sec.113 Records
If, having regard to the nature and level of risk from plant used at a mine, it is necessary for managing the risk, the site senior executive for the mine must ensure a record is kept at the mine about— the plant’s— manufacture, construction, storage, transport, and installation; and commissioning; and use; and servicing and maintenance; and repair and modification; and inspection, testing and monitoring, and any action taken as a result of the inspection, testing and monitoring; and incidents, damage and operation happening outside the plant’s design envelope. For ropes used in winding operations in which a winder of at least 30kW capacity is used, the site senior executive must ensure a record is kept of the matters stated in subsection (1) regardless of the nature and level of risk from the ropes. The site senior executive must ensure the records are— kept for the life of the plant or until its earlier permanent decommissioning or disposal; and available to, and readily accessible by, each worker using the plant at the mine. s 113 amd 2019 SL No. 140 s 21 sch 1 (sec.113-ssec.1) If, having regard to the nature and level of risk from plant used at a mine, it is necessary for managing the risk, the site senior executive for the mine must ensure a record is kept at the mine about— the plant’s— manufacture, construction, storage, transport, and installation; and commissioning; and use; and servicing and maintenance; and repair and modification; and inspection, testing and monitoring, and any action taken as a result of the inspection, testing and monitoring; and incidents, damage and operation happening outside the plant’s design envelope. (sec.113-ssec.2) For ropes used in winding operations in which a winder of at least 30kW capacity is used, the site senior executive must ensure a record is kept of the matters stated in subsection (1) regardless of the nature and level of risk from the ropes. (sec.113-ssec.3) The site senior executive must ensure the records are— kept for the life of the plant or until its earlier permanent decommissioning or disposal; and available to, and readily accessible by, each worker using the plant at the mine.
- (a) the plant’s— (i) manufacture, construction, storage, transport, and installation; and (ii) commissioning; and (iii) use; and (iv) servicing and maintenance; and (v) repair and modification; and (vi) inspection, testing and monitoring, and any action taken as a result of the inspection, testing and monitoring; and
- (i) manufacture, construction, storage, transport, and installation; and
- (ii) commissioning; and
- (iii) use; and
- (iv) servicing and maintenance; and
- (v) repair and modification; and
- (vi) inspection, testing and monitoring, and any action taken as a result of the inspection, testing and monitoring; and