Macquarie Lightstation Heritage Management Plan 2020
In ForceCTH
Jurisdiction
Commonwealth
Collection
legislative instrument
Plain English Summary
6/10 complexity
This instrument is the Macquarie Lightstation Heritage Management Plan 2020, made under section 341S of the EPBC Act. It establishes binding management objectives, conservation policies, use rules, implementation priorities and monitoring arrangements to protect the Commonwealth Heritage values of the Macquarie Lightstation and its constituent buildings, grounds and archaeology. It governs the Harbour Trust’s decisions and constrains leaseholders (including AMSA and long‑term residential lessees) and contractors by requiring approvals, archaeological safeguards, contamination controls and ongoing reporting.
The Macquarie Lightstation Management Plan 2020 is a Harbour Trust instrument made under section 341S of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) to plan the protection and management of Commonwealth Heritage values at the Macquarie Lightstation (front page; Section 1). Mechanically the document performs three functions.
First, it records and articulates statutory obligations and site-specific policies. It reproduces the Harbour Trust’s interpretation of statutory duties under the Sydney Harbour Federation Trust Act 2001 (SHFT Act) and the EPBC Act, and maps those duties to site objectives and conservation policies (Sections 3.1, 3.5; Appendix D and E). The Plan is an EPBC Act management plan for Commonwealth Heritage Places prepared to satisfy Schedules 7A and 7B of the EPBC Regulations 2000 (Section 1; Appendix D and E).
Second, the Plan sets binding management outcomes and operational constraints for the Trust’s land at Macquarie Lightstation. It identifies the land parcels (Lots in DP 801240 and DP 811578), notes current leases and licensees (AMSA, long residential leases to 2116 and 2119, short-term leases for townhouses) and specifies permitted uses, access arrangements and conservation outcomes (Section 1.2; Sections 6.10, 7.1-7.6). The Plan contains 39 discrete conservation policies and prescriptive outcomes for buildings, landscape, archaeology, contamination, events, fencing, vegetation heights and services (Section 5.4, Policies 1-39; Sections 7 and 8).
Third, it operationalises monitoring, approval and implementation steps. It designates the Harbour Trust as the planning authority for actions on Trust land, requires Harbour Trust assessment of actions in accordance with the SHFT Act, Comprehensive Plan and EPBC Act, and establishes consultation, archaeological, hazardous materials and asset-recording processes. It sets a five year minimum review cycle under s341X of the EPBC Act and requires monitoring, record-keeping and community and Indigenous consultation (Sections 3.7, 9.1-9.5; Appendix D and E).
Current sections
Direct links to the current provisions in Macquarie Lightstation Heritage Management Plan 2020.
1
Source text: opening excerpt
Sourced from the Federal Register of Legislation (legislation.gov.au), CC BY 4.0.
meta-content-style-type: text/css
meta-content-type: application/xhtml+xml; charset=utf-8
meta-generator: Aspose.Words for .NET 22.10.0
title: Sydney Harbour Federation Trust
Environment Protection and Biodiversity Conservation Act 1999
MAKING OF THE MACQUARIE LIGHTSTATION HERITAGE MANAGEMENT PLAN 2020
I, MARY DARWELL, Executive Director, Sydney Harbour Federation Trust of the Department of the Environment, acting pursuant to section 341S of the Environment Protection and Biodiversity Conservation Act 1999, hereby make the Macquarie Lightstation Heritage Management Plan, to protect and manage the Commonwealth Heritage values of the Macquarie Lightstation Commonwealth Heritage place.
The Plan states its purpose in policy terms: to maintain the lighthouse as an operational navigation beacon, conserve and interpret Commonwealth Heritage values and maximise public access (Section 2). Those purpose-claims are explicit policy drivers in the Plan’s outcomes and conservation policies (Section 2; Section 5.4 Policy 30). Mechanically, therefore, the instrument prescribes how the Harbour Trust will exercise its planning authority and manage leases, site works, events, services, remediation, and interpretation on the 2.2 hectare site while complying with EPBC Act obligations (Section 4.1; Section 6.1; Section 7).
Who pays, who decides, and what changes in behaviour. The Harbour Trust is the decision-making authority for actions on Trust land and the primary implementer of works, monitoring and enforcement under the Plan (Sections 3.1, 3.7). The Australian Maritime Safety Authority (AMSA) remains the operational lessee for the lighthouse and retains maintenance responsibility under its lease; AMSA must be consulted for works affecting the lighthouse and must approve secondary uses (Sections 1.2, 7.1). Lessees of the residences hold long leases with specified covenants and constraints that limit building works and landscaping (Section 1.2; Section 6.10; Sections 7.2-7.3). The Harbour Trust funds remediation, conservation and some capital works, while rental income from the townhouses contributes to the Harbour Trust’s operations (Section 7.4; Implementation table, Section 8). Contractors and consultants undertaking works at the site are required to follow the Plan’s policies, the site-specific Environmental Management Plan prepared by Coffey, the Remediation Action Plan (GHD) and archaeological protocols (Section 6.5-6.6; Appendix C).
Behaviourally the Plan changes incentives by: requiring Harbour Trust approvals for alteration or excavation, imposing constraints on plantings and structures within leased areas, mandating archaeological assessment and Aboriginal consultation prior to ground disturbance, and restricting types of interpretation, events and installations within the compound to minimise heritage impacts (Policies 11, 13, 16, 19, 20, 26-29; Sections 7.6-7.11). The Plan also signals a longer term policy preference for removal of the townhouses to reveal archaeological footprints and improve distant views, while leaving the townhouses in place as a revenue source until removal is practicable (Section 7.4; Implementation, Section 8).
Main concepts
The Plan organises its management logic around three main concepts: statutory conformity and roles, conservation-led outcomes, and managed public access.
Statutory conformity and roles. The Plan situates the Harbour Trust as the authorised planning decision-maker on Trust land, operating under both the SHFT Act and the EPBC Act. It records the statutory protections that govern all actions on Trust land, in particular EPBC Act sections that protect the environment and heritage (the Plan explicitly cites s26 and s28 and the requirement in s341S for management plans, and s341ZC for the Trust to have regard to Commonwealth Heritage values before taking actions) (Section 3.5; Section 3.7). The Plan cross-references the Comprehensive Plan and the Harbour Trust’s own Heritage Strategy as higher level instruments that shape site-specific decisions (Sections 3.1-3.3).
