60ZZCNotification in relation to major project
Start here
Get a plain-English read of 60ZZC
Turn the raw legal text into a practical explanation grounded in Land Use Planning and Approvals Act 1993.
### 60ZZC Notification in relation to major project
> [*\[Section 60ZZC Inserted by No. 21 of 2020, s. 12, Applied:28 Oct 2020\]*](/view/html/inforce/2020-10-28/act-2020-021#GS12@EN)
>
> > (1) The Panel, within 14 days after preparing under [section 60ZZA(1)](#GS60ZZA@Gs1@EN) the initial assessment report in relation to the major project, must give a notice in relation to the major project to –
> >
> > > > (a) the proponent of the major project; and
> > >
> > > > (b) if the proponent is not the owner of all of the land on which the major project is to be situated – the owners of the parts of the land that the proponent does not own; and
> > >
> > > > (c) the owners of, the occupiers of, and the lessees of, any part of land adjoining the land on which the major project is to be situated; and
> > >
> > > > (d) each participating regulator in relation to the major project; and
> > >
> > > > (e) each person who has made a representation under [section 60ZL(2)](#GS60ZL@Gs2@EN) in relation to the draft assessment criteria in relation to the major project; and
> > >
> > > > (f) the council that is the relevant planning authority in relation to the major project; and
> > >
> > > > (g) each council that is not a relevant planning authority in relation to the major project but that is the council for a municipal area that is in the regional area, or regional areas, in which the major project is to be situated; and
> > >
> > > > (h) if the major project is to be situated on an area of land that is not within any municipal area – all councils for an area of land in a regional area that is adjacent to the area of land in which the major project is to be situated; and
> > >
> > > > (i) all State Service Agencies and Tasmanian Government Businesses that have been notified of the major project under [section 60ZJ(1)](#GS60ZJ@Gs1@EN) ; and
> > >
> > > > (j) if all or part of the land on which the major project is to be situated is in Wellington Park – the Wellington Park Management Trust.
>
> > (2) The notice under [subsection (1)](#GS40W@Gs1@EN) in relation to a major project is to –
> >
> > > > (a) contain the information, in relation to the major project, that is specified in relation to the major project in the notice referred to in [section 60ZZB(4)](#GS60ZZB@Gs4@EN) ; and
> > >
> > > > (b) invite the person to whom the notice is given to make a representation in relation to the major project.
>
> > (3) The Panel must, within 14 days after preparing under [section 60ZZA(1)](#GS60ZZA@Gs1@EN) the initial assessment report in relation to the major project, give to the proponent a copy of the report.