### sec.318ELBA Overlapping lease application for all of the land
This section applies if—
the overlapping authority priority is for all of the land; and
within the overlapping authority application period the overlapping permit holder applies for an overlapping lease for all of the land.
A further step can not be taken to decide the mining lease application until after the overlapping lease application has been decided.
The Geothermal Act , chapter 5 , part 5 and the GHG storage Act , chapter 4 , part 5 provide for refusal of the overlapping lease application if it is not pursued in a timely manner.
If the decision on the overlapping lease application is to grant an overlapping lease for all of the land, the mining lease application is taken to have lapsed.
s 318ELBA ins 2009 No. 3 s 511
sub 2010 No. 31 s 525
(sec.318ELBA-ssec.1) This section applies if— the overlapping authority priority is for all of the land; and within the overlapping authority application period the overlapping permit holder applies for an overlapping lease for all of the land.
(sec.318ELBA-ssec.2) A further step can not be taken to decide the mining lease application until after the overlapping lease application has been decided. The Geothermal Act , chapter 5 , part 5 and the GHG storage Act , chapter 4 , part 5 provide for refusal of the overlapping lease application if it is not pursued in a timely manner.
(sec.318ELBA-ssec.3) If the decision on the overlapping lease application is to grant an overlapping lease for all of the land, the mining lease application is taken to have lapsed.
- (a) the overlapping authority priority is for all of the land; and
- (b) within the overlapping authority application period the overlapping permit holder applies for an overlapping lease for all of the land.