2)), and face the higher corporate penalty caps specified for notification defaults (penalty up to 25 penalty units for a licensed entity, regulation 5(2)). Corporate entities also face the body corporate penalty units listed in Schedule 3 for the listed Act and regulation offences.
Natural persons. Individuals holding licences must notify personal contact changes within 21 days (regulation 5(1)) and are subject to lower penalty unit levels for infringements and notification failures than bodies corporate. Individuals providing building services are subject to the 10-year records retention duty and its lower listed maximum fine for individuals (regulation 6(1)(b)).
Owner builders and prospective owner builder permit-holders. Regulation 9 prescribes criteria that must be met to hold an owner builder permit. Natural persons who own premises and intend to carry out or manage building work fall within the owner builder regime, but they are subject to limits: the aggregate of the person and other owners must not have previously carried out or managed building work as an owner builder on two or more buildings in the prior 10 years (regulation 9(2)(e)). Owner builders must pay application fees as per Schedule 2 item 2 (regulation 15).
Plumbers acting as certifiers. The regulations explicitly preserve certain design and site-plan work performed by plumber practitioners (certifiers) within their competence under the Occupational Licensing (Plumbing Work) Regulations 2010 from being treated as prescribed building services work in certain circumstances (regulation 4(4)(b) and (c)). That limits the capture of some plumbing design work by these building services regulations.
Councils. Councils that obtain building services licences to enable them to perform the functions of a permit authority under the Building Act 2016 are exempt from fees under this Division by regulation 15A. That reduces the financial burden on councils acting in a statutory permit authority capacity.
Parties involved in building certification, assessment and design. Schedule 1 Part 1 itemises design, assessment and certification activities as prescribed work. Architects, engineers, specialist assessors and certifiers are therefore affected when they perform the listed activities in relation to buildings or building work. Schedule 2 clarifies that the occupation of architect attracts lower annual and triennial fee units than other occupations (Schedule 2 items 3-6).
Persons undertaking low-risk or investigatory work. The excluded work list in Schedule 1 Part 2 exempts low-risk work as defined in the Building Act 2016, and work performed for the purposes of providing a certificate under section 321 of the Building Act 2016. Those performing such work are outside the licensing duties under these regulations where the exclusions apply.
In effect, the regulations allocate compliance costs, notification obligations and financial charges across individual practitioners, businesses, owner builders, plumbers acting as certifiers, councils and specialist design and certification professionals, with specific differences by entity type and by the class of work performed.
Key duties and rights
The regulations create several specific duties and a small number of rights tied to licences and owner builder permits. These interact with the Act and external building legislation.
Key duties
Notification duty. Holders of building services licences must notify the Administrator in writing within 21 days of particular changes. For individual licence-holders the list is name, residential address, telephone/fax number used for the licence and email address (regulation 5(1)(a)-(d)). For licensed entities the list extends to the entity name, registered business name, directors or partners, registered office address, principal place of business, telephone/fax and email address (regulation 5(2)(a)-(g)). Penalties for non-compliance are set in regulation 5: up to 25 penalty units for bodies corporate and lesser fines for natural persons in some cases (regulation 5(1) penalty table).
Records retention. A building services provider must keep, for at least 10 years after the work is completed, records in an approved form of all building services work undertaken by the provider (regulation 6(1)). The regulation prescribes different triggers for when work is completed depending on the statutory regime applicable to the work: completion certificate issue or contract termination under the Building Act 2016 or Building Act 2000, last attendance in non-permit scenarios, or discharge of statutory obligations where the work is not building work (regulation 6(2)(a)-(d)).
Owner builder criteria and obligations. Applicants for owner builder permits must meet the prescribed criteria in regulation 9(2), including being a natural person, owning the premises, intending to carry out or manage the work, not intending to perform permit or notifiable demolition work, and not having, in aggregate with other owners, managed owner-builder work on two or more buildings in the previous 10 years (regulation 9(2)(a)-(f)). The regulations also make clear that obligations under the Act on owner builders are in addition to other obligations that would apply to a person performing work other than as an owner builder (regulation 11).
Fees payment. Applicants for licences and owner builder permits must pay the relevant fee specified in Schedule 2, which are expressed in fee units and are declared to be inclusive of GST (regulation 12(2), regulation 13, regulation 15, Schedule 2). A person applying for multiple occupations must pay an additional occupation fee for each extra occupation requested (regulation 14, Schedule 2 item 7). The regulations provide for refund of annual or triennial fees if an application is refused (regulation 12(3)).
