### 35K Modifications to draft LPS
> [*\[Section 35K Inserted by No. 47 of 2015, s. 10, Applied:17 Dec 2015\]*](/view/html/inforce/2015-12-17/act-2015-047#GS10@EN)
>
> > (1) The Commission, after complying with [section 35J](#GS35J@EN) in relation to a draft LPS in relation to the municipal area of a planning authority, may –
> >
> > > > (a) by notice to the planning authority, direct the planning authority to modify the draft LPS in the manner specified in the notice; or
> > >
> > > > (b) modify the draft LPS itself and notify the planning authority of the Commission's modification; or
> > >
> > > > (c) [*\[Section 35K Subsection (1) amended by No. 7 of 2021, s. 15, Applied:14 Jul 2021\]*](/view/html/inforce/2021-07-14/act-2021-007#GS15@Hpa@EN) by notice to the planning authority, reject the draft LPS and direct the planning authority to submit to the Commission a substitute draft LPS within 28 days, or a longer period allowed by the Commission, from the date of the notice.
>
> > (2) If a planning authority is directed under [subsection (1)(a)](#GS35K@Gs1@Hpa@EN) to modify a draft LPS –
> >
> > > > (a) the planning authority must undertake the modification in accordance with the direction and submit the modified draft LPS to the Commission within 28 days or a longer period allowed by the Commission; and
> > >
> > > > (b) the Commission may, if it is not satisfied with a modified draft submitted to the Commission under [paragraph (a)](#GS35K@Gs2@Hpa@EN) , issue a further notice under [subsection (1)](#GS35K@Gs1@EN) in relation to the draft LPS to which the modifications relate; and
> > >
> > > > (c) [*\[Section 35K Subsection (2) amended by No. 7 of 2021, s. 15, Applied:14 Jul 2021\]*](/view/html/inforce/2021-07-14/act-2021-007#GS15@Hpb@EN) the period referred to in [section 35L(3)](#GS35L@Gs3@EN) in relation to a draft LPS to which a report under [section 35F(1)](#GS35F@Gs1@EN) applies does not run until the modified draft LPS is submitted to the Commission under [paragraph (a)](#GS35K@Gs2@Hpa@EN) .
> > >
> > > > (d) [*\[Section 35K Subsection (2) amended by No. 7 of 2021, s. 15, Applied:14 Jul 2021\]*](/view/html/inforce/2021-07-14/act-2021-007#GS15@Hpc@EN) . . . . . . . .
>
> > (3) [*\[Section 35K Subsection (3) amended by No. 7 of 2021, s. 15, Applied:14 Jul 2021\]*](/view/html/inforce/2021-07-14/act-2021-007#GS15@Hpd@EN) If the Commission issues under [subsection (1)(c)](#GS35K@Gs1@Hpc@EN) a direction, in relation to a draft LPS (***the original draft LPS***), requiring a planning authority to submit to the Commission a substitute draft LPS –
> >
> > > > (a) the direction is taken to be a direction of the Minister under [section 35(2)](#GS35@Gs2@EN) to submit to the Commission a draft LPS; and
> > >
> > > > (b) this Division ceases to apply to the original draft LPS.
>
> > (4) [*\[Section 35K Subsection (4) omitted by No. 7 of 2021, s. 15, Applied:14 Jul 2021\]*](/view/html/inforce/2021-07-14/act-2021-007#GS15@Hpe@EN) . . . . . . . .