Mechanically, this local environmental plan replaces earlier local plans and establishes zoning, permitted/prohibited uses, exempt and complying development pathways, lot‑size controls and several map overlays for land in Oberon. The Council is the consent authority; landowners and developers pay application and compliance costs and must meet environmental, heritage and infrastructure conditions. The Plan’s stated aims include protecting natural and cultural assets, encouraging local employment and tourism, and managing subdivision and flood/karst risks, which is achieved by permit rules, site controls and discretionary decision‑making.
This instrument is a local environmental plan for the Oberon local government area, made under the Environmental Planning and Assessment Act framework and expressed as Oberon Local Environmental Plan 2013 (the Plan). It sets the planning rules that determine what land uses are permitted, permissible with consent, or prohibited across mapped zones (clause 2.1; cl. 2.2; Land Use Table). The Plan:
declares its aims (cl. 1.2), including protecting arts and cultural activity, encouraging sustainable economic growth and local employment, retaining productive agricultural land, and protecting natural and built heritage (cl. 1.2(1)-(2));
applies to the parcels shown on the Land Application Map (cl. 1.3) and relies on a set of statutory maps described in clause 1.7 (Land Zoning Map; Lot Size Map; Heritage Map; Riparian Lands and Watercourses Map; Industrial Buffer Map etc);
prescribes the full set of zones used in Oberon (cl. 2.1) and the Land Use Table at Part 2 which assigns objectives, permitted-without-consent uses, permitted-with-consent uses and prohibited uses for each zone (cl. 2.3);
requires development consent for subdivision and demolition in most cases (cl. 2.6; cl. 2.7) and identifies categories of exempt and complying development set out in Schedules 2 and 3 (cl. 3.1-3.2);
sets principal development standards, including minimum lot sizes (cl. 4.1 and related clauses 4.1AA, 4.1A), and includes an exceptions-to-standards mechanism (cl. 4.6) subject to specified limits;
imposes locally specific controls and decision-making requirements in Part 5 and Part 6 (for example heritage controls at cl. 5.10, flood planning at cl. 5.21, aquaculture controls at cl. 5.19, and riparian protections at cl. 6.3);
Current sections
Direct links to the current provisions in Oberon Local Environmental Plan 2013.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Advertising structures; Agriculture; Air transport facilities; Airstrips; Animal boarding or training establishments; Aquaculture; Bed and breakfast accommodation; Boat launching ramps; Boat sheds; Building identification signs; Camping grounds; Cellar door premises; Cemeteries; Community facilities; Correctional centres; Crematoria; Depots; Dual occupancies; Dwelling houses; Eco-tourist facilities; Educational establishments; Environmental facilities; Extractive industries; Farm buildings; Farm stay accommodation; Flood mitigation works; Freight transport facilities; Function centres; Helipads; Highway service centres; Home-based child care; Home industries; Industrial training facilities; Information and education facilities; Intensive livestock agriculture; Jetties; Landscaping material supplies; Open cut mining; Plant nurseries; Recreation areas; Recreation facilities (major); Recreation facilities (outdoor); Research stations; Roads; Roadside stalls; Rural industries; Sewerage systems; Veterinary hospitals; Water recreation structures; Water supply systems
4
Prohibited
4 Prohibited
4 Prohibited
Any development not specified in item 2 or 3
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
Note.
When this Plan was made it did not include all of these zones.
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Part 6
Additional local provisions
Part 6 Additional local provisions
Part 6 Additional local provisions
6
Earthworks
6 Earthworks
6.1 Earthworks
(1) The objective of this clause is to ensure that earthworks for which development consent is required will not have a detrimental impact on environmental functions and processes, neighbouring uses, cultural or heritage items or features of the surrounding land.
(2) Development consent is required for earthworks unless—
(a) the earthworks are exempt development under this Plan or another applicable environmental planning instrument, or
(b) the earthworks are ancillary to development that is permitted without consent under this Plan or to development for which development consent has been given.
(3) Before granting development consent for earthworks (or for development involving ancillary earthworks), the consent authority must consider the following matters—
(a) the likely disruption of, or any detrimental effect on, drainage patterns and soil stability in the locality of the development,
(b) the effect of the development on the likely future use or redevelopment of the land,
(c) the quality of the fill or the soil to be excavated, or both,
(d) the effect of the development on the existing and likely amenity of adjoining properties,
(e) the source of any fill material and the destination of any excavated material,
(f) the likelihood of disturbing relics,
(g) the proximity to, and potential for adverse impacts on, any waterway, drinking water catchment or environmentally sensitive area,
(h) any appropriate measures proposed to avoid, minimise or mitigate the impacts of the development.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
(c) land within a wetland of international significance declared under the Ramsar Convention on Wetlands.
Note.
Nothing in this clause affects any requirement under an Act relating to land specified in this clause to obtain a licence or other authority under that Act for development of the land.
8
Flood liability
8 Flood liability
8 Flood liability
Must be designed or constructed on land so that it will not be inundated by the discharge of a 1:100 ARI (average recurrent interval) flood event.
