270 Utility responses in relation to location of utility infrastructure for the purposes of North East Link Project
(1) This section applies if before the commencement day a utility has, in response to a request from the project authority for the North East Link Project about the location of utility infrastructure that it owns, operates or controls, given the project authority the requested information.
(2) On the commencement day, the utility is taken to have complied with section 212 (as substituted by section 7 of the amending Act).
Pt 12 (Heading and ss 271−278) inserted by No. 43/2021 s. 216.