Mechanically, the Lachlan Local Environmental Plan 2013 sets zoning, permitted/prohibited uses, consent pathways, maps and local schedules for land in Lachlan. It defines exempt and complying development, subdivision standards, heritage and environmental controls and names the Council as the consent authority.
The Plan states it aims to protect agriculture and heritage and to promote housing, services and sustainable growth (cl 1.2). Those aims impose consent tests, technical and environmental requirements on applicants; discretionary approvals and local exceptions create compliance costs for landowners and developers.
This instrument is a local environmental plan (LEP) for the Lachlan local government area that sets the statutory framework for land use and development on the land identified in the Land Application Map. Mechanically it:
Declares its commencement and territorial scope (cl 1.1AA; cl 1.3).
Repeals prior local environmental plans and deemed instruments that applied solely to the land now covered by this LEP (cl 1.8).
Allocates land into named zones and publishes a Land Zoning Map and other maps that determine permitted uses, lot sizes and special overlays (cl 2.1; cl 2.2; cl 1.7).
Establishes a Land Use Table that lists, for each zone, objectives, development that is permitted without consent, development that is permitted with consent and development that is prohibited (cl 2.3; Land Use Table).
Specifies exempt and complying development classes via Schedules 2 and 3 and by reference to State SEPPs, and sets rules for where exempt/complying development is excluded (Part 3, cls 3.1-3.3).
Sets principal development standards regarding minimum subdivision lot sizes, special exceptions, rural subdivision flexibility, and a range of rules affecting dwellings in rural zones (Part 4, cls 4.1-4.6 and related clauses).
Identifies several local controls and requirements on matters such as earthworks, stormwater, biodiversity, groundwater vulnerability, wetlands, essential services and flood planning (Part 6, cls 6.1-6.7; cl 5.21).
Establishes a range of additional local provisions relevant to particular industries and activities including intensive livestock agriculture, aquaculture, eco-tourism, farm stay and farm gate premises, and controls for licensed premises and musical performance (Part 5, cls 5.13-5.20; Sch 6).
Current sections
Direct links to the current provisions in Lachlan Local Environmental Plan 2013.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Land Use tbl: Am 2019 (137), Sch 6 [1]; 2022 (314), Sch 1; 2023 (458), Sch 2.49[1] [2].
Zone RU1 Primary Production
Zone RU3 Forestry
Zone RU5 Village
Zone R5 Large Lot Residential
Zone SP2 Infrastructure
Zone RE1 Public Recreation
Zone C1 National Parks and Nature Reserves
Zone W1 Natural Waterways
Zone W2 Recreational Waterways
3
Permitted with consent
3 Permitted with consent
3 Permitted with consent
Agritourism; Air transport facilities; Airstrips; Animal boarding or training establishments; Aquaculture; Bed and breakfast accommodation; Boat launching ramps; Boat sheds; Camping grounds; Caravan parks; Cellar door premises; Cemeteries; Charter and tourism boating facilities; Community facilities; Correctional centres; Crematoria; Depots; Dual occupancies (attached); Dwelling houses; Eco-tourist facilities; Educational establishments; Environmental facilities; Extractive industries; Farm buildings; Farm stay accommodation; Freight transport facilities; Heavy industrial storage establishments; Helipads; Highway service centres; Home-based child care; Home industries; Industrial training facilities; Information and education facilities; Intensive livestock agriculture; Jetties; Kiosks; Landscaping material supplies; Moorings; Open cut mining; Plant nurseries; Recreation areas; Recreation facilities (major); Recreation facilities (outdoor); Roads; Roadside stalls; Rural industries; Rural workers’ dwellings; Secondary dwellings; Service stations; Timber yards; Veterinary hospitals; Water recreation structures; Wharf or boating facilities
4
Prohibited
4 Prohibited
4 Prohibited
Any development not specified item 2 or 3
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Part 6
Additional local provisions
Part 6 Additional local provisions
Part 6 Additional local provisions
6
Earthworks
6 Earthworks
6.1 Earthworks
(1) The objective of this clause is to ensure that earthworks for which development consent is required will not have a detrimental impact on environmental functions and processes, neighbouring uses, cultural or heritage items or features of the surrounding land.
(2) Development consent is required for earthworks unless—
(a) the earthworks are exempt development under this Plan or another applicable environmental planning instrument, or
(b) the earthworks are ancillary to development that is permitted without consent under this Plan or to development for which development consent has been given.
(3) Before granting development consent for earthworks (or for development involving ancillary earthworks), the consent authority must consider the following matters—
(a) the likely disruption of, or any detrimental effect on, drainage patterns and soil stability in the locality of the development,
(b) the effect of the development on the likely future use or redevelopment of the land,
(c) the quality of the fill or the soil to be excavated, or both,
(d) the effect of the development on the existing and likely amenity of adjoining properties,
(e) the source of any fill material and the destination of any excavated material,
(f) the likelihood of disturbing relics,
(g) the proximity to, and potential for adverse impacts on, any waterway, drinking water catchment or environmentally sensitive area,
(h) any appropriate measures proposed to avoid, minimise or mitigate the impacts of the development.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
sch.2-sec
Advertisements and advertising structures
sch.2-sec Advertisements and advertising structures
Advertisements and advertising structures
(1) Erection of an advertising structure and the display of an advertisement on it, or the display of an advertisement, in any of the following circumstances—
(a) the advertisement and any structure are not visible from the outside of the site on which they are displayed,
(b) the advertisement is behind the glass line of a shop or window,
(c) the content of the advertisement relates to the lawful use of the premises on which it is displayed,
(d) the advertisement is a real estate sign advertising that the premises on which it is displayed are for sale or lease.
(2) The advertisement must not be illuminated if located in Zone RU5 Village or Zone R5 Large Lot Residential. This subclause does not apply to an advertisement that is not visible from the outside of the site on which it is displayed.
(3) Maximum height of an advertisement and any associated advertising structure relating to the lawful use of premises on which they are displayed—
(a) in the case of an advertisement and any associated advertising structure that are suspended from an awning that is above a public road—2.7m above ground level (existing), or
(b) in the case of an advertisement affixed to a wall and below (and completely detached from) an awning—the height of the underside of the awning, or
(c) in any other case—3m above ground level (existing).
(4) Maximum area of an advertisement (other than a real estate sign) and any associated advertising structure relating to the lawful use of premises—
(a) 0.75m2 in Zone RU1 Primary Production, Zone RU5 Village and Zone R5 Large Lot Residential, or
(b) 2.5m2 in any other zone.
(5) Maximum area of a real estate sign and any associated advertising structure—4.0m2 on land in any zone.
(6) A real estate sign and any associated advertising structure must not be displayed for longer than 14 days after the date of sale or lease of the premises concerned.
(7) No more than two real estate signs are permitted to be displayed at any one time on the premises concerned.
(8) Subclauses (3)–(7) do not apply to—
(a) an advertisement and any structure that are not visible from the outside of the site on which they are displayed, or
(b) an advertisement that is behind the glass line of a shop or window.
Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
(Clause 5.2)
sch 4: Am 2017 (72), cl 4.
