129 Stop work orders
129 Stop work orders
(1) The Secretary may, by written order given to a developer in relation to residential building work (a stop work order), order the developer to ensure that the building work stops if—
(a) in the Secretary’s opinion the building work is, or is likely to be, carried out in a way that could result in significant harm or loss to the public or to occupiers or potential occupiers of the building to which the work relates or significant damage to property, or
(b) the following apply—
(i) there is a change in principal certifier or building practitioner for the residential building work,
(ii) in the Secretary’s opinion the building work is, or is likely to be, carried out in a way that could prevent the valid issue of an occupation certificate or building compliance declaration for the residential building work.
(2) In subsection (1)(b)(ii), the valid issue of an occupation certificate or building compliance certificate means the issue of the certificate or declaration in accordance with the following Acts and the regulations made under the Acts, as appropriate—
(d) this Act.
(3) A stop work order takes effect on the day the order is given to the developer or on a later day specified in the order.
(4) A stop work order may be unconditional or subject to conditions.
(5) The Secretary may, by written notice given to a developer who is subject to a stop work order, impose a condition on the order or revoke or vary a condition of the order.
(6) A stop work order remains in force until one of the following occurs—
(a) the order is revoked by the Secretary,
(b) the term, if any, of the order ends,