9
Species selection
9 Species selection
9 Species selection
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Oberon Local Environmental Plan 2013.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Oberon in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to encourage sustainable economic growth and development in Oberon,
(b) to encourage and provide opportunities for local employment growth and the retention of the population in Oberon,
(c) to encourage the retention of productive rural land in agriculture,
(d) to identify, protect, conserve and enhance Oberon’s natural assets,
(e) to identify and protect Oberon’s built and cultural heritage assets for future generations,
(f) to allow for the equitable provision of social services and facilities for the community,
(g) to provide for future tourist and visitor accommodation in a sustainable manner that is compatible with, and will not compromise the natural resource and heritage values of, the surrounding area.
designates the Council as the consent authority for the Plan (cl. 1.6) and identifies state policy interactions, including that State environmental planning policies prevail where they do so under the Act (cl. 1.9).
Mechanically, the Plan operates by zoning mapped land, specifying what uses are exempt, complying or require consent, and by listing matters the consent authority must have regard to in deciding applications (for example see cl. 2.3(2), cl. 4.6(3), cl. 5.10(4), cl. 6.3(3)). It also includes transitional and savings rules: planning instruments previously applying to the land are repealed (cl. 1.8) and development applications lodged but not finally determined before commencement are to be determined as if the Plan had not commenced (savings in cl. 1.8A). The Plan contains express local exceptions and site‑specific provisions (Schedules 1, 4 and 5), and records amendments and notes where provisions are "Not adopted" or "Not applicable".
All statements below are grounded in the Plan text cited above (clauses and Schedules referenced where relevant).
Main concepts
The Plan is structured around five recurrent planning concepts: zoning and land use tables; development consent regimes; mapped technical controls; constrained‑use clauses; and interaction with State instruments.
Zoning and Land Use Table. Clause 2.1 lists the zone categories used in Oberon (RU1, RU3, RU5, RU6, R1, R5, E1, E3, E4, SP3, RE1, RE2, C1). Clause 2.2 ties legal effect to the Land Zoning Map. The Land Use Table at Part 2 specifies objectives and the triage of uses: permitted without consent (i.e. generally low-impact or home-based uses), permitted with consent (broader classes of development), and prohibited (anything not listed) (cl. 2.3(1), Land Use Table entries).
Development consent and its alternatives. The Plan distinguishes development requiring consent from exempt development (Schedule 2; cl. 3.1) and complying development (Schedule 3; cl. 3.2). Exempt and complying development must still meet the Plan’s environmental exclusions and standards (cl. 3.3). Subdivision, demolition and many other significant works are expressly placed within the development consent regime (cl. 2.6; cl. 2.7).
Mapped technical controls. The Plan relies heavily on maps: Lot Size Map dictates minimum lot sizes and special lot‑averaging rules (cl. 4.1; cl. 4.1A); Heritage Map and Schedule 5 identify heritage items and conservation areas with consequential consent duties (cl. 5.10; Sch 5); Riparian Lands and Watercourses Map sets out 40 metre riparian buffers and triggers for additional consideration (cl. 6.3); Industrial Buffer Map identifies the Oberon Timber Complex and triggers special buffer assessment (cl. 6.6).
Locally calibrated standards and procedures. The Plan imports and tailors standards on specific activities: aquaculture (cl. 5.19 and Sch 6), intensive livestock thresholds (cl. 5.18), temporary uses (cl. 2.8), eco‑tourism assessment criteria (cl. 5.13), and music/noise exclusions for licensed premises (cl. 5.20). There are bespoke clauses for Titania Estate lot averaging (cl. 4.1A), strata and community title rules (cl. 4.1AA; cl. 4.2A), and suspension of covenants to enable development consistent with the Plan (cl. 1.9A).
Flexibility mechanisms with constraints. Clause 4.6 allows the consent authority to grant consent to contravene development standards where compliance is unreasonable or unnecessary, but records limits (for example a prohibition on granting such consents where a subdivision would create two or more lots below minimum sizes or less than 90% of a minimum size in certain rural and conservation zones, cl. 4.6(6)). The objectives and decision‑factors across heritage (cl. 5.10), riparian (cl. 6.3), flood planning (cl. 5.21) and earthworks (cl. 6.1) impose discretionary but structured duties.
Across these concepts, decision power is localised: the Council is the consent authority (cl. 1.6) and must apply the Plan alongside relevant State environmental planning policies that have precedence where provided by the Act (cl. 1.9(1)). The Plan frequently cross‑refers to other Acts and State policies (Heritage Act 1977, Rural Fires Act 1997, Fisheries legislation, Local Government Act 1993), making it a locally framed instrument that calls for multi‑statutory coordination.