Schedule 5
Environmental heritage
Schedule 5 Environmental heritage
Schedule 5 Environmental heritage
(Clause 5.10)
| Locality | Item name | Address | Property description | Significance | Item no |
| Albert | Albert General Cemetery | Melrose Road | Lot 7009, DP 1024420 | Local | I1 |
| Bena | Cemetery | Condobolin Road | Lot 7037, DP 1029677 | Local | I2 |
| Condobolin | Community centre (former Commercial Hotel) | 23 Bathurst Street (corner Denison Street) | Lot 189, DP 534875 | Local | I8 |
| Condobolin | Court house | 25 Bathurst Street | Lot 7302, DP 1143144 | Local | I9 |
| Condobolin | Post office | 33 Bathurst Street | Lot 1, DP 747334 | Local | I15 |
| Condobolin | Lachlan Shire Museum (former Shire Hall) | 35 Bathurst Street | Lot 1, DP 1134993 | Local | I12 |
| Condobolin | Post box | 112 Bathurst Street (adjacent) | Bathurst Street road reserve | Local | I14 |
| Condobolin | General Cemetery | Corner of Boona Road and Maitland Street | Lot 2, DP 114302; Lot 1, DP 1114278; Lot 7314, DP 1144751; Lot 3, DP 1114305; Lot 2, DP 1114275; Lot 1, DP 114269; Lot 7313, DP 1142965; Lot 4, DP 114294 | Local | I10 |
| Condobolin | Goodwill dwelling | 19 Goodwill Street | Lot 7, DP 231702 | Local | I11 |
| Condobolin | Bogandillon Swamp | Grassmere Road | Bogandillon Swamp | | I6 |
| Condobolin | Memorial Park | Lachlan Street | Lot 701, DP 1125197 | Local | I13 |
| Condobolin | All Saints Anglican Church | 1 McDonnell Street | Lots 1 and 2, DP 1112124 | State | I3 |
| Condobolin | Presbyterian church manse | 30 McDonnell Street | Lot 12, DP 1014352 | Local | I16 |
| Condobolin | Sacred Park | Corner Molong, Denison and Station Streets | Lot 5, Section 26, DP 758271 | Local | I17 |
| Condobolin | Bill Hurley Water Tower | 23 Molong Street | Lot 7020, DP 1124093 | Local | I5 |
| Condobolin | Cadow Cemetery | South Forbes Road | Lot 111, DP 753078 | Local | I7 |
| Condobolin | Avenue of peppercorns | The Gipps Way | Road reserve | Local | I4 |
| Goobothery Hill | Kings Grave | Goobothery Hill Site | Lot 7300, DP 1134212 | Local | I18 |
| Lake Cargelligo | Memorial Hall | Foster Street | Lot 18, Section 2, DP 758595 | Local | I23 |
| Lake Cargelligo | Royal Mail Hotel | 14 Foster Street | Lot 12, Section 2, DP 758595 | Local | I27 |
| Lake Cargelligo | The Bank Coffee Shoppe | South east corner, Foster and Canada Streets | Lot A, Section 2, DP 406722 | Local | I28 |
| Lake Cargelligo | National Australia Bank | South west corner, Foster and Canada Streets | Lot 1, Section 3, DP 758595 | Local | I24 |
| Lake Cargelligo | Apex Park | Bogan Street | Part Reserve 60288 | Local | I19 |
| Lake Cargelligo | Bicentennial Park | Lake Street | Lots 2 and 3, DP 758595, Part Reserve 60288 | Local | I20 |
| Lake Cargelligo | Liberty Park | Lake Street | Lot 1, DP 758595; Section 75, Reserve 53331 | Local | I22 |
| Lake Cargelligo | Rotary Park | Lake Street | Lot 7049, DP 1023913 | Local | I26 |
| Lake Cargelligo | Old original cemetery | Narrandera Street | Lot 78, DP 752329 | Local | I25 |
| Lake Cargelligo | General Cemetery | Pillinger Drive | Lot 7053, DP 1026629 | Local | I21 |
| Melrose | Melrose Homestead | Cobar Road | Lot 48, DP 752102 | Local | I29 |
| Tottenham | Memorial Hall | Bulbodney Street | Lot 5, Section 9, DP 758989 | Local | I30 |
| Tottenham | Tottenham General Cemetery | Corner Racecourse Road and The Bogan Way | Lot 7003, DP 1061183 | Local | I31 |
Schedule 6
Pond-based and tank-based aquaculture
Schedule 6 Pond-based and tank-based aquaculture
Schedule 6 Pond-based and tank-based aquaculture
(Clause 5.19)
Division 1
Site location requirements
Division 1 Site location requirements
Division 1 Site location requirements
Division 2
Operational requirements
Division 2 Operational requirements
Division 2 Operational requirements
7
Conservation exclusion zones
7 Conservation exclusion zones
7 Conservation exclusion zones
(1) Must not be carried out on the following land, except to the extent necessary to gain access to water—
(c) land within a wetland of international significance declared under the Ramsar Convention on Wetlands.
Note.
Nothing in this clause affects any requirement under an Act relating to land specified in this clause to obtain a licence or other authority under that Act for development of the land.
8
Flood liability
8 Flood liability
8 Flood liability
Must be designed or constructed on land so that it will not be inundated by the discharge of a 1:100 ARI (average recurrent interval) flood event.
9
Species selection
9 Species selection
9 Species selection
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Lachlan Local Environmental Plan 2013.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Lachlan in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to protect, conserve and enhance agricultural land through the proper management, conservation and development of natural and man-made resources,
(b) to encourage the provision of a range of housing, employment and recreation facilities to meet the needs of existing and future residents of Lachlan,
(c) to promote the efficient and equitable provision of public services, infrastructure and amenities,
(d) to protect, conserve and enhance the environmental and cultural heritage of Lachlan,
(e) to encourage the sustainable growth of Lachlan,
(f) to encourage development that is matched by adequate land supply for long-term needs and that is linked with key services and infrastructure.
Provides for the classification and reclassification of public land, maps land reserved for acquisition and identifies the State authorities for owner-initiated acquisition (cl 5.1; cl 5.2; Sch 4).
Lists specific additional permitted uses for particular parcels of land and identifies heritage items and conservation areas (Sch 1; Sch 5).
The Plan explicitly sits within the framework of the Environmental Planning and Assessment Act and State environmental planning policies. For example, it is subject to any SEPP that prevails under s 3.28 of the Act (cl 1.9(1)). It also incorporates references to other legislation and instruments affecting implementation, for example the Building Code of Australia, the Heritage Act 1977, the Local Government Act 1993 and various State SEPPs (see cl 3.1(3)(a), cl 5.10, cl 5.12).
The Plan states its environmental and planning aims, such as protecting agricultural land, encouraging a range of housing and services and conserving environmental and cultural heritage (cl 1.2). Those aims are operationalised through zoning, development consent requirements, local development standards, and bespoke controls for particular activities or parcels of land.
Mechanically important provisions that change behaviour immediately include the repeal of prior local instruments for the same land (cl 1.8), a savings rule preserving the status of existing development applications lodged before commencement (cl 1.8A), a clause suspending private covenants to the extent necessary to give effect to development authorised by the Plan but preserving certain public and conservation instruments (cl 1.9A), and a prohibition on canal estate development (cl 2.9). The Plan also constrains the consent authority’s discretion in a few areas, for example by prohibiting refusal of licensed-premises development on grounds relating solely to the genre or presence of music provided noise can be managed (cl 5.20).