Infringement notice regime. The regulations prescribe a set of offences under the Act and the regulations that may be the subject of infringement notices, and prescribe the penalty unit amounts for corporate and natural persons (regulation 16(1)-(3), Schedule 3). An authorised officer serving an infringement notice must forward a copy of the notice to the Administrator (regulation 16(4)).
Rights and administrative features
Fee refund entitlement. If an application for a licence under these regulations is refused, any annual or triennial fee paid in respect of the issue of the licence must be refunded to the person who paid the fee (regulation 12(3)). That creates a financial protection for unsuccessful applicants.
Fee inclusions. Fees in Schedule 2 are stated to be inclusive of any GST that may be payable (regulation 12(2)(a)). That provides determinacy to applicants about the total fee burden in fee units.
Council exemption from fees. Regulation 15A provides that a fee is not payable under the Division in respect of a building services licence issued to a council to enable it to perform the functions of a permit authority under the Building Act 2016. That is a specific statutory relief requiring no separate application where the council holds a licence for that purpose.
The regulations primarily create obligations rather than positive rights. Rights that do appear are limited and procedural, for example the fee refund where an application is refused. The duties are enforceable with monetary penalties set as penalty unit amounts and via infringement notices as specified in Schedule 3.
Penalties and enforcement
The regulations set out the monetary enforcement framework by specifying which offences can be issued by infringement notice and the penalty unit amounts that apply to bodies corporate and natural persons. They also attach monetary fines to particular regulatory failures.
Infringement notice regime
Regulation 16 prescribes that certain offences under the Act and under these regulations can be the subject of infringement notices (regulation 16(1)). The relevant offence lists are contained in Schedule 3 Part 1 for offences under the Act and Schedule 3 Part 2 for offences under the regulations (regulation 16(1)(a)-(b)).
Schedule 3 lists specific sections of the Act and specific regulations, and specifies the penalty unit amounts for body corporates (column 2) and natural persons (column 3). For example, contravention of section 25(2A) of the Act attracts an infringement penality of 20 penalty units for a body corporate and 10 penalty units for a natural person (Schedule 3 Part 1 row 11). Under the regulations, failure to comply with regulation 6 (records retention) attracts 20 penalty units for a body corporate and 10 for a natural person (Schedule 3 Part 2 row 2).
An authorised officer who serves an infringement notice must forward a copy of the notice to the Administrator unless the notice is withdrawn (regulation 16(4)). This creates an enforcement reporting flow to the Administrator.
Direct fines in regulations
Regulation 5 contains explicit penalties for failing to notify the Administrator of changes. For holders of a building services licence that is not a licensed entity, failure to notify the specified personal changes within 21 days carries a penalty: for a body corporate a fine not exceeding 25 penalty units, for a natural person a fine not exceeding 10 penalty units (regulation 5(1) penalty table). For licensed entities, the prescribed penalty for failing to notify within 21 days is a fine not exceeding 25 penalty units (regulation 5(2) penalty).
Regulation 6(1) prescribes the records duty and attaches maximum fines: for a body corporate a fine not exceeding 50 penalty units, and for an individual a fine not exceeding 25 penalty units if the duty is breached (regulation 6(1) penalty table). This is separate from the infringement notice regime in Schedule 3.
Mechanics and administrative practice
The regulations do not specify investigative powers, timeframes for enforcement action, appeal rights or remission options in the text itself. Those procedural details will be found in the Act or in administrative policies of the Administrator and authorised officers. The regulations do impose a duty on the authorised officer to forward a served infringement notice to the Administrator (regulation 16(4)), which will create centralised records of enforcement action.
Monetary penalties are expressed in penalty units. The regulations and schedules specify penalty unit amounts, but do not convert fee units or penalty units into dollar amounts. Users therefore must consult the applicable penalty unit value as prescribed elsewhere in law to convert these figures into monetary sums.
From the instrument it follows that enforcement is primarily monetary and administrative, channelling breaches into either infringement notices under Schedule 3 or the fines attached to specific regulations. The distribution of penalty unit amounts differentiates between corporate and natural person liability and reflects higher fines for corporate entities in many instances.
How it interacts with other laws
The regulations are interlaced with the Occupational Licensing Act 2005 and the building regulatory framework. The text explicitly cross-references several statutes and subordinate instruments; those linkages shape scope, timing and duties.