Conservation-led outcomes. The Plan accepts and records the Commonwealth Heritage values that led to multiple Commonwealth listings for elements of the site: Macquarie Lighthouse and associated buildings, the Greenway retaining wall and the Macquarie Lighthouse Group (Appendix F; Section 5.1). It embeds the Conservation Management Plan (CMP 2018) by LSJ as the evidence base, using that CMP to establish ranked significance for fabric and to derive 39 conservation policies (Section 5.2; Section 5.4). These policies implement Burra Charter principles by requiring minimal intervention, use of skilled conservation professionals, like-for-like repair for high-significance fabric, and preservation of the site’s open, windswept landscape character (Policies 2, 3, 11, 12, 16, 23, 24).
Managed public access. The Plan prioritises maximising public access consistent with heritage protection. Public access is to continue across the grounds and guided interior tours of the lighthouse will continue via a tourist access licence with AMSA (Sections 2; 7.1). The Plan sets strict rules to protect views and setting, to limit physical intrusions within the compound (no large site furniture, limited signage, no new roads or car parking), and to manage events so they remain low impact and reversible (Policies 31, 38; Sections 7.6-7.10).
Other recurring technical concepts. Archaeological sensitivity is prominent. The Plan records previous archaeological testing and its findings, treats subsurface disturbance as a risk to both Aboriginal and historic archaeology, and prescribes monitoring, investigation by qualified archaeologists, and contractual clauses for unexpected discoveries (Section 5.2 Archaeological Assessments; Policies 19, 20; Section 9.1). Contamination management is another central technical feature: the Plan recounts the 2010-11 remediation, the site audit statement of 2011, the existence of residual contamination capped in situ, and requires compliance with Coffey’s Environmental Management Plan for any future ground disturbance (Section 6.5-6.6; Section 7.11). Asset management and documentation is also emphasised: the Trust will maintain inventory sheets, records of intervention and maintenance and incorporate these into its asset management system (Section 9.2; Policy 9).
Interlocking decision rules. Practically, the Plan imposes a decision cascade: (1) determine whether the action affects Commonwealth Heritage values; (2) if so, consult CMP and relevant guidelines (Significant Impact Guidelines 1.1 and 1.2 are referred to); (3) consult Department informally if unsure; (4) obtain Harbour Trust approvals and engage conservation specialists; (5) where actions may have significant impacts, refer to the Minister under EPBC Act for further assessment and approval (Policies 1, 9; Section 3.7). The Plan frames these as both operational protocols and compliance checks.
Spatial and use constraints. The Plan identifies specific spatial restrictions: the elevated compound around the lighthouse is to remain free of structures and large furniture; plantings within leased residential areas are limited to species that will not exceed 1 metre in height; fences will be realigned to reflect the original compound symmetry and the cliff-edge fence replaced with timber post and rail; townhouses are identified for possible long-term removal to reveal archaeological remains, but removal is low priority (Policies 16, 17, 31, 34, 36; Sections 7.1-7.4; 7.7).
Time horizon and review. The Plan is both immediate and long term. It records ongoing tasks (contamination management, service upgrades, monitoring), medium-term works (greenway wall reconstruction, vegetation works), and low-priority possibilities (townhouse removal, construction of a new structure to emulate the Engineer’s Quarters). The Plan will be reviewed at least every five years in accordance with s341X of the EPBC Act (Section 9.5).
Who it affects
Primary decision-makers and implementers. The Harbour Trust is the primary decision-maker and the planning authority for actions on Trust land (Section 3.7). It is responsible for approving works, managing leases, implementing conservation works, enforcing the Plan’s restrictions, and coordinating consultation with AMSA, lessees, Woollahra Council and Aboriginal groups (Sections 3.1, 3.7, 9.3-9.4).
AMSA. AMSA holds the lease/licence for the lighthouse (Lot 4 DP 801240) and is responsible for the operation and maintenance of the lighthouse as an Aid to Navigation (Section 1.2; Section 7.1). The Plan requires the Harbour Trust to coordinate with AMSA on any works affecting the lighthouse and notes that any secondary uses or work within the lighthouse require AMSA approval. The existing tourist access licence with AMSA allows the Harbour Trust to conduct tours but also requires prior AMSA permission for works (Section 6.10; Section 7.1).
Residential lessees. The Head Keeper’s Quarters and the Assistant Keepers’ Quarters are on very long leases (125 years, commencing 1991 and 1994 and expiring in 2116 and 2119 respectively) that contain covenants and development restrictions. Leases require compliance with specified management plans (for example the 1993 Plan of Management for the Head Keeper’s Quarters), and specify restricted planting and building rights in parts of Lot 1 in DP 811578 (Section 1.2; Section 6.10; Sections 7.2-7.3). Lessees must obtain Harbour Trust approval for works to interiors, exteriors or grounds (Sections 7.2-7.3). The Plan expressly limits use of these dwellings to private residential occupation and prohibits public access to interiors as a general rule (Policies 30, 33).
Harbour Trust staff, contractors and consultants. Conservators, archaeologists, engineers, remediation firms, landscape contractors and event suppliers who carry out work on site must comply with the Plan’s conservation policies and the Environmental Management Plan. The Plan requires skilled conservation personnel to be engaged and sets archaeological and hazardous materials protocols that must be incorporated into contracts and work briefs (Policies 3, 19, 20; Sections 6.5-6.6).
Local and state authorities. Woollahra Municipal Council and other local land managers are stakeholders where the Plan interacts with adjacent Crown or Council land such as Lighthouse Reserve and Christison Park. The Plan records the Harbour Trust’s intention to liaise with Council on matters such as access, the Coastal Walk, cliff-top fencing, and bus shelter relocation, but also notes that Harbour Trust land is excluded from State planning law under the SHFT Act, 2001 (Section 3.8; Sections 7.7-7.8).
Traditional Owners and Aboriginal stakeholders. The Plan records Aboriginal heritage sensitivity and the need for consultation with La Perouse Local Aboriginal Land Council and the Harbour Trust’s Aboriginal and Torres Strait Islander Advisory Group for works that might affect Aboriginal heritage. The Plan incorporates findings from Aboriginal archaeological assessments and requires Indigenous consultation for ground-disturbing works and interpretation of Aboriginal values (Section 4.3 Aboriginal Heritage; Policies 19, 26; Section 9.4).
Visitors, tourists and the public. The Plan maximises managed public access to external areas and guided interior tours, while limiting intrusive public infrastructure within the compound. Event organisers and visitors will face constraints on signage, structures, temporary installations and use of the grounds for events (Policies 31, 37, 38; Sections 7.6-7.10).