Official rationale statements appear in the instrument as objectives and aims (for example cl 1.2; cl 2.3(1)) and are recorded as the Plan’s purpose. Those statements are internal claims about the instrument’s intent. The Plan implements those aims through zoning, minimum lot sizes, development controls and the specified duties the consent authority must take into account when determining applications (for example cl 2.3(2); cl 4.1(1); cl 5.21).
This deep dive first outlines the Plan’s central concepts and then analyses who is affected, the practical duties and rights it creates, enforcement mechanics as stated in the instrument, interactions with other law, the amendment record as recorded in the Plan, litigation history within the instrument, operational pitfalls to watch, and concrete steps for compliance.
Main concepts
The Plan’s core conceptual architecture is the classic LEP model: zones, land use tables, maps, schedules, and clauses that impose standards and processes. The principal concepts are:
Zoning and permitted uses: The Plan divides land into specific zones such as RU1 Primary Production, RU3 Forestry, RU5 Village, R5 Large Lot Residential, SP2 Infrastructure, RE1 Public Recreation, C1 National Parks and Nature Reserves, W1 Natural Waterways and W2 Recreational Waterways (cl 2.1; Land Use Table). For each zone the Land Use Table defines objectives, development permitted without consent, development permitted only with consent and prohibited development (cl 2.3(1); Land Use Table). The consent authority must have regard to zone objectives when determining applications (cl 2.3(2)).
Maps and numeric controls: External digital maps (Land Zoning Map, Lot Size Map, Heritage Map, Terrestrial Biodiversity Map, Wetlands Map, Groundwater Vulnerability Map, Land Reservation Acquisition Map) determine the application of many clauses and overlays (cl 1.7; cl 2.2; various clauses referencing maps). Minimum lot sizes for subdivisions are mapped and enforced in clause 4.1, with specified exceptions for Areas A and B where smaller lots are permitted if connected to water and sewer systems (cl 4.1(3)-(3A)).
Development consent as the central regulatory mechanism: The Plan repeatedly differentiates development that can be carried out without consent, development that requires consent and prohibited development. Where consent is required, the consent authority is required to consider specified matters under particular clauses before granting consent, for example heritage impacts (cl 5.10), flood planning considerations (cl 5.21), earthworks impacts (cl 6.1(3)), biodiversity impacts (cl 6.4), and aquaculture requirements (cl 5.19 and Sch 6).
Exempt and complying development: The Plan specifies exempt development in Schedule 2 and complying development in Schedule 3, but cross-references State SEPPs for wider state-wide exempt/complying development (cl 3.1-3.2). Exempt development must meet Building Code of Australia requirements and cannot be designated development or affect State heritage (cl 3.1(3)-(5)). Exempt/compliant classes are further curtailed by an overlay that excludes environmentally sensitive areas (cl 3.3).
Exceptions to standards: Clause 4.6 provides a statutory mechanism to grant consent that contravenes a development standard in the Plan or another instrument, provided the applicant demonstrates compliance is unreasonable or unnecessary and there are sufficient environmental planning grounds, and the consent authority records its assessment (cl 4.6(2)-(4)). This mechanism is qualified by prohibitions that certain standards (for complying development, BASIX, cl 5.4 limits, cl 5.5) cannot be varied under this clause (cl 4.6(8)).
Localised and activity-specific controls: The Plan contains detailed local controls for intensive livestock agriculture (cl 5.18), pond-based/tank-based and oyster aquaculture (cl 5.19 and Sch 6), eco-tourist facilities (cl 5.13), farm stay and farm gate premises (cls 5.24-5.25), and rules preserving opportunities for live music at licensed premises (cl 5.20). These controls combine objective-setting, mandatory considerations, and operational thresholds or exclusions.
Protection and process for heritage: Clause 5.10 sets objectives to conserve environmental heritage, requires development consent for a wide range of works affecting heritage items and areas, allows minor works if the consent authority advises in writing, and sets consultation requirements including notifying the Heritage Council or local Aboriginal communities and considering responses received within 28 days (cl 5.10(1)-(9)). Schedule 5 lists identified heritage items and places.
Public land classification and acquisition: Clause 5.1 designates the relevant State authority for owner-initiated acquisition processes and points to a Land Reservation Acquisition Map. Clause 5.2 enables the Council to classify or reclassify public land under the Local Government Act, and Schedule 4 lists land classified as operational or community land.
Covenant suspension for Plan-consistent development: Clause 1.9A suspends private covenants, agreements or similar instruments to the extent necessary to enable development in accordance with the Plan or consent, but excludes covenants imposed by the Council and a defined list of Crown and conservation instruments, and does not affect public authority rights under registered instruments (cl 1.9A(1)-(3)).
The Plan’s mechanisms are a mix of prescriptive standards (mapped lot sizes, maximum floor areas for specific retail or farm stay uses, thresholds for complying development), discretionary decision-making with specified matters to consider (heritage, biodiversity, flood risk, intensive agriculture), and procedural limits on refusal or variation in specified circumstances (music at licensed premises, cl 5.20; exceptions to standards, cl 4.6).
Several provisions explicitly link decisions to other policy material. For example, flood planning requires the consent authority to consider the Considering Flooding in Land Use Planning Guideline and the Flood Risk Management Manual (cl 5.21(4)-(5)). Aquaculture clauses cross‑refer to aquaculture industry development plans and the NSW Oyster Industry Sustainable Aquaculture Strategy (cl 5.19(5)-(6); Sch 6).
Taken together, the main concepts create a layered regulatory structure where mapped controls and specific local limitations shape development opportunity, while the consent authority’s responsibilities to consider identified environmental, heritage and infrastructure factors shape discretionary outcomes.
Who it affects
This Plan affects a defined set of actors. The text makes clear who decides, who bears costs and who must change behaviour.
Primary decision-maker and enforcing bodies
Council is the consent authority for development on land to which the Plan applies, subject to the Act (cl 1.6). That places planning discretion, assessment and record-keeping responsibilities with the local council, operating within the Act and in interaction with State policies.
State authorities are implicated where the Plan identifies them as the relevant acquisition authority for land reserved for particular public purposes (cl 5.1(2)). For example, Transport for NSW for classified roads and the corporation constituted under s 2.5 of the Act for regional open space are listed in the table in cl 5.1(2).
Other State agencies figure as consultees or holders of regulatory powers referenced in clauses, for example Fire and Rescue NSW in the context of fire alarm monitoring (cl 5.8), the Heritage Council for archaeological sites and State heritage items (cl 5.10(7), (9)), and the Department of Primary Industries for aquaculture industry development plans (cl 5.19).
Landowners, applicants and developers
Owners of land within the mapped area of the Lachlan LEP, and people proposing to carry out development on that land, are the principal private actors constrained by the Plan. The Plan changes the legal baseline for development by specifying permitted uses, development that requires consent, mapping overlays (including minimum lot sizes), and local controls (cl 2.1; cl 4.1; Schs).
Prospective subdividers must comply with mapped minimum lot sizes and other constraints, including special rules for Areas A and B and strata or community title subdivisions (cl 4.1; cl 4.1AA; cl 4.2A).
Agricultural operators, intensive livestock producers and aquaculture operators are affected by activity-specific rules and thresholds. Intensive livestock agriculture is subject to mandatory considerations and, for small‑scale operations under specified capacity thresholds and location constraints, may be carried out without development consent (cl 5.18(3)-(5)). Pond-based and tank-based aquaculture must meet site location and operational requirements in Schedule 6 and may be permitted without consent in some zones if they meet the Part 2 requirements (cl 5.19; Sch 6).