Who it affects
The Plan creates rules that affect several categories of actors, with different exposures and decision roles:
Landowners and applicants. Owners and prospective developers on land within the mapped area are subject to the zoning matrix and the development consent, exempt and complying development rules (cl. 2.2; cl. 3.1-3.2). Subdivision, demolition and many development types require consent (cl. 2.6; cl. 2.7). Lot owners in mapped Lot Size areas face minimum lot size constraints and special area rules (cl. 4.1; cl. 4.1A; cl. 4.1AA). Heritage‑listed owners (Schedule 5) face consent and heritage management requirements (cl. 5.10).
Council (the consent authority). Clause 1.6 designates the Council as the consent authority, subject to the Act. The Council decides applications and must take into account zone objectives (cl. 2.3(2)), lists of matters for heritage, riparian, flood, industrial buffer, earthworks and other clauses (for example cl. 5.10(4)-(9), cl. 6.3(3), cl. 5.21(3)). The Council is also the local authority for classification/reclassification of public land under cl. 5.2 and for the "repeal and replacement" function under cl. 1.8.
State agencies and specialist authorities. The Plan preserves State policy primacy where relevant (cl. 1.9). Specific State agencies are nominated as relevant acquisition authorities for particular reserved land types (cl. 5.1(2) table). The Heritage Council must be notified in certain heritage/archaeological matters (cl. 5.10(7)-(9)). Fire and Rescue NSW appears indirectly in the conversion-of-fire-alarms clause (cl. 5.8).
Neighbours and the community. The Plan imposes constraints to protect surrounding amenity and environmental values (e.g. riparian zone protections cl. 6.3; buffer considerations for the Oberon Timber Complex cl. 6.6). Temporary uses are limited to 52 days in any 12‑month period unless an exception applies (cl. 2.8). Music and performance decisions in licensed premises cannot be refused on certain stylistic grounds provided noise can be managed (cl. 5.20).
Specialist industries. Specific industries are regulated through bespoke rules. Aquaculture developers face site and operational requirements (cl. 5.19; Sch 6). Intensive livestock agriculture is carved with capacity thresholds below which consent is not required subject to location restrictions (cl. 5.18). Timber and waste operators in the Oberon Timber Complex area trigger special considerations (cl. 6.6).
Public land users and local government administration. The Plan classifies and reclassifies public land (cl. 5.2; Sch 4) which affects Local Government Act functions, trust discharges and operational/community land categorisation.
Who pays. The burden falls primarily on applicants and landowners who must prepare applications, heritage management plans, environmental assessments, and provide infrastructure or services where required (for example cl. 6.4 on essential services). The community may face opportunity costs from land not being available for alternative uses due to mapped protections (Lot Size Map, Heritage Map, Riparian Map). The Council incurs assessment and administration costs when exercising consent functions and complying with notification duties (e.g., notifying Heritage Council or local Aboriginal communities under cl. 5.10).
Who decides. Council is the primary decision maker for development consent (cl. 1.6) subject to matters in this Plan and prevailing State policy (cl. 1.9). The Plan also identifies other specified State bodies as acquisition authorities for reserved land (cl. 5.1(2) table) and preserves State agency roles where other laws require.
Key duties and rights
The Plan sets out a matrix of duties for consent authorities, applicants and landowners, and rights such as permitted uses and exemptions. Below are concrete, source‑grounded duties and rights.
Consent authority duties and decision factors
Have regard to zone objectives when assessing applications (cl. 2.3(2)). Zone objectives are stated in the Land Use Table entries for each zone and are mandatory contextual factors.
Keep a record of any assessment under the exceptions to standards clause (cl. 4.6(4)). Where a development proposes to contravene a development standard, the consent authority must be satisfied of the applicant’s demonstration that compliance is unreasonable or unnecessary and there are sufficient environmental planning grounds (cl. 4.6(3)-(4)).
In heritage cases, consider effects on heritage significance and, where specified, require heritage management documents or conservation management plans and notify the Heritage Council or local Aboriginal communities as stipulated (cl. 5.10(4)-(9)). Consent is required for demolition, alteration or subdivision affecting heritage items unless exempted or considered minor under cl. 5.10(3).
For riparian land and watercourses, consider impacts on water quality, bank stability, aquatic species and flows and be satisfied that development is designed, sited and managed to avoid, minimise or mitigate adverse impacts (cl. 6.3(3)-(4)).
For flood planning, decline consent unless satisfied the development is compatible with flood function and will not worsen flood behaviour, and that evacuation and life safety risks are addressed (cl. 5.21(2)-(3)).
Applicant/owner duties
Comply with the zoning and permissible uses matrix: ensure proposed use is permitted in the zone, or seek consent if it is a permitted-with-consent use (cl. 2.3; Land Use Table).
For exempt or complying development, meet the standards in Schedule 2 or Schedule 3 and the exclusions in cl. 3.3 (e.g. not on environmentally sensitive areas).
Provide adequate information where the Plan or the Environmental Planning and Assessment Regulation requires it, for example an exception‑to‑standard application must be accompanied by the grounds document (cl. 4.6 note and cl. 4.6(3); Regulation reference is in the Plan).