Primary statutory interaction
Occupational Licensing Act 2005. These regulations operate under and for the purposes of the Act. They determine which building services work is prescribed for the Act (regulation 4(2)). They also implement section-specific provisions, such as prescribing building services work for the purposes of section 25(2A) of the Act (regulation 8), and providing the fee and infringement notice architecture to operate alongside the Act (regulations 12 and 16).
Building Act 2016 and Building Act 2000. The regulations rely on the Building Acts to define exclusions and completion events. Schedule 1 Part 2 excludes work that is low-risk as defined in the Building Act 2016 and work not required to be performed by a licensed builder under that Act (Schedule 1 Part 2(1)). Regulation 6(2) defines when building services work is completed by reference to the issue of completion certificates under the Building Act 2016 or Building Act 2000, and by reference to statutory obligations under those Acts being discharged (regulation 6(2)(a)-(d)). The intended effect is to align record-retention triggers with building permit and completion regimes established in the Building Acts.
Occupational Licensing (Plumbing Work) Regulations 2010. Regulation 4(4)(b)-(c) excludes certain design work and site-plan preparation carried out by plumber practitioners (certifiers) working within their area of competence under the Plumbing Work Regulations from being prescribed building services work under these regulations. This preserves a degree of regulatory separation for certified plumbing activities.
Architects Act 1929. Schedule 2 uses the defined term architect for fee differentiation, referencing the Architects Act 1929 for meaning (Schedule 2, interpretation). Schedule 2 also sets lower fee units for licences in respect of the occupation of architect (Schedule 2 items 4 and 6).
A New Tax System (Goods and Services Tax) Act 1999. The regulations declare that GST has the same meaning as in the Commonwealth GST Act for the purposes of the fee provisions (regulation 12(1)). Regulation 12(2)(a) then states the fees in Schedule 2 are inclusive of any GST that may be payable.
Administrative and publication links
Rules Publication Act 1953. The instrument notes that the schedules are displayed and numbered in accordance with the Rules Publication Act 1953 (concluding note), which governs how the instrument is published and authenticated.
Building services work determination under section 30 of the Act. Regulation 3(1) includes "building services work determination" as the determination made under section 30 of the Act and says expressions defined in that determination carry the same meaning in these regulations (regulation 3(2)). This gives the determination authority to populate technical definitions used in the regulations.
Practical implications of these interactions
Timing and retention windows are driven by the building permit/completion framework in the Building Acts, which may differ if work falls under the Building Act 2000 or Building Act 2016 regimes; regulation 6(2) lists both. Where no statutory certificate exists, ordinary contractual or attendance-based triggers apply.
The exclusion for plumber practitioners operating within their competence under the Plumbing Work Regulations means that certain plumbing design and site-plan tasks will remain governed by the plumbing regulatory framework rather than by the building services licensing regime here, limiting regulatory duplication in those circumstances.
Fee and penalty amounts are stated in unit terms and GST-inclusive, so monetary conversions require consulting the current statutory value of a penalty unit and any fee unit conversion rules in force elsewhere.
Overall, the regulations are an implementing instrument that aligns the occupational licensing regime with existing building permit and plumbing certification frameworks, while delegating definitional and technical detail to a building services work determination and to the Building Acts.
Amendment history
The regulations include marginal amendment notes that record certain changes. The instrument also contains provisions that will commence in tandem with associated amending Acts. The following items are recorded in the text provided.
Commencement linkage. Regulation 2 specifies that these regulations take effect on the day on which the Occupational Licensing Amendment Act 2016 commences (regulation 2). The instrument therefore ties its operative start to the commencement of an amending Act.
Regulation 7 rescission. The text contains a marginal note indicating that Regulation 7 was rescinded by S.R. 2016, No. 112, applied 01 Jan 2019. The marginal note is: "[Regulation 7 Rescinded by S.R. 2016, No. 112, Applied:01 Jan 2019]" beneath the heading for regulation 7. The substantive text for regulation 7 is not present because it was rescinded.
Regulation 9 amendment. Regulation 9 contains a marginal note indicating that subregulation (2) was amended by No. 39 of 2018, s. 54, applied 01 Jan 2017. The text of regulation 9 includes that amendment note attached to paragraph (e) of regulation 9(2). This amendment adjusted the owner builder eligibility rule (the printed text includes the amended wording that the person and each other owner, in aggregate, have not carried out or managed building work as an owner builder on 2 or more buildings in the 10 years before the application).