Who pays. Implementation costs are to be borne primarily by the Harbour Trust for works it decides to commission, with some costs borne by lessees for works within leased areas and by event hirers for damage or impacts caused by events (Policy 31.6; Implementation Section 8). The townhouses provide rental income to support Harbour Trust operations until removal is feasible (Section 7.4). Contractors and consultants engaged by the Trust or lessees will bear compliance costs embedded in contracts, such as archaeological monitoring and hazardous materials protocols (Policies 19, 20; Section 6.5).
Indirectly affected stakeholders. Transport for NSW and the Department responsible for public bus infrastructure are parties to be engaged if the bus shelter on Old South Head Road is to be relocated to preserve the historic view corridor (Policy 13; Section 7.7). Neighbouring residents are affected by fencing, vegetation and view protections that the Plan seeks to preserve, and by any short-term events authorised by the Trust.
Net behavioural changes. Licence-holders, lessees and contractors will need to adopt conservation-first practices, obtain Harbour Trust approvals for alterations, include archaeological and Aboriginal discovery clauses in contracts, and comply with the Coffey EMP when disturbing soils. Events organisers and visitors will see more constrained, heritage-sensitive access rules and fewer permanent public amenities in the compound (Policies 1-5, 19-21, 31, 38; Sections 7 and 9).
Key duties and rights
Statutory duties embedded in the Plan. The Plan structures duties around the Harbour Trust’s statutory obligations under the SHFT Act and the EPBC Act as recorded in the Plan. The Trust must manage Trust land so as to protect, conserve and interpret environmental and heritage values and to maximise public access consistent with those values (Sections 3.1-3.3). The Plan expressly requires the Harbour Trust to assess actions on its lands, to have regard for Commonwealth Heritage values before taking actions under s341ZC of the EPBC Act, and to consult with the Department for advice where the significance of impact is unclear (Sections 3.5, 3.7; Policy 1).
Harbour Trust approval powers. The Trust is the planning authority for actions on Trust land; this means Harbour Trust approval is required for works, adaptations, excavations, interpretation installations, events and any activity that may impact Commonwealth Heritage values (Section 3.7; Policy 9; Policy 33). Policy 9 sets out that the Harbour Trust must implement a rigorous decision-making process, record asset management decisions and consult AMSA and Woollahra Council where relevant.
Leases and lessees’ obligations. Long residential leases contain specific covenants and impose limits on alterations and plantings. The Plan reiterates that lessees must comply with their lease terms, the Harbour Trust’s management plan and obtain Harbour Trust approval for works affecting the interior, exterior or grounds (Section 6.10; Sections 7.2-7.3). The Assistant Keepers’ Quarters lease includes a Restricted Area where planting is restricted to low-growing shrubs not exceeding 1 metre (Section 6.10; Policy 17). The Head Keeper’s lease requires compliance with the 1993 Plan of Management as amended (Section 6.10).
AMSA’s duties and limited rights. AMSA’s lease obliges it to keep the lighthouse in good order and repair and in a safe condition (Section 7.1). AMSA maintains the lighthouse as an Aid to Navigation and follows its own heritage management systems. The Plan recognises AMSA’s operational role and requires Harbour Trust consultation with AMSA on works and interpretive material within the lighthouse; AMSA retains approval rights for any works inside the lighthouse and for secondary uses consistent with navigation safety (Section 7.1).
Archaeological and Aboriginal consultation duties. The Plan imposes duties to avoid excavation where possible, to engage suitably qualified archaeologists for necessary excavation, and to include contractual clauses requiring immediate cessation of works and notification to the Harbour Trust if relics are found (Policies 19, 20; Section 9.1). The Plan calls for consultation with the La Perouse Local Aboriginal Land Council and the Harbour Trust’s Aboriginal Advisory Group for actions impacting Aboriginal values (Policies 19 and 26; Section 9.4).
Contamination management obligations. The Harbour Trust has carried out remediation and continues to manage remnant contamination under the site audit statement and the Environmental Management Plan (Coffey, 2011). The Plan requires that any future disturbance of capped areas or works on sealed contaminated areas be done in accordance with the EMP and that excavation near boundaries be undertaken with caution because contaminated fill may be present on adjacent sites (Section 6.5-6.6; Section 7.11).
Event and temporary structure controls. The Plan authorises occasional, short-term, low-impact events subject to heritage protections. Event organisers must ensure minimal infrastructure, reversible impacts and are contractually liable for any damage to fabric (Policy 31; Section 7.6). Temporary/mobile structures are permitted if quickly removable and reversible and if they do not impact heritage values (Policies 37, 31).
Rights of public access and restricted rights. The Plan reconfirms the public’s right to access much of the grounds for passive recreation and coastal walk connectivity, but it restricts permanent additions that could obscure or diminish Commonwealth Heritage values. Interior access to the lighthouse is to continue in a managed way through guided tours; interior access to private residences is to remain restricted, consistent with long residential leases (Sections 2; 7.1; Policies 30-31).
Approval and referral to Minister. Where proposed actions are considered to potentially have a significant impact on the environment or heritage values, the Plan records that such proposals may be referred to the Minister for the Environment for further assessment and approval under the EPBC Act (Section 3.7; Policy 1). The Plan refers to the Significant Impact Guidelines 1.1 and 1.2 as decision aids (Policy 1).
Recordkeeping, monitoring and review duties. The Plan requires the Harbour Trust to record assets, maintain condition reports, preserve records of interventions and to review the Plan at least once every five years (Section 9.2-9.5; Policy 9). The Implementation table in Section 8 maps outcomes to priorities and supporting studies.
Who decides in practice and discretionary scope. The Harbour Trust decides day-to-day approvals and implementation priorities within the Plan’s policy framework, but the Plan also preserves discretion to consult with the Department or to refer proposals to the Minister when impacts may be significant (Section 3.7; Policies 1, 9). AMSA retains practical decision rights as the operational lessee for any internal lighthouse works (Section 7.1). Woollahra Council, Transport for NSW and Aboriginal organisations are consultative participants with influence but not final decision-making power over Trust land, except where statutory regimes outside the Harbour Trust’s control apply to adjacent Crown or Council land (Section 3.8; Section 7.7).
Penalties and enforcement
The Plan itself is a management instrument; it sets policies, procedures and approval protocols rather than specific criminal or civil penalties. Enforcement mechanisms and sanctions derive from the EPBC Act and the Harbour Trust’s administrative powers and leases, as recorded in the Plan.
