60ZZPMajor project permit may be granted subject to conditions or restrictions
Start here
Get a plain-English read of 60ZZP
Turn the raw legal text into a practical explanation grounded in Land Use Planning and Approvals Act 1993.
### 60ZZP Major project permit may be granted subject to conditions or restrictions
> [*\[Section 60ZZP Inserted by No. 21 of 2020, s. 12, Applied:28 Oct 2020\]*](/view/html/inforce/2020-10-28/act-2020-021#GS12@EN)
>
> > (1) The Panel may impose conditions or restrictions on a major project permit granted under [section 60ZZM(1)(a)](#GS60ZZM@Gs1@Hpa@EN) .
>
> > (2) In addition to imposing under [subsection (1)](#GS60ZZP@Gs1@EN) any conditions or restrictions on a major project permit that are required under [subsection (4)](#GS60ZZP@Gs4@EN) to be imposed on a major project permit, the Panel may, subject to [subsection (5)](#GS60ZZP@Gs5@EN) , impose under [subsection (1)](#GS60ZZM@Gs1@EN) any conditions or restrictions that, in the opinion of the Panel, are necessary or desirable for the effective and appropriate use or development of land.
>
> > (3) In deciding whether to impose under [subsection (1)](#GS60ZZM@Gs1@EN) conditions or restrictions on a major project permit to be granted in relation to the major project, the Panel must consider –
> >
> > > > (a) the conditions and restrictions that a participating regulator requested, in a final advice under [section 60ZZF(1)](#GS60ZZF@Gs1@EN) , the Panel to impose on a major project permit in relation to the project; and
> > >
> > > > (b) any representations made under [section 60ZZD(1)](#GS60ZZD@Gs1@EN) in relation to such conditions or restrictions; and
> > >
> > > > (c) any matters raised in hearings in relation to the major project.
>
> > (4) The Panel must, under [subsection (1)](#GS60ZZP@Gs1@EN) , impose on a major project permit granted under [section 60ZZM(1)(a)](#GS60ZZM@Gs1@Hpa@EN) any conditions or restrictions that a participating regulator that is a relevant regulator in relation to the [Aboriginal Heritage Act 1975](/view/html/inforce/2026-04-12/act-1975-081) or the [Threatened Species Protection Act 1995](/view/html/inforce/2026-04-12/act-1995-083) , requests the Panel, in a final advice under [section 60ZZF(1)](#GS60ZZF@Gs1@EN) , to impose on the permit.
>
> > (5) The Panel must not impose on a major project permit a condition or restriction that is inconsistent with a condition or restriction that the Panel must, under [subsection (4)](#GS60ZZP@Gs4@EN) , impose.
>
> > (6) The conditions that may be imposed on a major project permit include, but are not limited to including, a condition that all reasonable steps must be taken to enter into an agreement in respect of a use or development forming all or part of the project to which the permit relates.
>
> > (7) If a condition referred to in [subsection (6)](#GS60ZZP@Gs6@EN) is imposed on a major project permit, the Panel must specify on the major project permit the matters, and the requirements in respect of those matters, to be included in the agreement.
>
> > (8) If –
> >
> > > > (a) a person is granted a major project permit on which is imposed a condition, referred to in [subsection (6)](#GS60ZZP@Gs6@EN) , that all reasonable steps must be taken to enter into an agreement; and
> > >
> > > > (b) that person is not the owner of all of the land in respect of which the agreement must be entered into –
> >
> > the Panel must, within 7 days of granting the permit, serve on each other owner of the land notice of the Panel's decision to impose the condition.
>
> > (9) [*\[Section 60ZZP Subsection (9) substituted by No. 33 of 2022, s. 27, Applied:17 May 2023\]*](/view/html/inforce/2023-05-17/act-2022-033#GS27@EN) If a condition or restriction is imposed under [subsection (1)](#GS60ZZP@Gs1@EN) on a major project permit in accordance with [subsection (4)](#GS60ZZP@Gs4@EN) , the Panel must designate on the permit the relevant regulator, or relevant regulators, if any, that has or have the responsibility under [section 60ZZZD(4)](#GS60ZZZD@Gs4@EN) for the enforcement of the condition or restriction.
>
> > (10) [*\[Section 60ZZP Subsection (10) inserted by No. 33 of 2022, s. 27, Applied:17 May 2023\]*](/view/html/inforce/2023-05-17/act-2022-033#GS27@EN) Without limiting the conditions or restrictions that may be imposed under [subsection (1)](#GS60ZZP@Gs1@EN) on a major project permit otherwise than in accordance with [subsection (4)](#GS60ZZP@Gs4@EN) , such a condition or restriction may specify that –
> >
> > > > (a) plans, information, designs, or other documents, are required, under the condition or restriction, to be prepared and provided to the Panel or a planning authority; and
> > >
> > > > (b) particular actions or works are to be carried out to the satisfaction of the Panel or a planning authority –
> >
> > and, if such a condition or restriction refers to the Panel, then, after the major project permit has taken effect, the reference in the condition or restriction to the Panel is taken to be a reference to the Commission.