Schedule 1 Part 2 amendment. Schedule 1 Part 2 includes a marginal note "[Part 2 of Schedule 1 Amended by No. 39 of 2018, s. 55, Applied:01 Jan 2017]". This indicates that the excluded work Part 2 was amended by the 2018 instrument as applied from 1 January 2017. The textual effect is the current wording excluding low-risk work and investigative certificates under section 321 of the Building Act 2016.
Schedule 2 amendment. Schedule 2 contains a marginal note showing it was amended by No. 39 of 2018, s. 57, applied 17 Dec 2018. The Schedule 2 interpretation for "architect" carries that marginal note. The schedule lists fee units for licences, owner builder permits and additional occupations, and the amendment note indicates adjustments to the schedule were made by the 2018 Act.
Insertion of regulation 15A. Regulation 15A is shown as inserted by No. 9 of 2023, s. 42, applied 01 Oct 2024, with a marginal note: "[Regulation 15A Inserted by No. 9 of 2023, s. 42, Applied:01 Oct 2024]". The inserted regulation provides that a fee is not payable under the Division for a building services licence issued to a council to enable it to perform functions of a permit authority under the Building Act 2016.
Publication and administration notes. The instrument concludes with a note that it was notified in the Gazette on 21 December 2016 and states the regulations are administered in the Department of Justice.
These marginal notes in the printed instrument document legislative adjustments to owner builder criteria, the excluded work list, the fees schedule and the insertion of a council fee exemption. The text supplied does not include cumulative amendment provisions or transitional rules beyond those marginal notes, so for precise historical application dates and transitional arrangements practitioners must consult the consolidated reprint or the principal legislation and amending Acts referenced in the marginal notes.
Litigation history
The supplied text of the regulations contains no cases, no judicial decisions, and no litigation history. There are no authority citations to judicial determinations within the instrument. The Schedule 3 infringement list refers to sections of the Act that may themselves have been the subject of litigation, but the regulations do not record any judicial consideration.
From an analytical perspective, the regulatory provisions create multiple potential areas where litigation or judicial review could arise, but any discussion of case law is outside the text. The regulations themselves provide no appeal or review mechanism for administrative decisions made under these regulations; such mechanisms, if any, will be those contained in the Occupational Licensing Act 2005 or the general administrative law system. Potential litigation focal points, drawn from the text only, include questions of statutory interpretation and the following matters.
Scope and meaning of prescribed versus excluded work. The boundary between Schedule 1 Part 1 (prescribed work) and Schedule 1 Part 2 (excluded work) may generate disputes about whether particular work is low-risk within the meaning of the Building Act 2016, or whether particular design or assessment work falls within the exclusions. Because the regulations adopt definitions from the building services work determination and cross-reference the Building Acts, disputes could involve the proper reading of those instruments and whether the regulator misapplied them.
Record completion triggers. Regulation 6(2) provides multiple alternative events that mark completion for the 10-year retention period. Litigation could arise if there is disagreement about which event applies to a particular project, for example when a contract is terminated, whether the certificate of completion has been properly issued, or whether statutory obligations have been discharged under the Building Acts. The regulation’s multiple subparagraphs create potential room for differing interpretations in particular factual scenarios.
Application of plumber practitioner carve outs. Regulation 4(4)(b)-(c) excludes certain design work and site-plan preparation performed by a plumber practitioner (certifier) under the Plumbing Work Regulations, when done within their area of competence. Disputes could appear over whether the work is within competence limits, or whether the work is the preparation of a site plan "in relation to work" for Class 10 or Class 7b farm buildings (regulation 4(4)(d)).
Owner builder permit eligibility and prior works calculation. Regulation 9(2)(e) sets an aggregate limit on prior owner-builder authorisations over the prior 10 years. Litigation could arise over the correct calculation of prior owner builder instances, whether certain prior works are "building work carried out or managed under an authorisation as an owner builder" for the purposes of the regulation, or whether transitional or simultaneous authorisations should be aggregated.
Absent specific cases in the instrument, readers must check consolidated legislation databases and relevant tribunal and court decisions for any judicial decisions interpreting these regulations or the cross-referenced Act and Building Acts. The regulations as supplied do not themselves record litigation history.
Gotchas
Several operational and interpretive traps exist in these regulations that create compliance risk and practical uncertainty. These are concrete items that practitioners should flag for clients, licence-holders and advisers.