Statutory enforcement context. The Plan records that all actions on Trust land are controlled by the EPBC Act, and it cites s26 and s28 which protect aspects of the environment and the environment from actions that may have significant impacts (Section 3.5). The Plan also records the requirement in s341ZC for the Harbour Trust to have regard for Commonwealth Heritage values before taking actions. The text sets out that where actions may have significant impacts, proposals will be referred to the Minister for the Environment for further assessment and approval under the EPBC Act (Section 3.7).
Administrative enforcement and approvals. As the planning authority for Trust land, the Harbour Trust controls approvals and may withhold permission for works that would adversely affect Commonwealth Heritage values or that do not comply with its policies. The Harbour Trust will include contractual clauses in contractor agreements requiring notification and cessation of works if relics or Aboriginal objects are found, and it will enforce lease covenants that require lessee compliance with the Plan, including obligations to maintain plants below 1 metre and to obtain Harbour Trust written consent prior to works (Policies 17, 19; Section 6.10; Section 7.2-7.3). Policy 31.6 states that lessees and hirers are responsible for damage or adverse impacts and that adherence to lease and contract conditions will be regularly monitored and corrective actions taken if required.
Remediation and environmental compliance. The Plan documents a completed remediation program and the Site Audit Statement which certified the site as suitable for residential, parks and recreational open space subject to compliance with the Environmental Management Plan (EMP) (Section 6.5). The EMP imposes operational controls on works in remediated or capped areas. Non‑compliance with EMP requirements would expose contractors and the Harbour Trust to environmental regulatory scrutiny under applicable Commonwealth environmental laws; the Plan however does not specify penalty amounts.
Heritage offences and Ministerial referral. The Plan acknowledges that the EPBC Act regulates actions relating to Commonwealth Heritage Places. Where actions may have significant impacts, the Minister’s approval process under the EPBC Act will apply, with consequences for failure to comply with the EPBC Act’s requirements. The Plan references the Significant Impact Guidelines 1.1 and 1.2 as tools to assess significance and referral thresholds (Policy 1; Appendix C).
Enforcement via leases and contracts. The Trust enforces many obligations through lease covenants: the Plan notes that the Head Keeper’s Quarters lease requires compliance with the 1993 Plan of Management and that the Assistant Keeper’s Quarters lease contains restricted area covenants and planting limitations (Section 6.10). The Plan further records that lessee non-compliance with lease conditions will be monitored and corrective action taken (Policy 9.5.6; Policy 31.6). Contractual clauses for contractors are required, for example to suspend works if relics are uncovered and to notify the Harbour Trust (Policies 19 and 20).
Monitoring and corrective measures. The Plan prescribes record-keeping and monitoring functions including asset management records, condition reports and a five-year statutory review cycle under s341X of the EPBC Act (Section 9.5; Policy 9). These monitoring mechanisms constitute administrative enforcement levers: the Harbour Trust can use monitoring results to vary approvals, require remedial work or suspend activities that threaten heritage values.
Limitations and absence of specific penalties in the Plan. The Plan does not itself specify criminal sanctions, fine amounts or precise enforcement procedures beyond administrative controls, contractual obligations, lease enforcement and referral to the EPBC Act process. Where the Plan refers to 'protection' or 'management', those terms take effect via Harbour Trust approvals, the EPBC Act referral and approval process, lease enforcement mechanisms, and compliance with the EMP. The Plan therefore relies on the broader Commonwealth legislative framework and contract law to effect penalties and remedies rather than containing standalone sanctioning provisions (Section 3.5; Section 6.5; Policies 19-21).
Practical enforcement risk and margin for discretion. The Plan centralises decision-making in the Harbour Trust and preserves discretion to consult the Department or refer to the Minister where impacts are uncertain or significant (Policy 1; Section 3.7). That discretion means outcomes can vary with interpretations of significance, quality of assessment work and the Trust’s resourcing to monitor compliance. The Plan attempts to reduce uncertainty by referencing mandatory processes (archaeological monitoring, EMP compliance, heritage specialist engagement) and by prescribing contractual clauses for on-site works (Policies 3, 19, 20).
How it interacts with other laws
Statutory primacy and exclusion. The Plan starts from the statutory premise that land vested in the Harbour Trust is excluded from State planning law, including State Environmental Planning Policies, REPs and Local Environmental Plans prepared by councils (Section 3.8). This means the Harbour Trust is the functional planning authority for Trust land and decides permitted uses and approvals on that land, subject to Commonwealth law such as the EPBC Act and any other applicable Commonwealth statutes (Sections 3.1, 3.8).
Commonwealth overlay: EPBC Act and EPBC Regulations. The Plan was made under s341S of the EPBC Act and is designed to satisfy the management-plan requirements in Schedules 7A and 7B of the EPBC Regulations 2000 (front page; Appendix D and E). It incorporates the Commonwealth Heritage management principles (Appendix E) and lists the EPBC sections that protect environmental and heritage values (s26, s28, s341ZC). The Plan uses the Significant Impact Guidelines 1.1 and 1.2 (as in force in 2013) to assess potential referrals under the EPBC Act (Policy 1; Appendix C).
Leases and contract law. The Plan operates in tandem with existing lease arrangements that allocate rights and obligations between the Harbour Trust, AMSA and private lessees. Those leases are private law instruments that survive the management plan, and the Plan explicitly references lease terms (e.g. long 125 year leases, Restricted Area covenants, obligations to comply with prior management plans) and requires that any works within leased areas require Harbour Trust written approval (Section 6.10; Sections 7.2-7.3). The Plan proposes to enforce many of its requirements through lease covenants and contract clauses that impose obligations on contractors and hirers (Policies 19-21, 31.6).
Heritage law interfaces. The Plan cross-references Commonwealth heritage listings (Appendix F) and the State Heritage Register listing for the site (Section 5.1). While Harbour Trust land is outside state planning legislation, the Plan states it seeks consistency with state and local planning instruments in order to observe best practice and coordinate with Woollahra Council and regional planning (Section 3.8; Sections 3.2-3.4). That coordination is particularly relevant for the Coastal Walk and adjoining Crown or Council reserves where policies and works will require liaison.
Environmental remediation and audit regimes. The Plan records remediation work undertaken in 2010-11, the 2011 Site Audit Statement certifying suitability for certain uses subject to the Coffey EMP, and ongoing management of capped contamination areas (Section 6.5-6.6). Environmental remediation and site audit processes are regulated by Commonwealth and state environmental rules and by accredited site auditors; the Plan requires compliance with the EMP for further disturbance. The Plan therefore overlays its approvals with the EMP’s operational controls when works risk exposing residual contamination.
