(1) AEMO’s declared network functions are as follows—
(a) to plan, authorise, contract for, and direct, augmentation of the declared shared network;
(b) to provide information about the planning processes for augmentation of the declared shared network;
(c) to provide information and other services to facilitate decisions for investment and the use of resources in the adoptive jurisdiction’s electricity industry;
(d) to provide shared transmission services by means of, or in connection with, the declared shared network;
(e) any other functions, related to the declared transmission system or electricity network services provided by means of or in connection with the declared transmission system, conferred on it under this Law or the Rules;
(f) any other functions, related to the declared transmission system or electricity network services provided by means of or in connection with the declared transmission system, conferred on it under a law of the adoptive jurisdiction.
(2) AEMO—
(a) is not limited in planning augmentation of the declared shared network to its role as National Transmission Planner; and
(b) may make or issue market information instruments as may be necessary or expedient for that or any other declared network function.
ss 50A–50C: Ins 2009 No 31, sec 17.