10-year record retention with a range of completion triggers. Regulation 6(1) imposes a 10-year retention duty for all building services work "in an approved form". Regulation 6(2) gives multiple alternative events that count as completion depending on whether the work was subject to a building permit regime under the Building Act 2016, the Building Act 2000, was not covered by those acts, or was not building work. The multiplicity of triggers increases the chance that parties will miscalculate the retention start date, especially on projects spanning different regimes or on works not requiring permits. The regulation does not specify what constitutes "approved form" in the text, so practitioners must obtain the Administrator’s approval specification.
Approved form unspecified in text. The records must be kept "in an approved form" (regulation 6(1)), but the regulations do not contain the approval instrument or criteria. This means a provider may comply with the 10-year retention requirement but still fall foul of the form requirement if the Administrator issues a particular approval standard. The absence of the approved form in the text requires suppliers to monitor administrative instruments closely.
Penalty unit framing and conversion. Fines and infringement penalties are expressed in penalty units and fee units (Schedule 2 and Schedule 3), not dollar amounts. In practice this means compliance advisers and clients must convert units into dollars using the current statutory value of a penalty unit. The regulations do not specify the conversion, so failing to convert correctly could lead to underestimating exposure.
Differential obligations for individuals and entities. Notification duties and fines differ between natural persons and licensed entities, and the text makes specific distinctions (regulation 5). Practitioners acting for corporate licence-holders must ensure corporate governance processes are in place to satisfy the broader notification list (including directors and principal place of business) within 21 days, otherwise the corporate fine threshold (up to 25 penalty units) exposures apply.
Owner builder aggregate limit. Regulation 9(2)(e) prohibits an owner builder permit where the person and each other owner of the premises have, in aggregate, already carried out or managed owner-builder building work on 2 or more buildings in the prior 10 years. The aggregation rule can be counterintuitive, especially for joint owners or family groups who have been involved in prior owner-builder works. Careful client history checks are required before applying for an owner builder permit.
Plumbing certifier carve outs are limited. Regulation 4(4) excludes design work by plumber practitioners (certifiers) only where performed within their area of competence under the Plumbing Work Regulations. That protection does not apply to design work outside competence, or to design work by non-plumber practitioners. Clients who are plumber certifiers but whose work crosses discipline lines need careful assessment to avoid being captured by the building services licensing regime.
Fee refund limited to application refusal. Regulation 12(3) requires refund of annual or triennial fees if an application is refused, but the provision does not address partial refunds in other circumstances, fee transfers or fee credits. Applicants who change their mind after payment or who have administrative delays should not assume broader refund rights.
Council fee exemption narrow in scope. Regulation 15A exempts fees for licences issued to councils enabling them to perform permit authority functions under the Building Act 2016. The exemption appears narrow: it applies where the licence is issued to enable the council to perform permit authority functions. Councils seeking licences for other commercial or non-permit-authority functions may not be covered.
Infringement notice forwarding requirement. Regulation 16(4) requires authorised officers to forward copies of served infringement notices to the Administrator. Failure by an authorised officer to do this is not given a sanction in the text, but it may create administrative record-keeping risks and delayed central oversight.
Overlap between Building Acts. The regulations reference both the Building Act 2000 and the Building Act 2016 for completion triggers and exclusions (regulation 6(2), Schedule 1 Part 2). Projects that straddle changes in the Building Act regime or that involve different classes of works may require nuanced analysis to determine which completion event applies.
These operational issues are all grounded in the text of the regulations. They create compliance and administrative risk and require systems and advisory attention to manage.
How to comply
The regulations set out discrete, actionable compliance steps. Below are pragmatic measures derived from the text that practitioners and regulated parties should adopt.
Understand scope for each project
Determine whether the work falls within Schedule 1 Part 1 (prescribed) or Part 2 (excluded) by mapping the activity to the listed items: building/demolition work, design work, and assessment/certification work (Schedule 1 Part 1). If the work is low-risk within the meaning of the Building Act 2016 or not required under that Act to be performed by a licensed builder, it may be excluded (Schedule 1 Part 2(1)).
For plumbing-related design or site-plan tasks, check whether the plumber practitioner is acting as a certifier and is working within the area of competence defined under the Occupational Licensing (Plumbing Work) Regulations 2010, because regulation 4(4)(b)-(c) provides an exclusion in those narrow circumstances.