Building codes and safety standards. The Plan notes the Building Code of Australia/BCA compliance assessment that was undertaken and that future long-term upgrading works to achieve BCA compliance for guided tours will be required in consultation with AMSA (Section 6.8). The Plan directs that temporary safety works have been implemented in a reversible and heritage‑sensitive way and that any long-term upgrades will be coordinated with AMSA.
Local government and adjacent Crown land. The Plan recognises that adjacent lands such as Lighthouse Reserve and Christison Park are managed by Woollahra Council and that coordinated management will be required for paths, fencing, sightlines, and access arrangements, including the access to the Assistant Keepers’ Quarters across Lighthouse Reserve (Sections 3.8; 6.2; 7.7-7.8). The Plan intends to follow relevant council DCP and local planning instruments where possible while preserving Harbour Trust decision-making powers.
Transport and public infrastructure law. The Plan notes the bus shelter on Old South Head Road that currently obstructs a historic view corridor and records an intention to liaise with Transport for NSW and Woollahra Council about potential relocation (Policy 13; Section 7.7). Such relocation would require coordination with those authorities and must respect their statutory responsibilities.
Indigenous heritage law. The Plan documents previous Aboriginal heritage surveys and records obligations to consult La Perouse Local Aboriginal Land Council for works that may affect Aboriginal objects, in accordance with the National Parks and Wildlife Act 1974 (NSW) standards used in the 2018 Aboriginal Archaeological and Historical Assessment (Section 4.3; Policies 19, 26; Section 9.4). Even though Trust land is outside state planning law, the Plan indicates the Trust will observe Aboriginal consultation processes and include clauses in contracts requiring notification and halt of works if Aboriginal objects are found.
Interplay of instruments. Practically, the Plan functions as an overlay which binds Harbour Trust decision-making and contracts on Trust land, but it does not displace private law in leases or the roles of other Commonwealth agencies where those agencies hold rights (for example AMSA’s operational obligations for navigation). Where actions trigger EPBC Act referral thresholds, the EPBC Act process and Ministerial determinations will supersede the Plan’s administrative approvals (Section 3.7; Policy 1).
Amendment history
Formal issuance and status. The Management Plan reproduced here was made under the EPBC Act by the Harbour Trust’s Executive Director and dated 9 October 2020 (front page). The Plan was reviewed by the Australian Heritage Council on 7 June 2019, adopted by the Harbour Trust Board on 17 September 2019 and came into force the day after publication on the Federal Register of Legislative Instruments (Section 1.1).
Plan succession and revocation record. The document contains a concise table of Harbour Trust management plans for Macquarie Lightstation that records the prior plan and the replacement chronology. The 2007 Macquarie Lightstation Management Plan commenced on 20 December 2007 and was revoked effective 8 October 2020. The current Plan commenced via the formal making and adoption process under the Comprehensive Plan and s341S of the EPBC Act and is dated 9 October 2020 (Harbour Trust Management Plans table, early in the Plan).
Linkage to the Harbour Trust Comprehensive Plan and Heritage Strategy. The Plan is explicitly prepared in accordance with the Harbour Trust’s Comprehensive Plan (2003, amended 2009) and in conformity with the Harbour Trust’s existing Heritage Strategy (prepared 2006 and amended 2016) (Sections 3.2-3.6). The Plan therefore sits in a hierarchy of Harbour Trust instruments and will be subject to review against more general policy changes to the Comprehensive Plan and Heritage Strategy.
Review schedule. The Plan prescribes that it will be monitored continuously and reviewed at least once in every five year period after adoption, in accordance with s341X of the EPBC Act, 1999 as amended (Section 9.5). The review is to assess ongoing consistency with Commonwealth Heritage management principles in force at the time.
Mechanism for future amendment. Although the Plan does not set out a specific amendment procedure within its text, its integration with the SHFT Act and the EPBC Act framework means that amendment would be undertaken by the Harbour Trust through its ordinary governance processes, including consultation with the Community Advisory Committee, Aboriginal advisory groups and the Department as required by the Comprehensive Plan’s consultation protocols (Sections 3.2-3.4; Policy 39). The Plan records that it will be updated to ensure that new Harbour Trust policies or guidelines do not adversely affect Commonwealth Heritage values, creating an explicit trigger for review if other Harbour Trust policies are developed (Section 3.4).
Record of implementing documents. The Plan’s Implementation table links specific outcomes to supporting studies and priorities (Section 8). That table provides a traceable schedule that can be used to monitor implementation and to inform amended priorities. The Plan also lists supporting technical studies and reports in Appendix C, which function as subordinate material that would typically be revised when circumstances change.
No other formal amendments recorded in the Plan. The Plan’s own historical record does not show any subsequent amendments after its adoption in 2019 and formal making in October 2020. The earlier 1993 Plan of Management is noted as being referenced in the Head Keeper’s Quarters lease and still having some residual validity (Section 3.8). Proposed changes to the site, such as the removal of townhouses, are recorded as long-term or low priority outcomes and would require further implementation steps that could include future amendments to the Plan (Section 7.4; Implementation table, Section 8).
Litigation history
The Plan does not record any litigation history. There are no judicial decisions, appeals or enforcement proceedings described in the text. The document is framed as a management and implementation instrument that relies on administrative approvals, lease enforcement and the EPBC Act referral and approval process rather than litigation. Where the Plan contemplates disputes or enforcement it references administrative corrective actions, contractual obligations and referral to the Minister for EPBC Act assessment where actions may have significant impacts (Section 3.7; Policy 31.6). If litigation were to arise it would most likely involve lease disputes, challenges to Harbour Trust approvals, or claims under the EPBC Act, but the Plan does not record any specific cases or litigation history.
Users should therefore assume no litigation record is available in or attached to the Plan. Any legal contestation would be external to this document and handled under the applicable statutes, leases and administrative law; the Plan anticipates and prescribes administrative processes intended to reduce the risk of contested decisions (Policies 9, 19, 20, 31).
Gotchas
Long leases constrain Trust flexibility. Two residential leases run until 2116 and 2119; these leases include restrictive covenants and obligations that substantially limit the Harbour Trust’s ability to reconfigure leased land without lessee consent or lease variation (Section 1.2; Section 6.10). If the Trust wishes to remove intrusive structures or alter leased areas, it may face legal and financial constraints.
“Maximise public access” sits alongside strict constraints inside the compound. The Plan repeatedly states a policy aim to maximise public access while simultaneously imposing tight restrictions on what can be installed in the compound, limiting interior public access to occasional guided tours and generally excluding public entry to private residences (Section 2; Policies 30, 31; Sections 7.1-7.3). Practitioners should not assume unfettered public use rights.