Operators of licensed premises (pubs, clubs, bars) are affected by clause 5.20, which restricts the grounds on which consent can be refused in relation to music and entertainment, provided noise can be managed (cl 5.20(1)-(2)).
Owners and beneficiaries of covenants and private agreements
Private covenants, agreements and similar instruments are effectively suspended to the extent necessary to enable development that complies with the Plan, unless the covenant is one of the exclusions listed in clause 1.9A(2). The suspension removes private restrictions in many cases, but does not override covenants imposed by the Council, certain Crown instruments, conservation agreements, biobanking agreements, planning agreements, or registered public authority rights (cl 1.9A(1)-(3)).
Heritage stakeholders and Aboriginal communities
Owners of heritage items and land within heritage conservation areas are affected by the consent requirements and consultation processes in cl 5.10. The consent authority can require heritage assessments and management plans, and must notify and consider responses from the Heritage Council and local Aboriginal communities where specific categories of development arise (cl 5.10(4)-(9)).
Public service providers and infrastructure owners
Entities responsible for providing water reticulation and sewerage are implicated because certain lower minimum lot sizes require connection to water and sewer systems (cl 4.1(3A)), and specific subdivisions are required to show connection to services (cl 6.8 for Lot 280 Boona Road).
Neighbouring landowners and the public
The Plan creates obligations on the consent authority to consider amenity, environmental impacts, heritage, flood risk and noise that can affect adjoining properties and the wider community, for example in clauses on temporary use (cl 2.8), earthworks (cl 6.1), stormwater (cl 6.3) and flood planning (cl 5.21).
Who pays and who bears compliance costs
The Plan does not set statutory fee levels, but the structure makes clear that applicants pay for compliance costs: preparing statements of environmental effects, heritage management documents, EISs where designated development is involved, BASIX certificates where relevant, engineering works for stormwater and connection to reticulation systems where required (cl 3.1(3); cl 5.10(5)-(6); cl 6.3; cl 4.1(3A); cl 6.8). Where development is permitted without consent but requires other licences under separate Acts (for example aquaculture, water licences), the applicant must obtain those authorities (Schedule 2 Note 2; cl 5.19(2)(b)).
Behavioural effects and decision incentives
The Plan’s mapped minimum lot sizes, prohibitions (for example canal estates cl 2.9), and specific use limitations (for rural, village and large lot residential zones in the Land Use Table) shape investment choices by landowners and developers, encouraging particular types of development in certain zones and discouraging others.
The clause allowing suspension of covenants (cl 1.9A) lowers a source of private constraint where development conforms to the Plan, which may increase landholders’ ability to develop, subject to the exclusions in cl 1.9A(2).
The requirement that the consent authority consider specified environmental matters places a procedural burden on applicants and steers decisions towards planned, assessed outcomes rather than ad hoc development (see cl 6.1(3); cl 6.4; cl 5.21).
In summary, the Plan affects the Council’s regulatory role, State acquisition authorities, landowners, specific industry operators (agriculture, intensive livestock, aquaculture, tourism), heritage stakeholders and the local community by mapping permitted uses, setting standards and procedural rules that allocate costs of compliance to applicants and allocate decision-making responsibilities to the local consent authority.
Key duties and rights
This section summarises the principal duties the Plan imposes on decision-makers and applicants, and the rights and protections it provides to particular stakeholders. All references below are to the clauses of the Plan.
Duties of the consent authority (Council)
General consent authority role: Council is the consent authority subject to the Act (cl 1.6). It must have regard to objectives for development in the relevant zone when determining applications (cl 2.3(2)).
Record-keeping for exceptions: When applying clause 4.6 (exceptions to development standards), the consent authority must keep a record of its assessment under cl 4.6(3) (cl 4.6(4)).
Heritage processes and consultation duties: Before granting consent affecting archaeological sites (except where the land is State heritage-listed), the consent authority must notify the Heritage Council and consider any response received within 28 days (cl 5.10(7)). For Aboriginal places of heritage significance, the consent authority must investigate and consult local Aboriginal communities and take into account responses within 28 days (cl 5.10(8)). For demolition of nominated State heritage items the consent authority must notify the Heritage Council and take into account any response received within 28 days (cl 5.10(9)).
Flood planning considerations: The consent authority must be satisfied that development in the flood planning area is compatible with flood function and will not result in adverse flood behaviour impacts, will incorporate measures to manage risk to life and consider climate change impacts and evacuation capacity (cl 5.21(2)-(3)).
Site-specific considerations: The consent authority must be satisfied of various matters in relation to earthworks (cl 6.1(3)), stormwater (cl 6.3(3)), biodiversity (cl 6.4(3)-(4)), groundwater vulnerability (cl 6.5(3)-(4)), wetlands (cl 6.6(3)-(4)), intensive livestock agriculture (cl 5.18(3)), pond/tank aquaculture (cl 5.19(2)-(3)) and eco-tourist facilities (cl 5.13(3)).
Duties of applicants and landowners
Development consent where required: Most subdivision (cl 2.6), demolition (cl 2.7) and various development types listed in the Land Use Table require development consent unless made exempt or complying under the Plan or a SEPP. Applicants must comply with the applicable standards and supply necessary information.
Evidence and documentary requirements: Applications that seek to contravene a development standard must be accompanied by a document setting out the grounds on which the applicant seeks to demonstrate the matters in cl 4.6(3) in accordance with the Environmental Planning and Assessment Regulation (cl 4.6(3) Note). For intensive livestock and designated aquaculture projects applicants must provide adequate statements of environmental effects or EIS materials for proper consideration (cl 5.18(3)(a); cl 5.17(4)(a)).
Heritage-related duties: Where a consent authority requires a heritage management document or heritage conservation management plan, the applicant must prepare it as a precondition to consent (cl 5.10(5)-(6)). Applicants proposing work on Aboriginal places must participate in consultation processes (cl 5.10(8)).
Operational and design constraints: Applicants for pond- or tank-based aquaculture must comply with the species selection and operational requirements in Schedule 6, including outlet screening and no freshwater discharges to natural waterbodies for intensive aquaculture except for specified systems (cl 5.19; Sch 6 Div 2). Intensive livestock applicants must respect the location exclusions and capacity thresholds set out in cl 5.18(4)-(5).
Rights and protections created by the Plan
Protection from refusal on certain entertainment grounds: For licensed premises, the consent authority may not refuse consent on the listed grounds relating to the playing and performance of music, dancing, stage direction, decorations or lighting, and must not refuse on noise grounds if satisfied the noise may be managed and minimised to an acceptable level (cl 5.20(1)-(2)). This limits a type of municipal discretion to refuse entertainment-based developments.
Savings for pending applications: Development applications lodged before commencement of the Plan that are not finally determined are to be determined as if this Plan had not commenced, preserving the applicant’s position under previous instruments (cl 1.8A). The Plan’s note clarifies how Division 3.5 of the Act interacts with such applications.
Ability to seek consent to contravene standards: Clause 4.6 allows applicants to seek consent that contravenes a development standard if they can satisfy the tests in cl 4.6(3). This provides an administrative pathway for flexibility where compliance would be unreasonable or unnecessary and sufficient planning grounds exist.