Set up record-keeping systems
Implement a retention policy to keep records of all building services work for at least 10 years after the work is completed, in an "approved form" (regulation 6(1)). Because the approved form is not contained in the regulations, obtain the Administrator’s specification and ensure digital or physical records meet that specification.
Define completion triggers in project-management systems to capture the earliest relevant event from regulation 6(2): certificate of completion under the Building Act 2016, certificate of completion under the Building Act 2000, contract termination, the last attendance by the provider, or discharge of statutory obligations where not building work. Ensure automated retention start dates are set accordingly.
Notification procedures for licence-holders
For individual licence-holders, monitor and update the Administrator within 21 days for changes of name, residential address, telephone or fax number used in connection with the licence, and email address (regulation 5(1)(a)-(d)).
For licensed entities, expand monitoring to include entity name, registered business name, directors or partners, registered office address, principal place of business, telephone or fax number used in connection with the licence, and email address (regulation 5(2)(a)-(g)).
Keep a compliance calendar and a responsible officer assigned to ensure the 21-day notification window is respected, because non-compliance attracts fines up to the amounts stated in regulation 5.
Fee compliance and budgeting
Consult Schedule 2 for the applicable fee units: owner builder permit fees (Schedule 2 item 2), annual and triennial fees for building services licences (Schedule 2 items 3-6), fee for additional occupations (Schedule 2 item 7), and replacement certificate fees (Schedule 2 item 1).
Note that fees are expressed in fee units and are inclusive of GST per regulation 12(2)(a). Convert fee units to monetary amounts using the current statutory fee unit value in force where fee-unit-to-dollar conversion rules are published.
Include the fee refund rule in budgeting: if an application for a licence is refused, any annual or triennial fee paid must be refunded to the payer (regulation 12(3)).
Owner builder permit eligibility check
Before applying for an owner builder permit under Part 3, verify that the applicant is a natural person, owns the premises, intends to carry out or manage the work (or another intending owner does), will not perform permit or notifiable demolition, and that the aggregate prior owner builder authorisations by the person and other owners do not exceed two in the previous 10 years (regulation 9(2)(a)-(f)).
If the proposed work is excluded under Schedule 1 Part 2 or involves Class 7b farm buildings, an owner builder permit may not be required (regulation 10).
Infringement notice readiness and risk management
Map conduct to the offences listed in Schedule 3, both under the Act (Part 1) and under the regulations (Part 2). For instance, record-keeping breaches under regulation 6 attract significant penalties including possible infringement notices (Schedule 3 Part 2 row 2 and regulation 6(1) fines).
Maintain insurance and risk management measures commensurate with potential penalty exposures. The regulations note separately that obligations under the Act in respect of an owner builder are additional to other obligations such as insurance obligations (regulation 11).
Liaison with Administrator and authorised officers
Keep documented proof of notifications to the Administrator and maintain a log showing dates and content, because authorised officers are required to forward served infringement notices to the Administrator and administrative records may be relied upon.
Seek guidance or published administrative instruments from the Administrator about the approved form for records, the procedure for notification, and any operational guidance on fee payment and conversions.
Corporate governance for licensed entities
For licensed entities, allocate internal responsibility for timely notification of corporate changes including directors, registered office and principal place of business, because failures carry the corporate penalty unit exposure in regulation 5(2).
Maintain cross-regulatory awareness
Because completion triggers and exclusions reference both the Building Act 2000 and Building Act 2016, confirm which Building Act regime applies to each project and update systems accordingly.
For plumbing work, check the Plumbing Work Regulations to determine scope and competence boundaries that affect whether design and site-plan tasks fall under these building services regulations.
Documentation and audit trail
Implement an audit trail for notifications, record retention, licence renewals, fee payments and owner builder permit applications, including electronic backups and retention of proof of postal or electronic delivery, to demonstrate compliance in the event of an enforcement action.
These steps follow directly from the textual duties and the schedules. They are designed to reduce regulatory risk by aligning internal processes with the times, trigger events, and notification windows set out in the regulations.
(3) Despite subregulation (2) , work specified in Part 2 of Schedule 1 is excluded from the application of the Act.
