sec.23 Interrupting electricity supply to particular plant
The operator or site senior executive must ensure the electricity supply to the following plant at the mine is capable of interruption from an accessible position remote from the plant— a stacker, reclaimer, dredge, floating treatment plant and underground electrical installation; other plant identified by a risk assessment as needing its electricity supply to be capable of interruption from an accessible position remote from the plant to ensure an acceptable level of risk.
- (a) a stacker, reclaimer, dredge, floating treatment plant and underground electrical installation;
- (b) other plant identified by a risk assessment as needing its electricity supply to be capable of interruption from an accessible position remote from the plant to ensure an acceptable level of risk.