In heritage and archaeological matters, prepare heritage management documents or conservation management plans if required by the consent authority (cl. 5.10(5)-(6)) and notify local Aboriginal communities where an Aboriginal place of heritage significance is involved (cl. 5.10(8)).
Rights and entitlements
Where a use is listed as "permitted without consent" it can be carried out subject to applicable environmental assessment under Part 5 of the Act and any other approvals from other Acts (cl. 2.3(1)-(2); Schedule 2 note). The Plan also recognises State instruments that provide exempt or complying pathways (cl. 3.1 note).
The Plan allows limited flexibility through clause 4.6 for development that would contravene a development standard, provided the applicant satisfies the criteria and the consent authority records its assessment.
Where a development application was lodged before commencement and not finally determined, cl. 1.8A gives applicants the right to have the application determined as if the Plan had not commenced, preserving the pre‑existing rights.
Other key duties
The Council must manage classification/reclassification of public land in accordance with the Local Government Act and the Plan (cl. 5.2).
The Plan suspends private covenants that would hinder carrying out development in accordance with the Plan, subject to enumerated exceptions (cl. 1.9A). This is a duty of legal effect, not an administrative duty, that alters private instrument efficacy where necessary to enable development under the Plan.
These duties and rights are embedded in the Plan clauses cited above. The Plan frequently cross‑references other statutory regimes, so parties will also have duties under those Acts where relevant (for example Crown Land, Heritage, Fisheries, Rural Fires). The Plan does not itself set out procedural appeal rights or penalty schedules; those matters are addressed in the Act and regulations referred to by the Plan.
Penalties and enforcement
The Plan establishes permissioning regimes and decision rules but does not itself set out detailed penalty tariffs or an enforcement schedule within its text. Enforcement mechanisms and penalties for non‑compliance with development consent, unauthorised development, or breaches of planning controls are matters generally governed by the Environmental Planning and Assessment Act and associated regulations rather than by local environmental plans. The Plan does, however, create substantive compliance triggers and obligation nodes that produce enforceable outcomes:
Consent triggers. The requirement for consent for subdivision, demolition and many other categories means carrying out such development without consent will be contrary to the Plan and subject to enforcement action under the Act (see cl. 2.6; cl. 2.7). The Plan’s classification of development as exempt, complying or requiring consent determines where enforcement risk arises if the wrong pathway is used.
Heritage and archaeological protections. Clause 5.10 requires consent for demolition or alteration of heritage items and sets out notification obligations. Unauthorised disturbance of archaeological sites (including Aboriginal objects) is also governed by the National Parks and Wildlife Act and the Plan emphasises the need to avoid disturbing relics (cl. 6.1 note; cl. 5.10(2)(c),(d)).
Environmental exclusions and permitted‑without‑consent limitations. Clauses such as 3.3 exclude environmentally sensitive areas from exempt or complying development. Carrying out such development contrary to the exclusion will place the activity outside the exempt/compliant category and potential enforcement follows.
Suspension of covenants. Clause 1.9A suspends private covenants to the extent necessary to enable development under the Plan, but it does not affect rights of public authorities under registered instruments. That is a legal effect rather than an enforcement mechanism.
Service of notices and mandatory consultation steps. Certain clauses impose procedural actions that, if not followed, may affect validity of consent decisions or give rise to administrative challenge. For instance, in heritage matters the consent authority must notify the Heritage Council or Aboriginal communities and consider responses within specified timeframes (cl. 5.10(7)-(9)).
What the Plan does not do in its text
The Plan does not list infringement amounts, maximum fines, or detailed enforcement procedures. Those functions are left to the Act and regulations.
The Plan does not itself provide a step‑by‑step enforcement protocol; it defines the substantive planning framework that enforcement authorities (usually the consent authority and prosecuting bodies under the Act) will apply in pursuing unauthorised activity.
Practical enforcement implications for practitioners and applicants
Non‑compliance risks are factual and arise where development occurs without the required consent or contrary to conditions and standards, and the Plan supplies the threshold rules that determine those risks (for example, whether an activity is exempt in Schedule 2 and meets the cl. 3.1 conditions).
Because the Plan cross‑refers to other Acts for certain protections (Heritage Act, Rural Fires Act, Fisheries, Crown land legislation), an activity may trigger enforcement under those regimes as well as under the Act if obligations are breached.
The Plan’s requirement for consent in heritage and riparian areas creates additional avenues for third‑party complaints and possibly administrative review. The Plan’s requirement to notify certain bodies (Heritage Council, local Aboriginal communities) can create procedural grounds on which consent decisions can be attacked if those notification duties are not discharged.
All enforcement action and penalty imposition will be taken under the broader legislative framework; the Plan supplies the substantive zoning and consent matrix. Practitioners should therefore consult the Act and its enforcement provisions in parallel with the Plan when advising on compliance and enforcement risks.
How it interacts with other laws
The Plan is expressly cross‑referential. It operates alongside, and defers to where necessary, State environmental planning policies and other statutory regimes. The Plan’s clauses identify specific interactions; below are the principal cross‑references and practical coordination points.