(4) Work referred to in subregulation (2) is prescribed as building services work for the purposes of paragraph (a) of the definition of building services work in section 3(1) of the Act unless –
(a) excluded from the application of the Act under subregulation (3) ; or
(b) the work is design work carried out by a plumber practitioner (certifier), within the meaning of the Occupational Licensing (Plumbing Work) Regulations 2010 , working within his or her area of competence; or
(c) the work is the preparation of a site plan, or as-constructed plan, in relation to work, or in association with work, carried out by a plumber practitioner (certifier), within the meaning of the Occupational Licensing (Plumbing Work) Regulations 2010 , working within his or her area of competence; or
(d) the work is the preparation of a site plan in relation to work performed on, or in association with work performed on, Class 10 buildings or Class 7b farm buildings.
5 Administrator to be notified of changes
5 Administrator to be notified of changes
(1) The holder of a building services licence that is not a licensed entity must notify the Administrator in writing within 21 days after any change to the following information:
(a) his or her name;
(b) his or her residential address;
(c) a telephone or fax number used in connection with the licence;
(d) an email address used in connection with the licence.
Penalty: In the case of –
(a) a body corporate, a fine not exceeding 25 penalty units; or
(b) a natural person, a fine not exceeding 10 penalty units.
(2) The holder of a building services licence that is a licensed entity must notify the Administrator in writing within 21 days after a change to the following information, if applicable:
(a) the name of the licensed entity;
(b) a registered business name used in connection with the licence;
(c) a person who is a director or partner of the licensed entity, or a person who is a licensed person for a municipal council;
(d) the address of the holder's registered office;
(e) the address of the holder's principal place of business;
(f) a telephone or fax number used in connection with the licence;
(g) an email address used in connection with the licence.
Penalty: Fine not exceeding 25 penalty units.
6 Records of building services work
6 Records of building services work
(1) A building services provider must keep, for at least 10 years after the work is completed, records, in an approved form, of all building services work, undertaken by the building services provider.
Penalty: In the case of –
(a) a body corporate, a fine not exceeding 50 penalty units; or
(b) an individual, a fine not exceeding 25 penalty units.
(2) For the purposes of this regulation, building services work is completed –
(a) if the building services work is building work or demolition work, other than low-risk work, within the meaning of the Building Act 2016 , on the earlier of the following days:
(i) the day on which a certificate of completion is issued under that Act in respect of the work;
(ii) the day on which the contract to perform the building work, or demolition work, is terminated; or
(b) if the building services work is building work that is covered by a building permit issued under the Building Act 2000 , on the earlier of the following days:
(i) the day on which a certificate of completion is issued under that Act, or the Building Act 2016 , in respect of the work;
(ii) the day on which the contract to perform the building work, or demolition work, is terminated; or
(c) if the building services work is building work that is not covered by paragraph (a) or (b) , on the earlier of the following days:
(i) the day on which the work is last attended to by the building services provider;
(ii) the day on which the contract to perform the building services work is satisfied by both parties to the contract or terminated; or
(d) if the buildings services work is not building work, on the earlier of the following days:
(i) the day on which all of the building services provider's statutory obligations in respect of the work under the Building Act 2000 , or the Building Act 2016 , are discharged;
(ii) the day on which his or her engagement as a building services provider in respect of the work ceases under the Building Act 2000 or the Building Act 2016 .
7.
[Regulation 7 Rescinded by S.R. 2016, No. 112, Applied:01 Jan 2019]
8 Duties of licence holders
8 Duties of licence holders
For the purposes of section 25(2A) of the Act, all building services work is prescribed.
Part 3 Owner Builders
Part 3 Owner Builders
9 Prescribed criteria
9 Prescribed criteria
(1) In this regulation –
building authority includes an authority allowing an accredited building practitioner to carry out or manage building work under the Building Act 2000 , and a building services licence.
(2) For the purposes of section 29B(1)(a) of the Act, the prescribed criteria for a person to hold an owner builder permit are –
(a) the person is a natural person; and
(b) the person owns the premises in respect of which the work to be performed under the proposed permit relates; and
(c) the person intends, or another owner builder in respect of the premises intends, to carry out or manage the building work on the premises under the authority of the proposed permit, whether or not that work has commenced before the proposed permit is issued; and
(d) the person does not intend, or another owner of the premises does not intend, to perform permit demolition work, or notifiable demolition work, within the meaning of the Building Act 2016 , under the authority of the proposed permit; and
(e) [Regulation 9 Subregulation (2) amended by No. 39 of 2018, s. 54, Applied:01 Jan 2017] other than building work carried out or managed under a building authority, the person and each other owner of the premises, in aggregate, have not already carried out or managed building work, under an authorisation as an owner builder, on 2 or more buildings in the 10 years immediately before the person made the application for the proposed permit; and
(f) each other owner of the premises meets the prescribed criteria set out in paragraphs (a) , (b) , (c) , (d) and (e) .