Replacement and repair rights: Clause 4.2B(5) allows replacement of lawfully erected dual occupancies, dwelling houses or secondary dwellings in Zone RU1, and cl 5.9 permits repair or replacement of lawfully erected dwelling houses and secondary dwellings destroyed or damaged by a natural disaster if the application is made within five years (cl 4.2B(5); cl 5.9(2)-(3)).
Key procedural constraints and limits
Certain standards cannot be varied under cl 4.6, including standards for complying development and BASIX commitments, and certain clauses such as cl 5.4 and cl 5.5 are expressly protected from variation (cl 4.6(8)).
The Plan prevents subdivision that would separate a principal dwelling and secondary dwelling into separate lots unless minimum sizes are met (cl 2.6(2)).
Clause 1.9A suspends private covenants only to the extent necessary to give effect to Plan-consistent development; it excludes covenants imposed by the Council and specified conservation, Crown and planning instruments (cl 1.9A(1)-(3)).
Other administrative duties and interactions
The Plan requires that named maps are kept and made publicly available in accordance with Minister-approved arrangements (cl 1.7(3)). Applicants and interested persons must check the maps on the NSW Planning Portal as the Plan relies heavily on map-based application of rules (cl 1.7 Note).
The consent authority must apply and consider other statutory frameworks when relevant, for example State SEPPs that prevail over the Plan (cl 1.9(1)), licences under other Acts required for aquaculture or water management (cl 5.17(4)(b)), and the Local Government Act for classification and reclassification matters (cl 5.2 Note).
In short, the Plan allocates procedural duties to the Council, submission duties to applicants and preserves certain rights for applicants and landowners through savings clauses and exception mechanisms. Applicants face a range of preconditions, report-writing obligations and design constraints; the consent authority must exercise discretion in line with the Plan’s identified considerations and record assessments where exceptions to standards are sought.
Penalties and enforcement
The Plan itself is a statutory environmental planning instrument that prescribes land use rules and decision-making procedures. The instrument contains limited express penalty provisions; instead, it embeds enforcement and compliance within the broader statutory regime under the Environmental Planning and Assessment Act and related legislation. The text of the Plan provides the enforcement context and points to mechanisms and processes rather than setting out standalone pecuniary penalties.
Enforcement framework and where to look
Reliance on the Act: The Plan repeatedly operates "subject to the Act" and delegates or refers to the Act’s consent, compliance and enforcement provisions. For example, the consent authority role is defined "subject to the Act" (cl 1.6), and Part 3 notes that exempt development is exempt from development consent but is not exempt from other statutory approvals (cl 3.1 Note). Enforcement of breaches (carrying out development without consent, contravening consent conditions, unlawful demolition, etc.) therefore falls to the mechanisms in the Environmental Planning and Assessment Act, the Act's regulations and related enforcement practices in NSW planning law, rather than to specific sanction schedules in the LEP.
Procedural remedies and refusal/approval controls: The Plan prescribes mandatory preconditions and matters that must be satisfied before consent may be granted (for example cl 5.21 for flood planning, cl 6.4 for biodiversity). Non‑compliance with those preconditions gives the consent authority an arguable basis to refuse consent. Conversely, approval that does not satisfy statutory requirements may be vulnerable to merits review or judicial review under the Act and general administrative law, although the Plan does not itself set out appeal mechanisms.
Heritage consultation timetables: The Plan sets procedural duties for notice and consultation with heritage bodies and Aboriginal communities (cl 5.10(7)-(9)), and these processes are part of the statutory decision-making record that would be reviewable if not complied with.
Registered instruments and covenants: Clause 1.9A suspends private covenants for Plan-consistent development but expressly preserves the rights or interests of any public authority under any registered instrument (cl 1.9A(3)). That creates an interaction between registered property interests and the Plan, and non-compliance with registered public authority instruments would continue to be actionable under property law or the relevant statutory scheme.
No express penalty clauses in the LEP text
The Plan does not itself specify monetary penalties, enforcement notices, stop-work orders or infringement notice regimes within its text. It does not specify criminal sanctions or civil penalty amounts. Those instruments are within the Act, the EP&A Regulation and other statutes.
Enforcement mechanisms that will be applied in practice
Enforcement actions for breaches of the Plan are taken under the statutory enforcement tools provided by the Environmental Planning and Assessment Act and related legislation, including orders for remedial work, fines, injunctions and, where relevant, offences. The LEP’s requirements form the substantive law that those enforcement tools uphold, for example, requiring development consent prior to carrying out subdivision (cl 2.6) or demolition (cl 2.7).
Administrative controls: The consent authority can attach conditions to development consents, require heritage management plans or other preconditions (cl 5.10(5)-(6)), and refuse consent where mandatory matters are not satisfied (for example cl 5.21(2) for flood planning). Failure to comply with consent conditions gives rise to enforcement options under the Act.
Practical enforcement indicators in the LEP
The Plan signals where compliance will be monitored by listing matters that must be satisfied pre‑consent and by requiring consent authorities to keep records for exceptions to development standards (cl 4.6(4)). That record-keeping supports later enforcement and review.
Specific activities are excluded from exempt/compliant pathways where environmentally sensitive areas are involved (cl 3.3). Carrying out development that is excluded as exempt or complying but for which no consent has been obtained would be a breach enforceable under the Act.
Constraints on enforcement expectations
Because the LEP does not state penalties, practitioners must turn to the Act and relevant regulations to determine the precise sanctions and enforcement procedures available. The LEP structures the substantive rights and duties that those procedures will enforce.
In short, the Plan provides the substantive regulatory requirements and embeds procedural duties that the consent authority and applicants must observe. Enforcement and penalties are not itemised in the LEP itself but operate through the established enforcement regime under the Environmental Planning and Assessment Act and other linked legislation, assisted by the Plan’s record-keeping and consultation requirements.
How it interacts with other laws
The LEP is designed to sit within a broader statutory and policy framework. The Plan cross-references State policies and other Acts at multiple points. The text both defers to, and imposes requirements that interact with, other statutory regimes. Key interactions set out in the Plan are as follows.
Primacy and State policies
SEPP primacy: Clause 1.9(1) states the Plan is subject to any State environmental planning policy (SEPP) that prevails over the Plan as provided by s 3.28 of the Act. This confirms that where a SEPP applies and prevails, its provisions will override inconsistent LEP provisions.
Cross-referencing of State SEPPs: The Plan lists several SEPPs as potentially relevant in the Land Use Table note, including SEPP (Housing) 2021, SEPP (Transport and Infrastructure) 2021, SEPP (Resources and Energy) 2021, SEPP (Resilience and Hazards) 2021, SEPP (Industry and Employment) 2021 and SEPP (Primary Production) 2021. Those SEPPs will operate alongside the LEP where applicable.
Building regulation and BASIX
Building Code of Australia and BASIX: Exempt development requires compliance with relevant deemed-to-satisfy provisions of the Building Code of Australia (cl 3.1(3)(a)), and clause 4.6(8)(b) excludes from variation any standard that arises in connection with commitments in a BASIX certificate. Thus, building regulation and sustainability commitments under BASIX operate as binding constraints within the LEP framework.
Local Government Act and public land
Classification of public land: Clause 5.2 enables the Council to classify or reclassify public land under Part 2 of Chapter 6 of the Local Government Act 1993. That clause also sets out the effect of inserting land descriptions into Schedule 4, including discharge of trusts in certain circumstances (cl 5.2(2)-(5)). The Plan therefore interacts directly with the Local Government Act’s regime for operational and community land.