State environmental planning policies (SEPPs)
Clause 1.9(1) states that the Plan is subject to State environmental planning policy provisions that prevail over this Plan as provided by section 3.28 of the Act. The Plan therefore does not displace SEPPs where those SEPPs have precedence under the Act.
The Land Use Table and various notes list potentially relevant SEPPs such as State Environmental Planning Policy (Housing) 2021, SEPP (Transport and Infrastructure) 2021, SEPP (Resources and Energy) 2021 and others (Land Use Table note). These SEPPs potentially alter permitted uses, infrastructure approvals, or override local controls in specified areas.
Heritage and Aboriginal cultural heritage
The Plan invokes the Heritage Act 1977 by requiring consent for alterations or demolition of items listed on the State Heritage Register and by requiring notification to the Heritage Council in specified circumstances (cl. 5.10(2), (7), (9)). It also requires consideration of Aboriginal objects and places and notification of local Aboriginal communities before granting consent for development in Aboriginal places of heritage significance (cl. 5.10(8)). The Plan does not supplant the Heritage Act; rather it implements local controls that operate in parallel.
Crown and Crown land management
Clause 1.9A(2) excludes certain Crown instruments from the covenant suspension mechanism, including Crown Land Management Act 2016 instruments and conservation agreements under the National Parks and Wildlife Act 1974. Clause 5.12 recognises that the Plan does not restrict Crown infrastructure development allowed under SEPP (Transport and Infrastructure) 2021.
Rural Fires and bushfire regulation
Clause 5.11 expressly permits Rural Fires Act 1997 bush fire hazard reduction works without development consent. The Plan also notes that the Rural Fires Act contains other provisions about development on bush fire prone land.
Fisheries and aquaculture law
The aquaculture provisions cross‑refer to the Fisheries Management Act 1994 and related aquaculture industry development plans (cl. 5.19 and Sch 6). The Plan requires compliance with those plans and with NSW Oyster Industry Strategy considerations.
Land acquisition and public land classification
Clause 5.1 refers to the Land Acquisition (Just Terms Compensation) Act 1991 when identifying relevant acquisition authorities for owner-initiated acquisition of reserved land. Clause 5.2 links classification and reclassification of public land to the Local Government Act 1993.
Local Government Act and on‑site services
Clauses concerning classification of public land (cl. 5.2) operate with section 30 of the Local Government Act as noted in the Plan. Clause 3.2(3)(c) requires Council approval under the Local Government Act 1993 for on-site effluent disposal systems where complying development is proposed on unsewered land.
Building Code and BASIX
Clauses 3.1(3)(a) and 3.2(3)(b) require compliance with the Building Code of Australia deemed‑to‑satisfy provisions for exempt and complying development, and cl. 4.6(8) prohibits contravening standards that arise in a BASIX commitment.
Other planning instruments and mapping standards
Clause 1.7 requires mapping to be approved and maintained in accordance with Ministerial arrangements and references standard technical requirements for LEP maps and GIS data. This ties the Plan to the Department’s mapping and GIS standards.
Practical effect of these interactions
Many approvals will require applicants to navigate multiple regimes and obtain parallel approvals or certifications (for example, a development in a heritage place that requires excavation may trigger the Heritage Act, EP&A Act, approvals under Crown land arrangements and possibly fisheries or water permits depending on location).
Where State policies prevail, the Plan’s local standards may be displaced; practitioners must check SEPPs relevant to a site (cl. 1.9(1)).
The Plan’s repeated cross‑references to other statutes mean that compliance advice must be multi‑statutory. The Plan itself sometimes defers substantive technical matters (for example flood risk assessment guidance refers to the government's Considering Flooding in Land Use Planning Guideline and the Flood Risk Management Manual; cl. 5.21(4)-(5)).
All interactions above are stated in the Plan text (cl. 1.9; cl. 5.10; cl. 1.9A; cl. 5.12; cl. 5.19; cl. 5.1; cl. 3.1; cl. 4.6(8); cl. 1.7; cl. 5.21). Practitioners should treat the Plan as the local piece of a multi‑layered statutory puzzle that includes SEPPs, State Acts and technical guidelines cited in the Plan.
Amendment history
The Plan text includes references to a number of amendments and editorial notes indicating when particular clauses were amended, inserted, repealed or not adopted. The Plan records multiple amendment citations adjacent to clause headings and Schedule notes. Those in‑text amendment annotations should be read as the Plan’s own amendment record. Key in‑text amendment markers include:
Clause 1.8A was amended: "cl 1.8A: Am 2019 (621), Sch 5[1]" , this is the savings provision for development applications lodged before commencement (cl. 1.8A).
Clause 1.9A (suspension of covenants) shows amendment markers: "cl 1.9A: Am 2019 (621), Sch 5[2]-[4]".
Clause 2.1 (land use zones) carries amendments "cl 2.1: Am 2019 (356), Sch 1 [1]; 2022 (830), Sch 1.18[1]".
