National Electricity (NSW) Law
28ZJFunctions where AER is regulator
Start here
Get a plain-English read of 28ZJ
Turn the raw legal text into a practical explanation grounded in National Electricity (NSW) Law.
28ZJ Functions where AER is regulator
28ZJ Functions where AER is regulator
(1) This section applies if the AER is appointed as regulator under the Electricity Infrastructure Investment Act 2020, section 64.
(2) If this section applies—
(a) the AER has the functions conferred under section 15(1)(a), (b), (c) and (d) and Part 6 as if the relevant provisions are part of the Rules; and
(b) the Court has jurisdiction under Part 6 to deal with proceedings commenced by the AER under paragraph (a).
(3) In this section—
relevant provisions means provisions in a regulation made under the Electricity Infrastructure Investment Act 2020 that confer or impose functions on an infrastructure planner relating to a section 27/41 rule or section 42A rule.
s 28ZJ: Ins 2013 No 79, sec 6. Rep 2021 No 3, sec 10. Ins 2024 No 83, Sch 1[22]. Am 2025 No 80, Sch 1[48].