Archaeology and contamination create overlapping risk regimes. Ground-disturbing works trigger both archaeological protocols and contamination controls. The Plan requires archaeological assessment and monitoring for new ground disturbance and demands compliance with the Coffey EMP for remnant contamination (Policies 19-21; Sections 6.5-6.6; Section 9.1). Contractors may face simultaneous obligations to halt work on discovery of relics and to manage potentially contaminated soils.
AMSA has operational vetoes over lighthouse works. AMSA is the operator and maintainer of the lighthouse, and the Plan records that AMSA must approve secondary uses and that the tourist access licence and any works require AMSA permission (Section 6.10; Section 7.1). Harbour Trust proposals that affect the lighthouse interior or the navigation aid may be constrained by AMSA’s safety and operational priorities.
Removal of townhouses is aspirational and low priority. The Plan identifies removal of the townhouses as a long term, low priority outcome that would enhance views and reveal archaeological remains, but it also records that the townhouses generate rental income and are currently occupied on short-term leases (Section 7.4; Implementation table). Expect long lead times, funding needs and potential leaseholder disputes before removal can occur.
Restricted planting and vegetation height rules affect lessee amenity. Leases and the Plan limit plantings to a maximum 1 metre in height in leased areas in order to preserve sightlines to the lighthouse (Policies 16-17; Sections 7.2-7.3). Lessees may find landscaping options constrained, which can be a source of friction.
Safety and heritage trade-offs. The Plan discourages safety infrastructure that may be visually intrusive, favouring conservation solutions such as re-pointed Greenway crenellations as visual cues instead of handrails. That choice creates practical trade-offs between protecting people and preserving views or fabric and may require risk assessments to justify departures (Policy 14; Sections 7.7; 7.1).
Multiple consultees, overlapping jurisdictions. The Plan requires consultation with AMSA, Woollahra Council, Transport for NSW for bus shelter works, and the La Perouse LALC for Aboriginal matters (Policies 9, 13, 19, 39; Sections 7.7, 9.4). Coordinating those parties adds timing, resourcing and project-management overhead.
Record-keeping and monitoring obligations. The Plan requires maintenance of inventory sheets, asset records and a five-year review cycle (Section 9.2-9.5). Non-compliance with these administrative obligations may reduce the Trust’s ability to demonstrate due diligence in a legal or audit context.
Events are allowed but conditional. Short-term events are permissible, but the Plan requires minimal infrastructure, reversible impacts and contractual liability for damage (Policy 31). Event organisers and Harbour Trust staff must be attentive to heritage protection measures during event approvals.
The Plan does not set fines or criminal penalties. Enforcement relies on the EPBC Act enforcement regime, lease remedies and contract law. Practitioners should not expect enforcement tools inside the Plan itself; they must instead rely on statutory processes and contract enforcement.
Visual corridor and bus shelter are dependent on third parties. Policy 13’s objective to relocate the bus shelter depends on Transport for NSW and Council action and is not within the Trust’s unilateral control. Expect protracted negotiations and possible refusal.
How to comply
For Harbour Trust officers, lessees, AMSA, contractors and consultants, compliance requires an operational and documentary workflow that follows the Plan’s decision cascade. The following checklist translates the Plan’s policies and sections into practical steps.
Read and map applicable policies and site references. Start by locating the policies that bind your work: Policies 1-5 for general heritage duty, Policy 9 for decision-making process and record-keeping, Policies 19-21 for archaeology, Policies 16-17 for landscaping, Policy 31 for events, and Policy 38 for site furniture and facilities (Section 5.4).
Confirm land parcel and lease status. Before any proposal, confirm the relevant lot (Lots 1, 2, 4, 5, 6 in DP 801240 and DP 811578) and the lease obligations for that lot. Leased areas have specific covenants and require Harbour Trust written approval for works (Section 1.2; Section 6.10; Sections 7.2-7.3).
Screen for EPBC significance. Apply the Significant Impact Guidelines 1.1 and 1.2 as referenced in the Plan to determine whether a proposed action may have a significant impact on Commonwealth Heritage values and therefore requires referral to the Minister (Policy 1; Appendix C). For borderline cases, consult the Department informally as suggested.
Archaeological due diligence. If a proposal involves ground disturbance, obtain an archaeological assessment by a suitably qualified archaeologist before works commence. Include contractual clauses that require immediate cessation and notification to the Harbour Trust if relics or Aboriginal objects are discovered (Policies 19-20; Section 9.1). Provide for archaeological monitoring during excavation where required, and incorporate research objectives if disturbance is unavoidable (Policy 20).
Contamination controls. For any works in or near capped or remediated areas, comply with the Coffey Environmental Management Plan and the Remediation Action Plan. Undertake testing if groundwater extraction or subsurface work is proposed, and implement site-specific soil-handling protocols (Section 6.5-6.6; Section 7.11).
Heritage conservation methodology. Engage conservators and specialists for works affecting fabric of Exceptional, High or Moderate significance. For such works, use like-for-like materials where the policy requires it, and adopt the Burra Charter approach for decision-making (Policy 2; Policies 11, 15, 23-24). Ensure restoration and reconstruction works are identifiable on close inspection (Policy 29).
Obtain Harbour Trust written approvals. Secure written Harbour Trust approval for any works to interiors, exteriors or grounds of buildings, including temporary structures for events, any excavation, tree removal, or installation of interpretation. The Plan requires prior written approval for lessee works and for AMSA-endorsed changes inside the lighthouse (Sections 7.1-7.3; Policies 31, 37).
AMSA coordination for lighthouse works. If the work affects the lighthouse, contact AMSA early to secure its approval and to co-ordinate any safety and operational requirements. The lighthouse remains an operational Aid to Navigation and AMSA retains maintenance responsibilities (Sections 1.2; 7.1).
Contract clauses and inductions. Include standard clauses in contracts requiring compliance with the Management Plan, the EMP and archaeological protocols. Invite the La Perouse LALC to participate in site inductions for ground-disturbing works, and ensure workers are briefed on stop-work procedures for archaeological finds (Policies 19-20; Section 9.4).
Landscape and planting rules. For any planting within leased areas or public parts of the site, select species that will not exceed one metre in height, and document plant choices. Remove or prune intrusive trees only after Harbour Trust approval and in accordance with conservation policies for preserving sightlines (Policies 16-17; Sections 7.7).
