14A Amended corridors
[Section 14A Inserted by No. 19 of 2001, s. 8, Applied:12 Apr 2001]
(1) The proponent of a major infrastructure project may request the Minister to amend a notified corridor.
(2) The request is to be accompanied by a plan of the proposed amended corridor.
(3) A plan for the purposes of subsection (2) is to identify the boundaries of the proposed amended corridor with sufficient accuracy to enable an owner of land to determine whether or not that land will be affected by the amended corridor.
(4) If the Minister is satisfied that it is reasonable to amend a notified corridor, the Minister must cause notice of the amended corridor to be served on –
(a) the Commission; and
(b) each planning authority on which obligations are imposed by the order under section 7(2) or which is otherwise affected by the amended corridor; and
(c) each owner of land added to the notified corridor by the amendment of that corridor; and
(d) each owner of land deleted from the notified corridor by the amendment of that corridor.
(4A) [Section 14A Subsection (4A) inserted by No. 64 of 2001, s. 6, Applied:10 Oct 2001] [Section 14A Subsection (4A) amended by No. 102 of 2001, Sched. 1, Applied:28 Jun 2002] A notice for the purpose of subsection (4) that is required to be served on an owner that is a company may be served by post on the owner at the postal address of the owner in the valuation roll prepared under section 24 of the Valuation of Land Act 2001 .
(5) The Commission must, in the performance of its functions and exercise of its powers, have regard to any notice which is served on it under subsection (4) .
(6) A planning authority must, in the performance of its functions and exercise of its powers, have regard to any notice which is served on it under .