59 Comprehensive impact statement issues report or statement
S. 59(1) substituted by No. 49/2013 s. 31(2).
(1) If an assessment committee has been given a direction to prepare a report under section 36(1)(bb), the committee must give the project proponent for the declared project in relation to which the committee was established—
(a) a written report that summarises the issues in relation to the comprehensive impact statement that the committee considers the project proponent should address; or
(b) a written statement that the committee considers that there are no issues in relation to the comprehensive impact statement that the committee considers the project proponent should address.
S. 59(2) amended by No. 49/2013 s. 31(3).
(2) A report or statement under subsection (1) must be given to the project proponent within 20 business days after the end of the public exhibition period.