Heritage Act and Aboriginal heritage
Heritage processes: Clause 5.10 references the Heritage Act 1977 and requires notification and consideration of the Heritage Council for certain archaeological matters and nominated State heritage items (cl 5.10(7), (9)), and requires consideration of Aboriginal objects and places that may be governed by Aboriginal heritage provisions. The LEP imposes local consent requirements that sit alongside State heritage approval processes.
Crown land and Crown instruments
Suspended instruments excluded: Clause 1.9A expressly excludes from suspension certain Crown land instruments within the meaning of s 13.4 of the Crown Land Management Act 2016, conservation agreements under the National Parks and Wildlife Act 1974, property vegetation plans under the Native Vegetation Act 2003, biobanking agreements under the Threatened Species Conservation Act 1995, and planning agreements under the EP&A Act (cl 1.9A(2)(b)-(g)). This clause therefore defines the limits of private covenant suspension and confirms Crown and conservation instruments retain effect.
Land acquisition and Land Acquisition (Just Terms Compensation) Act
Owner-initiated acquisition: Clause 5.1 identifies the relevant State authority for owner-initiated acquisition under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991, and notes section 23 of that Act on acquiring land if delay causes hardship. The Plan links mapped reservation types to designated acquisition authorities (cl 5.1(2)).
Fisheries, Water and Primary Industries regimes
Aquaculture and water licences: The Plan’s aquaculture rules reference the Fisheries Management Act, aquaculture industry development plans, the Water Management Act 2000 and the Department of Primary Industries’ aquaculture strategy (cl 5.17, cl 5.19). Clause 5.17(4)(b) requires applications to identify licences or approvals required under other legislation. The Plan therefore coexists with water/water use, fisheries and pollution approval regimes.
Rural Fires Act and bushfire management
Bush fire hazard reduction works authorised under the Rural Fires Act 1997 may be carried out without consent (cl 5.11). The Plan notes the Rural Fires Act also addresses development on bush fire prone land. The LEP’s bushfire‑related duties therefore interact with that Act.
Other Acts and licences
The Plan repeatedly notes that exempt development is not exempt from approvals, licences, permits or other authorities required under other Acts (Schedule 2 Note 2; cl 3.1(5) note). Examples include water licences, fisheries licences, environmental protection approvals and local government approvals for effluent disposal on unsewered land (cl 3.2(3)(c)).
Operational interplay and practical consequences
Sequential approvals: Many activities require both development consent and separate statutory licences. For example, aquaculture development may require a development consent under the Plan and separate licensing under water and fisheries legislation (cl 5.17(4)(b)). Practitioners must therefore coordinate parallel application processes.
Constraints on variance: Clause 4.6 preserves certain standards from variation, including the BASIX-related standards and complying development standards. That limits the ability to achieve planning flexibility where State building sustainability commitments or complying development standards attach.
Mapped overlays drive other-law engagement: The Plan’s requirement to check maps (cl 1.7) means that assessment of development must incorporate overlay-derived constraints that may trigger other statutory regimes, for example perched groundwater vulnerability or wetlands triggering environmental protections under other Acts.
In summary, the Plan is embedded in a web of State SEPPs and other statutory regimes. It anticipates and requires interaction with building regulation, heritage, Crown land management, water and fisheries law, the Local Government Act, and bushfire legislation. Practitioners must coordinate LEP compliance with the suite of approvals and regulatory instruments referenced explicitly in the Plan.
Amendment history
The Plan’s text records a set of amendments and insertions. The instrument itself annotates particular clauses and schedules with amendment and insertion notes. The Plan’s recorded amendment history, as shown in the instrument, includes the following entries and references (presented in the wording used in the Plan):
Clause 1.8A (Savings provision relating to development applications): annotated "Am 2019 (621), Sch 5[1]" indicating an amendment in 2019 recorded in Schedule 5 item 1 of the amending instrument.
Clause 1.9A (Suspension of covenants, agreements and instruments): annotated "Am 2019 (621), Sch 5[2]-[4]" indicating amendments in 2019 recorded in that Schedule.
Land Use Table (Land Use tbl): annotated "Am 2019 (137), Sch 6 [1]; 2022 (314), Sch 1; 2023 (458), Sch 2.49[1][2]" indicating amendments recorded across these instruments and schedules.
Clause 5.4 (Controls relating to miscellaneous permissible uses): annotated "cl 5.4: Am 2018 (406), Sch 1.78 [1] [2]" indicating amendment in 2018.
Clause 6.2: annotated "cl 6.2: Rep 2021 (225), Sch 1." showing clause 6.2 was repealed in 2021 under Schedule 1 of the amending instrument.
Clause 5.9: annotated "cl 5.9: Ins 2021 (302), Sch 1.14. Am 2024 (42), Sch 1.26." indicating the clause was inserted in 2021 and amended in 2024 by the cited instruments and schedules.
Schedule 1 (Additional permitted uses): annotated "sch 1: Am 2021 (532), cl 4(1); 2022 (646), cl 5." indicating amendments in 2021 and 2022.
Schedule 4 (Classification and reclassification of public land): annotated "sch 4: Am 2017 (72), cl 4." indicating an amendment in 2017.
Clause 6.8 (Subdivision at 60 Boona Road, Condobolin): annotated "cl 6.8: Ins 2022 (822), Sch 2.2." indicating insertion in 2022.
Clauses 5.24 and 5.25 (Farm stay accommodation and Farm gate premises): annotated "cl 5.24: Subst 2023 (458), Sch 1[4].", "cl 5.25: Subst 2023 (458), Sch 1[4]." indicating substitution in 2023.
Schedule 6 and other provisions include cross-references and notes indicating their status as part of the Plan, however not all sub‑parts carry explicit amendment annotations in the printed text provided.
The Plan includes notes like "When this Plan was made it did not include all of these zones" and similar historical remarks in relation to clauses that reference zones introduced later. The instrument also contains parenthetical annotations indicating some provisions are "Not adopted" or "Not applicable" which reflect the Plan’s local choices relative to model clauses.
This record is the Plan’s internal amendment trail as shown by the marginal annotations and clause notes. The Plan does not summarise a complete chronological register within its main text; practitioners should consult the NSW legislation website or consolidated LEP version for a compiled history with full amending instrument citations and dates.
Litigation history
The text of the Plan provided does not include any judicial decisions, case references or litigation history. The Plan itself lists statutory references and explanatory notes but does not record any court challenges or merits review outcomes. There are no cases named in the instrument.
Therefore, within the LEP document there is no litigation history recorded. If litigation or merits-review outcomes are relevant to interpreting or testing particular clauses (for example, the operation of cl 4.6 exceptions to development standards or the scope of cl 1.9A covenant suspension), those materials will need to be located in external case law and administrative review records. This Plan does not supply such materials and does not identify any precedent that interprets its clauses.
Practitioners relying on legal precedent should therefore undertake a targeted search of court and tribunal databases for decisions that reference the Lachlan LEP 2013, clause numbers cited above, or the particular legal issues (for example cl 4.6 exceptions, heritage requirements under cl 5.10, or the covenant suspension in cl 1.9A). The Plan itself provides the statutory language that any such decisions would interpret, but it contains no internal history of litigation.
Gotchas
The Plan contains multiple provisions that present potential traps for practitioners, developers and consent authorities. These are concrete operational risks and interpretation issues that the text itself creates.
