NATIONAL ELECTRICITY (NORTHERN TERRITORY) (NATIONAL UNIFORM LEGISLATION) (MODIFICATION) REGULATIONS 2016
25DClause 5.3.7 modified
Start here
Get a plain-English read of 25D
Turn the raw legal text into a practical explanation grounded in NATIONAL ELECTRICITY (NORTHERN TERRITORY) (NATIONAL UNIFORM LEGISLATION) (MODIFICATION) REGULATIONS 2016.
25D Clause 5.3.7 modified (1) After clause 5.3.7, heading Note Paragraphs (c) and (g)(2)(i), (5) and (6) of this clause have no effect in this (2) Clause 5.3.7(b) omit schedules 5.2, 5.3 and 5.3a accordance with jurisdictional electricity legislation (3) After clause 5.3.7(b) Note out in schedules 5.2 and 5.3 in the Rules applying in other participating jurisdictions. The application of paragraph (b) will be revisited as part of the (4) Clause 5.3.7(d) omit or any system strength connection works (5) Clause 5.3.7(g) and (h) AEMO
Regulations 2016 33 (6) Clause 5.3.7(h) omit schedule 7.4 schedule 7A.4