165J Project authority to fence lands before using them
(1) If part of any land is occupied or used for the purposes of section 165D, the project authority must, if required to do so by the owner or occupier of the land, separate that part from the remainder of the land adjoining it by a sufficient fence with any gates that are necessary.
(2) In the case of any difference between the owners or occupiers of the lands and the project authority as to the necessity of the fences and gates, the lands must be separated with any fences and gates that the Project Minister thinks necessary for the convenient occupation or use of the lands.
(3) This section does not apply in relation to the entry, occupation or use of land under section 165G.
S. 165K inserted by No. 43/2021 s. 190.