(1) Despite any other provision of this plan, master plan development may be carried out with development consent on a master plan site, but only if—
(a) the development complies with the development requirements specified for the site in Schedule 5, and
(b) the consent authority has taken into consideration the master plan for the site as adopted by the Council for the time being in accordance with this Part.
(2) Provisions or instruments identified in Schedule 5 as comprising the initial master plan for a master plan site are taken to have been adopted by the Council with the approval of the Minister in accordance with this Part as a master plan at the commencement of this Part, but nothing prevents the amendment or replacement of any such master plan in accordance with this Part.
(3) State Environmental Planning Policy No 1—Development Standards does not apply to any development standard imposed on master plan development by a development requirement specified in Schedule 5, except as provided otherwise in that Schedule.
(4) State Environmental Planning Policy No 71—Coastal Protection does not require a master plan to be adopted by the Minister under that Policy before consent is granted for master plan development of a master plan site.
(5) The Council must make a copy of each master plan, as adopted by the Council for the time being, available for inspection at the office of the Council during ordinary office hours.
(6) Nothing in this Part prevents development from being carried out on a master plan site in accordance with the other provisions of this plan, subject to the conditions of any consent granted for master plan development.
cl 47AB: Ins 7.1.2005.