Savings provision preserves old law for pending applications (cl 1.8A)
Risk: If a development application was lodged before the LEP commenced and remains undetermined, cl 1.8A requires determination as if the LEP had not commenced. That can leave applicants and neighbours with uncertainty about which rules apply. The Plan’s note points to Division 3.5 of the Act (the mechanism for dealing with applications for development that require a new instrument), which can interact awkwardly with public consultation and exhibition requirements. Practitioners must check lodgement dates and the precise point at which an application is "finally determined" to avoid strategic missteps.
Suspension of covenants is broad but has key exclusions (cl 1.9A)
Mechanism: Clause 1.9A suspends private covenants and similar instruments to the extent necessary to enable Plan-consistent development.
Caveat: The clause expressly excludes covenants imposed by Council, Crown land instruments, conservation agreements, biobanking agreements, certain Native Vegetation and Threatened Species instruments, and planning agreements, and it preserves public authority rights under registered instruments (cl 1.9A(2)-(3)). Practitioners must check the provenance of any covenant to see whether it falls within an exclusion, and confirm whether registered public authority interests apply.
Minimum lot size exceptions and connectivity conditions (cl 4.1 and cl 4.1(3A))
Mechanism: The Lot Size Map prescribes minimum lot sizes, but Areas A and B may permit smaller lots provided minimum area floors (5,000 m2, 8,000 m2) and connection to water and sewer reticulation systems are satisfied (cl 4.1(3A)).
Risk: Applicants who rely on Area A/B exceptions must secure water and sewer reticulation, which can be costly or infeasible, and failure to demonstrate connection will preclude the benefit. Clause 6.8 shows an example where a specific lot must be connected to water and sewer to subdivide (cl 6.8(2)). Practitioners should verify infrastructure availability before lodging applications.
Subdivision limits via exceptions to standards (cl 4.6(6))
Mechanism: Clause 4.6 allows exceptions to development standards, but expressly forbids the granting of consent under this clause where the subdivision would create two or more lots below the minimum area or create a lot less than 90% of the minimum (cl 4.6(6)).
Effect: This limits the scope of discretion where a subdivision would materially erode mapped minimum lot sizes. Applicants seeking multiple smaller lots cannot use cl 4.6 as a backdoor to fragmentation.
Standards that cannot be varied (cl 4.6(8))
Mechanism: Certain development standards cannot be contravened via 4.6, including standards for complying development and standards arising from BASIX commitments and specific clauses such as cl 5.4 and cl 5.5 (cl 4.6(8)).
Effect: Plans or applications that rely on 4.6 for flexibility must ensure the standards at issue are not protected from variation. BASIX‑linked measures and complying development standards are locked down.
Intensive livestock agriculture thresholds and location constraints (cl 5.18(4)-(5))
Mechanism: The Plan allows some small-scale intensive livestock activities to proceed without development consent if they meet specified capacity thresholds and are not located in environmentally sensitive areas, watercourses, drinking water catchments, or within distance buffers from other farms or dwellings (cl 5.18(4)-(5)).
Risk: The thresholds are precise and include species-specific buffers (for poultry and pigs). Misclassification of farm type or mismeasurement of capacity or location can inadvertently trigger the need for consent. The Plan requires the consent authority to assess odour, pollution risk and other environmental factors for larger projects (cl 5.18(3)), so applicants should prepare statements of environmental effects even where consent may not be required to avoid later compliance disputes.
Aquaculture discharge and escape controls (cl 5.19; Sch 6)
Requirements: For pond/tank aquaculture that is intensive, ponds must be drainable and dryable (Sch 6 Div 2, cl 3); discharges to natural waterbodies are broadly forbidden for intensive operations except limited cases (Sch 6 Div 2, cl 4); outlets must be screened to prevent fish escape (Sch 6 Div 2, cl 5). Extensive pond-based aquaculture must not be built on permanent watercourses and must prevent escape of stock (Sch 6 Part 2).
Risk: Projects that fail to meet these design or discharge standards may be treated as unauthorised and face enforcement or be required to obtain additional licences under water or fisheries law. The Plan also signals that other statutory approvals will be necessary and must be identified in applications (cl 5.17(4)(b)).
Heritage consultation deadlines and substantive protection (cl 5.10)
Duties: The consent authority must notify the Heritage Council for applications affecting archaeological sites and nominated State heritage items, and consider responses within 28 days (cl 5.10(7), (9)). For Aboriginal places, local Aboriginal communities must be notified and responses considered within 28 days (cl 5.10(8)).
Risk: Failure to follow these procedural steps could invalidate a consent decision or expose it to review. Applicants should factor in minimum 28‑day statutory windows into project timelines and budgets.
Music protections at licensed premises with a noise caveat (cl 5.20)
Mechanism: The consent authority must not refuse consent to development on the grounds specified concerning music, dancing and performance features, and must not refuse for noise if satisfied noise may be managed and minimised to an acceptable level (cl 5.20(1)-(2)).
Practical issue: The clause shifts the decision to whether noise can be "managed and minimised to an acceptable level," which is a fact-sensitive assessment. Applicants should supply noise management plans and monitoring strategies to meet this test. Councils should record reasons how noise will be managed to justify approval in the face of community objection.
Map-driven rules and public availability (cl 1.7)
Practicality: Many provisions depend on maps published on the NSW Planning Portal. The Plan requires that maps be kept and made available for public access (cl 1.7(3)). Practitioners must verify the latest consolidated mapped data on the Portal as minor map amendments may alter permissible outcomes.
These are concrete operational issues created by the Plan’s text. Good practice is to validate the parcel‑specific mapping, check the provenance of covenants and registered interests, scope infrastructure availability, and prepare the technical reports the consent authority is required to consider for the relevant clause.
How to comply
This section sets out pragmatic steps, document checklists and approval sequencing that flow from the Plan’s provisions. It focuses on what applicants and practitioners must do to keep applications compliant with the LEP and relevant statutory interactions.
Step 1 , Confirm the planning baseline
Identify the parcel on the Land Application Map and Land Zoning Map available on the NSW Planning Portal (cl 1.3; cl 2.2). Check which zone applies (cl 2.1; Land Use Table) and whether any Additional Permitted Uses apply to the parcel under Schedule 1.
Check mapped overlays that alter the application of clauses: Lot Size Map, Terrestrial Biodiversity Map, Groundwater Vulnerability Map, Wetlands Map, Heritage Map and Land Reservation Acquisition Map. The Plan relies on these maps for minimum lot sizes, biodiversity constraints and public land reservation matters (cl 1.7; cl 4.1; cl 6.4-6.6; cl 5.1; cl 5.2). Confirm the current consolidated mapping on the Planning Portal.
Step 2 , Determine whether the development is permitted, exempt, complying or prohibited
Use the Land Use Table to determine whether the proposed use is listed as permitted without consent, permitted with consent or prohibited in the relevant zone (cl 2.3; Land Use Table). If the use is not listed, it is prohibited (Land Use Table general rule).
Check Schedule 2 for exempt development classes that may enable the work to proceed without consent, but remember exempt development must meet cl 3.1 standards, not be designated development, comply with the BCA, and not affect State heritage items (cl 3.1(2)-(5); Schedule 2 notes).
Consider whether the proposal can be done as complying development under Schedule 3 or State SEPPs. Complying development requires compliance with development standards and Building Code requirements, and may require Council approvals for on‑site effluent disposal on unsewered land (cl 3.2(2)-(3)).
