[Section 12F Inserted by No. 36 of 2018, s. 7, Applied:17 Dec 2018]
(1) The Commission, as soon as practicable after the end of the exhibition period in relation to a draft of the TPPs –
(a) must consider whether it is satisfied that the draft of the TPPs meets the TPP criteria; and
(b) is to consider whether there are any matters of a technical nature, or that may be relevant, in relation to the application of the TPPs to –
(i) the Tasmanian Planning Scheme; or
(ii) each regional land use strategy –
if the TPPs were made under section 12G(2) in the terms of the draft of the TPPs; and
(c) may, if it thinks fit, hold one or more hearings in relation to the representations received under section 12E .
(2) The Commission, within 90 days, or a longer period allowed by the Minister, after the end of the exhibition period in relation to a draft of the TPPs, must provide to the Minister a report in relation to the draft of the TPPs.
(3) The report in relation to a draft of the TPPs is to contain –
(a) a summary of the issues raised in the representations in relation to the draft of the TPPs; and
(b) a statement as to whether the Commission is satisfied that the draft of the TPPs meets the TPP criteria; and
(c) a statement as to whether there are any matters of a technical nature, or that may be relevant, in relation to the application of the TPPs to –
(i) the Tasmanian Planning Scheme; or
(ii) each regional land use strategy –
if the TPPs were made under section 12G(2) in the terms of the draft of the TPPs.