sec.60B Notifying chief inspector if mine is a major hazard facility or a possible major hazard facility
The site senior executive for a mine that is a major hazard facility or possible major hazard facility must notify the chief inspector about the mine— in the approved form; and at least 6 months before the mine starts operations. Maximum penalty—200 penalty units. Subsection (1) is not a safety and health obligation for the Act . (sec.60B-ssec.1) The site senior executive for a mine that is a major hazard facility or possible major hazard facility must notify the chief inspector about the mine— in the approved form; and at least 6 months before the mine starts operations. Maximum penalty—200 penalty units. (sec.60B-ssec.3) Subsection (1) is not a safety and health obligation for the Act .
- (a) in the approved form; and
- (b) at least 6 months before the mine starts operations.