Events and temporary structures. Apply for event approval with a heritage impact assessment and a plan showing minimal infrastructure, reversible impacts and protection measures for the Greenway wall and other significant fabric. Ensure lease and hiring agreements make hirers responsible for damage and compliance (Policy 31; Section 7.6).
Interpretation and signage. Use the unified design language recommended by Policy 28 for interpretive signage, avoid commercial advertising and locate signage to minimise visual intrusion. Coordinate the content of Aboriginal interpretation with Indigenous stakeholders (Policy 28).
Record-keeping and reporting. Maintain inventory sheets, condition reports and records of intervention, and upload them into the Harbour Trust’s asset management system. Keep documentation of approvals, monitoring reports, archaeological records and EMP compliance records for audit and the five-year statutory review (Policy 9; Section 9.2-9.5).
Seek informal Department advice where uncertain. Policy 1 recommends consulting the Department for informal advice before deciding whether to make a formal EPBC referral. Use this step to reduce the risk of a later referral or objection.
Plan for long-term constraints. Recognise that certain long-term outcomes, like removal of townhouses or construction of a new structure over the former Engineer’s Quarters footprint, are low-priority or contingent on future resource allocation and consultation. Manage expectations with lessees and the community accordingly (Section 7.4; Implementation Section 8).
Coordinate with adjacent land managers. Where proposals affect access across Lighthouse Reserve or sightlines across Council land, begin early liaison with Woollahra Council and Transport for NSW and document coordination steps in project files (Sections 6.9; 7.7).
Training and capacity. Ensure staff and contractors engaged on site receive training on the site’s heritage values and the Plan’s requirements, as mandated by Policy 4.
In sum, compliance requires combining statutory screening under the EPBC Act, Harbour Trust approvals and lease compliance, archaeological and contamination controls, specialist conservation methods, contractual safeguards and thorough record-keeping. The Plan provides a clear procedural framework and a set of technical references (CMP 2018, Coffey EMP, Remediation Action Plan, archaeological assessments) that must be followed to mitigate legal, environmental and heritage risk (Appendix C; Section 5.2; Sections 6.5-6.6).
The Sydney Harbour Federation Trust developed the Macquarie Lightstation Management Plan, and is grateful to all the organisations, individuals and members of the Community Advisory Committee for their invaluable comments and suggestions throughout the drafting period.
Authors
Staff of the Sydney Harbour Federation Trust.
A list of supporting studies is available at Appendix C of this Plan.
Acknowledgement
The Harbour Trust acknowledges the Traditional Owners of this land the Birrabirragal people, and pays its respects to elders past and present.
This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no part may be reproduced by any process without written permission from the Sydney Harbour Federation Trust.
Requests and enquiries concerning reproduction and rights should be addressed to:
Director – Marketing & Visitor Experience
Sydney Harbour Federation Trust
PO Box 607
Mosman, NSW 2088
Or email to info@harbourtrust.gov.au
For more information about the Sydney Harbour Federation Trust or to view this publication online, visit the website at: http://www.harbourtrust.gov.au
This publication should be cited as:
Sydney Harbour Federation Trust (2020). Macquarie Lightstation Management Plan 2019, Sydney Harbour Federation Trust, Sydney.
Harbour Trust Management Plans for Macquarie Lightstation
Date Commences
Date Revoked
Plan Name
Comments
20 December 2007
8 October 2020
Macquarie Lightstation Management Plan
Made and adopted in accordance with the Harbour Trust’s Comprehensive Plan.
9 October 2020
Macquarie Lightstation Management Plan 2020
Made and adopted in accordance with the Harbour Trust’s Comprehensive Plan and section 341S of the Environment Protection and Biodiversity Conservation Act 1999.<br>This Plan includes updates to site conditions and relevant NSW and local plans.<br>The Plan commenced on the day after it was published on the Federal Register of Legislative Instruments.
SECTION 1 – INTRODUCTION – COVER PAGE
1. Introduction
Section 1 sets out the requirement for and the purpose of this Management Plan and provides an introduction to the land to which this Management Plan applies.
On 21st August 2003 the Minister for the Environment and Heritage (now the Department of the Environment and Energy) approved a Comprehensive Plan for the then seven harbour sites managed by the Sydney Harbour Federation Trust. The plan, which was prepared in accordance with the requirements of the Sydney Harbour Federation Trust Act 2001, sets out the Harbour Trust’s vision for the harbour sites under its control.
A requirement of the Harbour Trust’s Comprehensive Plan is that more detailed management plans are prepared for specific precincts, places or buildings. In addition to this the Environment Protection and Biodiversity Conservation (EPBC) Act 1999 also requires the Harbour Trust to make plans to protect and manage the Commonwealth Heritage values of Commonwealth Heritage Places that it owns. Macquarie Lightstation (which refers to the Lighthouse and ancillary buildings) is identified on the Commonwealth Heritage List as one of these places.
Accordingly, the purpose of this Management Plan is to guide the outcomes proposed in the Harbour Trust’s Comprehensive Plan and to satisfy the requirements of Schedule 7A and 7B of the EPBC Regulations 2000 and to be consistent with the Heritage Management Principles.
The Macquarie Lighthouse is a working maritime safety structure. It is this function which gives it such significance, reminding us that this is a harbour city which from its colonial infancy has relied on its links to the outside world. The Comprehensive Plan proposes to continue this working function, enhance the landmark qualities of the site and to improve its relationship with the adjacent coastal walk and cliff top parkland. It also proposes to continue and improve public access and to interpret the many phases of history of the site.
The vision for the site is a place where the Macquarie Lightstation’s position as an important attraction along the coastal walk and as a prominent harbour landmark is preserved and enhanced. The site’s rich cultural heritage, including its early Aboriginal occupation will be protected and interpreted.
1.1. Commencement Date
This plan was reviewed by the Australian Heritage Council at its meeting on 7 June 2019. The Council agreed that the plan as drafted is not inconsistent with the Commonwealth Heritage Management Principles and the requirements of the Environment Protection and Biodiversity Conservation Act 1999. The Plan was adopted by the Harbour Trust Board on 17 September 2019 and came into force the day after it was published on the Federal Register of Legislative Instruments.
1.2. Land to which the Management Plan Applies
The land covered by the Management Plan is shown by broken black edging on the plan at Figure 1, described as Lots 1, 4, 5 and 6 in DP 801240 and Lots 1 and 2 in DP 811578. All of the land is owned by the Sydney Harbour Federation Trust.
The Australian Maritime Safety Authority (AMSA) has a lease over Lot 4 in DP 801240 until 2023, and is responsible for the operation of the Lighthouse.
