93 Requirements for making, or not making, a scheme pipeline determination
93 Requirements for making, or not making, a scheme pipeline determination
(1) A scheme pipeline determination or a decision not to make a scheme pipeline determination must—
(a) be made in accordance with this Law and the Rules; and
(b) contain the information required by the Rules; and
(c) be given to the persons specified by the Rules; and
(d) be made publicly available in accordance with the Rules; and
(e) if a scheme pipeline determination is made—specify the date the determination takes effect.
(2) For subsection (1)(e), the date specified must be at least 6 months, but not more than 12 months, after the determination is made.