The Land Use Table includes an amendment string citing amendments across 2016-2022 (Land Use tbl: Am 2016 (168), Sch 1 [5]; 2017 (418), cl 4 (1); 2017 (493), Sch 1.1 [1]; 2018 (488), Sch 1.1 [1]; 2019 No 1, Sch 2.23 [1] [2]; 2019 (356), Sch 1 [2]; 2019 (621), Sch 3; 2022 (314), Sch 1; 2022 (830), Sch 1.18[2]).
Clause inserts and repeals include cl. 4.1A ("cl 4.1A: Am 2017 (105), Sch 1") which establishes Titania Estate lot averaging rules, and cl. 4.2C noted as inserted 2016 and later amended "cl 4.2C: Ins 2016 (249), Sch 1; 2022 (830), Sch 1.18[3] [4]".
Schedule 1 shows amendments including 2015, 2017 and 2024 (sch 1: Am 2015 (636), cl 4 (1); 2017 (418), cl 4 (2); 2024 (130), Sch 1), and an additional permitted use for 31 O’Connell Road is included in Schedule 1.
Schedule 5 (Environmental heritage) cites amendments up to 2026: "sch 5: Am 2015 (441), Sch 1; 2026 (146), Sch 1", indicating the heritage schedule received updates as recently as 2026 in the Plan text.
Other visible amendment markers:
Clause 6.2 noted as repealed with "cl 6.2: Rep 2021 (225), Sch 1."
Clause 4.3, 4.4 and 4.5 (height, floor space ratio and calculation) show "[Not adopted]" indicating the Plan did not adopt those standard measures at the time of making; these could be added by future amendment if desired by the plan‑making authority.
Multiple clauses were noted as "Not adopted" or "Not applicable" (for example cl. 5.7 development below mean high water mark; cl. 5.9 Dwelling house affected by natural disaster not adopted; cl. 5.14 Siding Spring Observatory,maintaining dark sky not adopted).
Interpretation of the amendment notes
The Plan records the legal provenance of individual clause changes by citing amending instruments and schedule references. The dates and instrument identifiers adjacent to each amendment tag are the Plan’s internal record of amendment events; they should be used to trace the amending legislation or instrument in the official NSW legislation database.
The Plan also notes which provisions have been inserted or repealed (for example cl. 4.2C insertion in 2016 and cl. 6.2 repealed 2021), so practitioners should check the current consolidated version for the operative text and amendment history.
For precise amendment instrument details and dates beyond the in‑text shorthand, users should refer to the official NSW legislation database where the full amending instruments are listed. All amendment citations above are taken from the Plan’s own amendment annotations as presented in the text.
Litigation history
The Plan text itself does not record judicial decisions or administrative appeal outcomes. There are no court judgments, tribunal decisions, or litigation summaries included in the Plan document provided. Accordingly:
The Plan contains no internal register of litigation or case law citing its provisions.
Practitioners seeking jurisprudence on the application or interpretation of specific clauses (for example clause 4.6 exceptions to standards, clause 5.10 heritage duties, or clause 1.9A suspension of covenants) will need to search external case law databases and administrative review records of the Land and Environment Court and other relevant tribunals.
What the Plan does provide that bears on litigation risk
The Plan includes several discretionary decision points and mandatory notification obligations (for example to Heritage Council or local Aboriginal communities under cl. 5.10). Failure to observe mandatory steps or to record required assessments (for example the record under cl. 4.6(4)) can create grounds for merits review or judicial review in practice, although specific outcomes will depend on case law not contained in this instrument.
The Plan’s cross‑references to State SEPPs, the Act and other statutory instruments mean interpretation disputes will often require combined assessment of multiple statutes and policy instruments.
Because the Plan itself contains no litigation history, anyone requiring precedent or an understanding of how particular clauses have been interpreted by courts should conduct an independent search of Land and Environment Court decisions and other relevant jurisprudence.
Gotchas
This Plan contains a number of provisions and interactions that commonly trip up applicants, solicitors, planners and landowners. The following are specific, sourced pitfalls to be aware of.
Savings provision for pending DA applications (cl. 1.8A). Development applications lodged but not finally determined before the Plan commenced must be determined as if the Plan had not commenced. Practitioners must check the lodgement and determination dates carefully. This can lead to different applicable controls depending on timing.
Suspension of covenants (cl. 1.9A). The Plan suspends private covenants to the extent necessary to permit development under the Plan, but excludes covenants imposed by the Council and a range of Crown or statutory agreements (cl. 1.9A(2)(a)-(g)). This creates a complex legal interaction: a private restrictive covenant might be suspended for a development authorised by the Plan, but a council‑imposed covenant remains effective. Advice on covenant status and enforceability should be site‑specific.
Exclusion of environmentally sensitive areas from exempt/compliant pathways (cl. 3.3). Exempt or complying development cannot be carried out on specified environmentally sensitive areas including World Heritage sites, Ramsar wetlands, land of high Aboriginal cultural significance and land reserved under the National Parks and Wildlife Act (cl. 3.3(2)(e)-(i)). Applicants who assume an exempt pathway without checking these mapped exclusions risk unauthorised works.