Step 3 , Check for special activity rules
For intensive livestock agriculture, confirm whether the proposal falls below the capacity thresholds and meets location requirements to be exempt from needing development consent; if not, prepare a statement of environmental effects addressing odour, pollution, soil degradation and mitigation measures (cl 5.18(3)-(5)).
For pond-based, tank-based or oyster aquaculture, use Schedule 6 to check site location exclusion zones and operational requirements (cl 5.19; Sch 6). Ensure pond design, outlet screening and discharge rules are met and that any required fisheries/water licences are identified and sought (cl 5.19(4)-(5); Sch 6, cl 3-5).
For farm stay and farm gate premises, prepare material addressing noise, pollution, visual amenity, flora and fauna, water quality, traffic, safety and bushfire/flood constraints as required by cls 5.24-5.25.
For licensed premises proposing music or dancing, prepare a noise management plan demonstrating how noise will be managed to an acceptable level, as cl 5.20 limits refusals on entertainment grounds but maintains a noise manageability test.
Step 4 , Prepare required supporting documents
Heritage: If the site contains a heritage item, a heritage conservation area, or likely Aboriginal objects, prepare a heritage management document or heritage conservation management plan if requested by the consent authority, and be ready to engage with the Heritage Council and local Aboriginal communities within the 28‑day response window (cl 5.10(4)-(9)).
Flooding: For development in a flood planning area, include a flood risk assessment that considers projected climate change impacts, evacuation and safe occupation strategies, and how the development avoids adverse impacts on flood behaviour (cl 5.21(2)-(3)). Use the Considering Flooding in Land Use Planning Guideline and the Flood Risk Management Manual as referenced (cl 5.21(4)-(5)).
Biodiversity, groundwater and wetlands: For mapped biodiversity, groundwater vulnerable or wetland sites include ecological assessments, measures to avoid, minimise and mitigate impacts, and any connectivity analysis required under cl 6.4-6.6.
Earthworks and stormwater: For earthworks include soil stability, drainage impacts, source/destination of fill, likely disturbance to relics and mitigation measures (cl 6.1(3)). For stormwater provide design for permeable surfaces, on‑site retention and mitigation of runoff impacts (cl 6.3(3)).
BASIX and BCA: For building works ensure compliance with the Building Code of Australia requirements and prepare or attach a BASIX certificate where applicable; remember BASIX-related standards cannot be varied under cl 4.6(8).
Exception cases: If an application seeks to contravene a development standard, prepare the 4.6 statement required by the EP&A Regulation addressing why compliance is unreasonable or unnecessary and the environmental planning grounds for the contravention, and note the consent authority must keep an assessment record (cl 4.6(3)-(4)).
Step 5 , Check registered interests and covenant implications
If private covenants exist on title, determine whether they would be suspended under cl 1.9A for Plan‑consistent development, and whether any exclusion applies (covenants imposed by Council, Crown instruments, conservation agreements, biobanking, planning agreements). Confirm any registered public authority rights remain effective (cl 1.9A(1)-(3)). Do not rely on covenant suspension for works inconsistent with public or Crown instruments.
Step 6 , Infrastructure and services
Confirm essential services availability: The consent authority must ensure essential services will be available for the development (water, electricity, sewage, stormwater drainage and vehicular access) or that arrangements are in place (cl 6.7).
For areas where smaller lots rely on connection to reticulated services (cl 4.1(3A)), secure commitments or evidence from service providers before relying on mapped minimum lot size relaxations. Clause 6.8 provides an example where the consent authority must be satisfied of connection for a particular lot.
Step 7 , Lodgement and timing
Factor in statutory consultation windows, particularly the 28-day response periods for the Heritage Council and Aboriginal community consultation where notification is required (cl 5.10(7)-(9)).
If the project is linked to maps or overlays, verify no recent map amendments have changed the parcel’s status on the NSW Planning Portal (cl 1.7(3)). If development applications were lodged prior to the Plan’s commencement, cl 1.8A requires treating them under the prior instrument; confirm the lodgement timing to determine the applicable rules.
Step 8 , Conditions, approvals sequencing and parallel licences
Expect the consent authority to impose conditions, such as requiring heritage conservation work, environmental management measures, or infrastructure works. Coordinate any approvals required under other Acts, such as fisheries or water licences, with the planning application timeline to avoid condition precedent issues (cl 5.17(4)(b)).
Step 9 , Record-keeping and appeals risk management
Where an exception under cl 4.6 is sought, ensure the consent authority’s assessment is fully documented (cl 4.6(4)). Maintain complete records of consultations and technical assessments, as procedural missteps in heritage, flood or biodiversity consultation can create review risks.
Practical checklists by activity
Subdivision: Confirm mapped minimum sizes, check Area A/B exceptions, secure evidence of reticulation connections where required, and avoid using cl 4.6 to create multiple lots below minimum area due to cl 4.6(6).
Intensive livestock: Prepare a statement addressing thresholds, location exclusions, odour and pollution controls, industry codes and DPI guidelines as required by cl 5.18.
Aquaculture: Meet Sch 6 site location and operational requirements, design ponds to be drainable and prevent escape, screen outlets, and identify required fisheries and water licences.
Heritage works: Provide heritage impact assessments, be ready to prepare a heritage conservation management plan if requested, and allow for statutory 28-day consultation periods.
Licensed premises and music: Produce a noise management plan that establishes how noise will be managed to an acceptable level to avoid refusal under cl 5.20.
Temporary uses: Limit temporary development to 52 days in any 12-month period (cl 2.8(2)), unless the use is a dwelling used as a sales office in which case the limit may be exceeded (cl 2.8(4)).
In conclusion, compliance with the Lachlan LEP 2013 requires parcel‑specific mapping checks, careful alignment with State SEPPs and other statutory licences, technical reports for environmental, heritage and flood matters and attentive sequencing of approvals. The Plan places a range of technical and procedural obligations on applicants and detailed duties on the Council as consent authority; compliance risk is highest where multiple regulatory regimes intersect (heritage, water, fisheries, bushfire, BASIX obligations and local service connections).
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Lachlan Local Environmental Plan 1991
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
cl 1.8A: Am 2019 (621), Sch 5[1].
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
cl 1.9A: Am 2019 (621), Sch 5[2]–[4].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
Rural Zones
RU1 Primary Production
RU3 Forestry
RU5 Village
Residential Zones
R5 Large Lot Residential
Special Purpose Zones
SP2 Infrastructure
Recreation Zones
RE1 Public Recreation
Conservation Zones
C1 National Parks and Nature Reserves
Waterway Zones
W1 Natural Waterways
W2 Recreational Waterways
2 Zoning of land to which Plan applies
2 Zoning of land to which Plan applies
2.2 Zoning of land to which Plan applies
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate may exceed the maximum number of days specified in that subclause.
(5) Subclause (3) (d) does not apply to the temporary use of a dwelling as a sales office mentioned in subclause (4).
2 Canal estate development prohibited
2 Canal estate development prohibited
2.9 Canal estate development prohibited
(1) Canal estate development is prohibited on land to which this Plan applies.
(2) In this Plan, canal estate development means development that involves—
(a) a constructed canal, or other waterway or waterbody, that—
(i) is inundated by surface water or groundwater movement, or
(ii) drains to a waterway or waterbody by surface water or groundwater moveme
This is an opening excerpt, not the complete document.