Lot 1 in DP 801240 and Lot 1 in DP 811578 (the Assistant Keepers’ Quarters) and Lot 5 in DP 801240 (the Head Keeper’s Quarters) are leased as private residences with leases expiring in 2116 and 2119 respectively.
Updated figure
Figure 1 – Management Plan Area
SECTION 2 – AIMS OF THIS PLAN – COVER PAGE
2. Aims of this Plan
Section 2 outlines the aims of this Management Plan.
The aims of this Management Plan are to:
Maintain the continuing operation of the Lighthouse as a navigation beacon;
Conserve and interpret the Commonwealth Heritage values of the Macquarie Lightstation and to facilitate its interpretation and appreciation as a landmark historic place in Sydney; and
Maximise public access.
In doing this it also aims to:
Be consistent with Commonwealth Heritage management principles;
Conserve and enhance the landmark qualities of the site and important views to and from the site and retain historic visual connections to the lighthouse lantern;
Improve the relationship of the site with adjoining public open space and coastal walk;
Interpret the original Greenway Palladian-style Lightstation and compound, and the quarry;
Retain the open windswept character of the site and ensure that plantings and vegetation do not obstruct important historical sightlines;
Improve vehicular access to the Head Keeper’s Quarters;
Provide visitor facilities and amenities including toilets, interpretation and gathering areas;
Improve the reticulation of existing services on the site including stormwater, water and power;
Appropriately manage any remnant site contamination and hazardous materials;
Improve the management of stormwater runoff;
Apply the principles of Ecologically Sustainable Development (ESD); and
Address any potential consequences of climate change.
SECTION 3 – PLANNING FRAMEWORK– COVER PAGE
3. Planning Framework
Section 3 outlines the planning framework that will guide the future use of the Macquarie Lightstation Precinct.
3.1. Sydney Harbour Federation Trust Act 2001
The objects of the Harbour Trust are set by the Sydney Harbour Federation Trust Act 2001 (SHFT Act), which are to:
Ensure that management of Trust land contributes to enhancing the amenity of the Sydney Harbour region
Protect, conserve and interpret the environmental and heritage values of Trust land
Maximise public access to Trust land
Establish and manage suitable Trust land as a park on behalf of the Commonwealth as the national government
Co-operate with other Commonwealth bodies that have a connection with any harbour land in managing that land
Co-operate with New South Wales, affected councils and the community in furthering the above objects.
The SHFT Act defines land that is vested in the Harbour Trust as ‘Trust land’ and surrounding land as ‘Harbour Land’. The SHFT Act requires the Harbour Trust to prepare a Plan (the Comprehensive Plan) for Trust land which may also cover Harbour land. The Comprehensive Plan, prepared in 2003, recognises the strategic value in its lands by allowing the Harbour Trust to take an holistic approach to its planning through the development of objectives, policies and outcomes to be implemented across its sites. This Management Plan furthers these objects.
3.2. Harbour Trust Comprehensive Plan
The Harbour Trust’s Comprehensive Plan, which commenced in 2003 and was amended in 2009, is a broad strategic plan which sets out the vision for all of the Harbour Trust’s sites and includes a process for preparing more detailed Management Plans for specific places, such as Macquarie Lightstation.
The Comprehensive Plan provides a framework for maintaining the site’s position as an important attraction along the Coastal Walk, and as a prominent landmark for all to see. It also seeks to preserve and enhance the site into the future, by removing intrusive structures and interpreting and conserving significant archaeological remains.
Unchanged figure
Figure 2 – Harbour Trust Comprehensive Plan –Outcomes
The Outcomes diagram in Part 10 of the Harbour Trust’s Comprehensive Plan for Macquarie Lightstation is reproduced at Figure 2.
The Comprehensive Plan sets out overarching Objectives and Policies for all of its sites (Part 3). Those that are most relevant to this Management Plan are: Ecologically Sustainable Development (ESD); cultural heritage; adaptive re-use of places and buildings; removal of buildings; design approach; tourism; contamination; water quality and catchment protection; access, open space and recreation; funding and management of leases; consultation and communities. The ways in which these objectives and policies will be implemented are covered throughout this Plan.
Part 3 also sets out Objectives and Policies for Consultation and Communications. Management Plans (including this Plan) will be prepared in consultation with the Harbour Trust’s Community Advisory Committee (CAC), the broad community, the Local Aboriginal Land Council, special interest groups, and Local, State and Commonwealth Governments.
Harbour Trust Management Plans are site-specific plans that refine and detail the site objectives and outcomes established in the Comprehensive Plan. They identify desired outcomes, suitable land uses, and how a site’s environmental and heritage values should be protected and interpreted.
This Management Plan describes specific outcomes for the Macquarie Lightstation. It interprets the Harbour Trust’s Comprehensive Plan and guides its implementation by providing more explicit detail about the way the site is used, interpreted and conserved.
This Management Plan is to be read in conjunction with the SHFT Act and Comprehensive Plan, in particular the Outcomes identified in Part 10 (see Figure 2 of this Plan), and the Objectives and Policies in Part 3 of the Comprehensive Plan.
3.4. Related Harbour Trust Policies and Guidelines
There are a number of overarching Policies and Guidelines foreshadowed in the Harbour Trust’s Comprehensive Plan that will be developed over the lifetime of the Harbour Trust and that will also guide the development of the Macquarie Lightstation. Current relevant policies are:
The Harbour Trust’s Corporate Plan;
The Harbour Trust’s Reconciliation Action Plan;
The Harbour Trust’s Rental Subsidy Policy for Contributory and Delivery Partners;
The Harbour Trust’s Leasing of Land and Buildings to Community Users Policy;
The Harbour Trust’s Event Policy; and
The Harbour Trust’s Heritage Strategy; and
The Harbour Trust’s draft Access Policy.
This Management Plan has regard for these existing policies. If or when other Harbour Trust Policies and Guidelines are developed this plan will be reviewed to ensure that they do not impact adversely on the Commonwealth Heritage values.
3.5. Environment Protection and Biodiversity Conservation Act 1999
All ‘actions’ on Trust land, undertaken by either the Harbour Trust or on behalf of the Harbour Trust, are controlled by the Environment Protection and Biodiversity Conservation (EPBC) Act, 1999, as amended.
Section 26 of the EPBC Act protects all aspects of the environment on Trust land from actions taken either on the Harbour Trust’s land or on adjoining land that may have a significant impact on it, while Section 28 protects the environment from any
This is an opening excerpt, not the complete document.