Melbourne Strategic Assessment (Environment Mitigation Levy) Act 2020
44Secretary to be notified of building permit application for building work on Crown land within levy area
Start here
Get a plain-English read of 44
Turn the raw legal text into a practical explanation grounded in Melbourne Strategic Assessment (Environment Mitigation Levy) Act 2020.
44 Secretary to be notified of building permit application for building work on Crown land within levy area
(1) The person responsible for the carrying out of building work on Crown land within the levy area must, within 14 days after an application is made for a building permit for that work, give the Secretary—
(a) written notice of the application; and
(b) a copy of the application; and
(c) the following information if the information is not contained in the application—
(i) a description of the location of the land on which the work is proposed to be carried out, including details of any Crown allotment if the work will be carried out on a Crown allotment;
(ii) the area of land on which the work is proposed to be carried out;
(iii) a description of the proposed building work and proposed use or purpose of the building to be constructed;
(iv) the date on which the application was made;
(v) the applicant's name and contact details;
(vi) the name and contact details of the person responsible for the carrying out of the work;
(vii) the name and contact details of the Crown land manager of the land if that manager is not the person responsible for the carrying out of the work;
(viii) the name and contact details of any occupier of that land if that occupier is not the person responsible for the carrying out of the work;
(ix) the name and contact details of the relevant building surveyor to whom the application was made.
(2) This section does not apply to prescribed building work.
See also sections 111 and 112.