Minimum lot size and the exception limits (cl. 4.1; cl. 4.6). Clause 4.1 enforces minimum lot sizes mapped on the Lot Size Map. Clause 4.6 allows contravention of development standards in limited circumstances but explicitly prohibits using that flexibility to permit subdivisions that would create two or more lots below the minimum area or lots less than 90% of minimum area in specified zones (cl. 4.6(6)). Attempting to use cl. 4.6 to circumvent mapped lot size minima in rural or conservation zones will be blocked by cl. 4.6(6).
Discrete local exceptions and site‑specific rules. Titania Estate lot averaging (cl. 4.1A) and Schedule 1 additional permitted uses for 31 O’Connell Road are examples of site‑specific departures from general rules. Practitioners must check the Lot Size Map for “Area A/B/C” identifiers and Schedule 1 entries to avoid missing bespoke permissions or constraints.
Heritage thresholds and notification duties (cl. 5.10). The Plan requires notification of the Heritage Council and local Aboriginal communities in certain circumstances and allows the consent authority to require heritage management documents and conservation plans. Failure to notify or to prepare adequate heritage documentation can delay or invalidate consents. The Plan distinguishes between minor works (for which the consent authority may confirm no consent is required) and works that require full consent (cl. 5.10(3)).
Aquaculture and intensive livestock location restrictions (cl. 5.19; cl. 5.18). Intensive livestock and aquaculture may escape consent thresholds subject to capacity and locational limits (e.g., poultry thresholds, distances from other farms, proximity to waterways). For aquaculture, Schedule 6 sets operational and site location requirements. Misstating capacity or failing to respect conservation exclusion zones can transform a permitted without consent activity into unauthorised development.
Music and licensed premises (cl. 5.20). Clause 5.20 bars consent authorities from refusing development for licensed premises based on music genre, whether live or amplified, whether dancing occurs, presence of a dance floor, or other decorative elements, so long as noise can be managed to an acceptable level. Applicants who rely on this provision must still demonstrate noise management; the clause prevents refusal on narrow stylistic grounds but does not remove noise management obligations.
Essential services and unsewered land (cl. 6.4; cl. 3.2(3)(c)). Development consent must ensure essential services are available. For complying development on unsewered land, Council approval for on‑site effluent disposal may still be required. Assuming infrastructure is in place without formal approvals is a common practical pitfall.
Interplay with State policy (cl. 1.9). The Plan is subject to SEPPs that may prevail. Local planning assumptions should be checked against current SEPPs; some State policies may authorise activities differently to the Plan.
Repeal and transition of earlier LEPs (cl. 1.8). The Plan repeals prior local environmental plans applying only to the land (cl. 1.8). Historical approvals, consents and entitlements need to be carefully tracked to understand what survives the repeal.
"Not adopted" clauses. Where the Plan labels clauses as "Not adopted" (for example cl. 4.3 Height of buildings; cl. 4.4 Floor space ratio), those standards are not present; absence of an adopted numerical control may create uncertainty about acceptable building forms and may result in heavier reliance on objectives‑based assessment. Practitioners should not assume a missing standard means permission for larger scale development.
These "gotchas" arise directly from the Plan’s clauses cited above. In practice, a site‑by‑site mapping check against the Land Zoning Map, Lot Size Map, Heritage Map and Riparian Map, plus cross‑checking relevant SEPPs and other Acts cited in the Plan, is essential before making a development decision.
How to comply
This practical section sets out an evidence‑based compliance checklist organised around common project stages. Each step references the Plan provisions that generate the requirement.
Initial due diligence and mapping
Confirm land applicability and zoning. Check the Land Application Map and Land Zoning Map referenced in cl. 1.3 and cl. 2.2 to confirm the exact zone and any map‑coded areas affecting the site (Lot Size Map, Heritage Map, Riparian Lands and Watercourses Map, Industrial Buffer Map).
Identify special map‑coded areas. If the lot is in Area A, B or C on the Lot Size Map, review clauses 4.1, 4.1A and 4.1AA for subdivision and lot‑averaging rules. If the site is within "Oberon Timber Complex" on the Industrial Buffer Map, apply cl. 6.6 requirements.
Confirm permitted uses and consent triggers
Consult the Land Use Table in Part 2 for that zone to determine whether your proposed use is permitted without consent, permitted with consent, or prohibited (cl. 2.3(1)). If not listed, it is prohibited in that zone (Land Use Table: Prohibited = any development not specified in items 2 or 3).
For exempt or complying development pathways, consult Schedule 2 and Schedule 3 and ensure compliance with the technical standards and the exclusions under cl. 3.3 (no exempt/compliant development in environmentally sensitive areas listed in cl. 3.3(2)).