10 Owner builder permit not required
10 Owner builder permit not required
A person does not require an owner builder permit under this Part if the person intends to manage or carry out building work –
(a) that is excluded work under items 1 or 2 of Part 2 of Schedule 1 ; or
(b) in respect of a Class 7b farm building.
11 Obligation to hold insurance, &c.
11 Obligation to hold insurance, &c.
For the avoidance of doubt, an obligation under the Act in respect of a person performing work as an owner builder is in addition to, and not limited by, any obligation in respect of that person that he or she would be required to meet if performing the work other than as an owner builder.
Part 4 Miscellaneous
Part 4 Miscellaneous
Division 1 Fees
Division 1 Fees
12 Fees generally
12 Fees generally
(1) In this regulation –
GST has the same meaning as in the A New Tax System (Goods and Services Tax) Act 1999 of the Commonwealth.
(2) The fees specified in Schedule 2 –
(a) are inclusive of any GST that may be payable in respect of those fees; and
(b) are prescribed as the fees payable to the Administrator in respect of the matter to which they relate.
(3) If an application under these regulations for the issue of a licence is refused, any annual or triennial fee paid in respect of the issue of the licence is to be refunded to the person who paid the fee.
13 Licence fees
13 Licence fees
A person applying for the issue of a building services licence must pay the fee specified in Schedule 2 for that licence.
14 Additional occupations
14 Additional occupations
In addition to any other specified fee required to be paid, a person intending to apply for, or to renew, a licence in respect of more than one occupation must pay, on application, the fee specified in Schedule 2 for each additional occupation to be included, or renewed, on the licence.
15 Owner builder permit fees
15 Owner builder permit fees
A person applying for the issue of an owner builder permit under these regulations must pay the application fee specified in Schedule 2 for that permit.
15A Licensed entity fees for council
15A Licensed entity fees for council
[Regulation 15A Inserted by No. 9 of 2023, s. 42, Applied:01 Oct 2024] A fee is not payable under this Division in respect of a building services licence that is issued to a council to enable the council to perform the functions of a permit authority under the Building Act 2016 .
Division 2 Infringement notices
Division 2 Infringement notices
16 Infringement notices
16 Infringement notices
(1) For the purposes of section 62(1) of the Act –
(a) an offence against a provision of the Act specified in column 1 of the table in Part 1 of Schedule 3 is prescribed as an offence for which an infringement notice may be issued; and
(b) an offence against a provision of these regulations specified in column 1 of the table in Part 2 of Schedule 3 is prescribed as an offence for which an infringement notice may be issued.
(2) A penalty specified in column 2 of a table in Part 1 or 2 of Schedule 3 is prescribed as the penalty for a body corporate for the relevant offence specified in column 1 of the relevant table.
(3) A penalty specified in column 3 of a table in Part 1 or 2 of Schedule 3 is prescribed as the penalty for a natural person for the relevant offence specified in column 1 of the relevant table.
(4) If an infringement notice is served under section 62 of the Act and is not withdrawn, the authorised officer serving the infringement notice is to forward a copy of the notice to the Administrator.
SCHEDULE 1 - Building services SCHEDULE 1 - Building services work
SCHEDULE 1 - Building services SCHEDULE 1 - Building services work
Regulation 4
Part 1 Prescribed work
Part 1 Prescribed work
1. Building work or demolition work that is –
(a) work carried out on, or as part of, the construction, erecting or re-erecting, installation, replacement, repair, underpinning, alteration, addition, maintenance, demolition or removal of any premises, building or temporary structure; or
(b) excavating or filling incidental to an activity referred to in paragraph (a); or
(c) the management, carrying out, certification or entering of a contract for any of the types of work in paragraph (a) or (b).
2. Design work that is –
(a) architectural analysis, design and documentation of any premises, building or temporary structure; or
(b) engineering analysis, design and documentation of any premises, building or temporary structure, or of building components and structural systems, including research, analysing criteria, and finding and analysing solutions; or
(c) design of the building services of any premises, building or temporary structure, or of building components or systems, including matters related to the design of mechanical, electrical, hydraulic, acoustics, energy management and fire protection components or systems; or
(d) assessment and certification of architectural or engineering designs of proposed building work, hydraulic or plumbing work, or demolition work, including
This is an opening excerpt, not the complete document.