Check development standards and exceptions
For subdivisions, confirm minimum lot sizes on the Lot Size Map and whether any special exceptions apply (cl. 4.1; cl. 4.2); if proposing to contravene a development standard, prepare the document required by the Environmental Planning and Assessment Regulation that demonstrates why compliance is unreasonable or unnecessary and sufficient environmental planning grounds exist (cl. 4.6(3) and Regulation reference in Plan).
Remember cl. 4.6(6) limits the use of the exceptions to prevent creating multiple undersized lots in specified zones. Do not rely on cl. 4.6 where that prohibition would apply.
Heritage, Aboriginal cultural heritage and archaeology
If the property is listed in Schedule 5 or lies within a Heritage Conservation Area, prepare heritage documentation and anticipate that the consent authority may require a heritage management document or conservation plan (cl. 5.10(5)-(6)). Notify and consult the Heritage Council and local Aboriginal communities where the clause mandates (cl. 5.10(7)-(9)).
If excavation or disturbance might reveal relics or Aboriginal objects, consider obligations under the National Parks and Wildlife Act and the Plan’s directions (cl. 6.1 note; cl. 5.10(2)(c),(d)).
Environmental and technical assessments
For riparian and watercourse proximity, prepare water quality, erosion and habitat impact assessments. The consent authority must consider specified matters (cl. 6.3(3)-(4)); design and siting must avoid or minimise impacts.
For flood‑prone sites, prepare flood risk assessments addressing the Considering Flooding in Land Use Planning Guideline and Flood Risk Management Manual as referenced in cl. 5.21(4)-(5). Demonstrate measures to manage life safety and evacuation.
Industry‑specific compliance
For aquaculture and intensive livestock proposals, ensure compliance with the site and operational requirements in cl. 5.19 and Schedule 6, and check the capacity and locational thresholds in cl. 5.18 if seeking a no‑consent pathway.
For eco‑tourism, prepare a management strategy that addresses the matters in cl. 5.13(3)(a)-(k) including measures for habitat regeneration, minimal energy/water usage and monitoring protocols.
Consult and notify
Where the Plan requires notification of external bodies (Heritage Council, local Aboriginal communities, or other agencies), build those timelines into the project plan (cl. 5.10(7)-(9)). The Plan sets 28‑day windows for Heritage Council responses in certain situations.
The Plan also requires the consent authority to consider matters like amenity impacts on adjacent landholders (e.g. cl. 2.8(3)(b) temporary uses; cl. 6.1(3)(d) earthworks).
Prepare the DA package
Assemble statements of environmental effects, heritage management documents, flood and riparian assessments, and the exception‑to‑standard document where applicable (cl. 4.6 note). Ensure any BASIX commitments or Building Code matters are addressed as cl. 4.6(8) prohibits contravening BASIX or complying development standards.
For complying development, ensure you meet the Building Code of Australia deemed‑to‑satisfy provisions and any Council approval requirements for septics on unsewered land (cl. 3.2(3)(b)-(c)).
Check covenants and title
Review registered covenants and other instruments. Clause 1.9A may suspend certain private covenants to the extent necessary to enable Plan‑consistent development, but does not affect Council‑imposed covenants or specified Crown instruments (cl. 1.9A(2)). Obtain legal advice on covenant status and the likely operative effect.
Post‑consent compliance and conditions
Development consent will carry conditions. Ensure essential services commitments required by cl. 6.4 are satisfied before occupation or as staged works. Conditions may reference heritage conservation works required by cl. 5.10(10) where conservation incentives are used.
For any conversion of fire alarms (cl. 5.8), note the working hours condition for complying development certificates and the need to obtain consent for conversions that are not strictly internal alterations.
Appeals and records
Keep records of the consent authority’s assessment, especially where cl. 4.6 exceptions are used because the consent authority must keep a record of its assessment (cl. 4.6(4)). This record is material in any later merits review or judicial review.
Cross‑check State instruments
Verify whether a SEPP applies to the site and whether its provisions prevail (cl. 1.9(1)). State instruments can alter permissible uses, approvals for infrastructure, or impose additional constraints.
This compliance pathway is a practical synthesis of the Plan’s operative clauses (cl. 1.3; cl. 2.3; cl. 3.1-3.3; cl. 4.1; cl. 4.6; cl. 5.10; cl. 5.19; cl. 5.21; cl. 6.1; cl. 6.3; cl. 6.4; cl. 1.9A). Site‑specific legal and technical advice should be obtained for complex projects, particularly where multiple statutory regimes intersect or where the Plan’s exemptions and exceptions are being relied upon.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Oberon Local Environmental Plan 1998
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
cl 1.8A: Am 2019 (621), Sch 5[1].
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
cl 1.9A: Am 2019 (621), Sch 5[2]–[4].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate may exceed the maximum number of days specified in that subclause.
(5) Subclause (3) (d) does not apply to the temporary use of a dwelling as a sales office mentioned in subclause (4).
2 Canal estate development prohibited
2 Canal estate development prohibited
2.9 Canal estate development prohibited
(1) Canal estate development is prohibited on land to which this Plan applies.
(2) In this Plan, canal estate development means development that involves—
(a) a constructed