This local environmental plan sets the zoning, permitted/prohibited uses, and development controls for land in the Gundagai area. It prescribes when development consent, exempt or complying development applies, minimum lot sizes, environmental and heritage safeguards, and maps that trigger special rules.
It affects landowners, developers, the Council (as consent authority) and certain State agencies. It matters because it determines who may build or subdivide, what approvals and standards apply, and what environmental, heritage and infrastructure constraints must be met.
This local environmental plan (the Plan) sets zoning, permitted uses, development controls, and procedural requirements for the part of the Cootamundra‑Gundagai Regional local government area to which it applies (cl 1.2; cl 1.3). It establishes the consent authority as the Council (cl 1.6), adopts named maps (cl 1.7) including the Land Zoning Map and Lot Size Map (cl 2.2; cl 4.1(2)), and replaces earlier local environmental plans and deemed environmental planning instruments for the same land (cl 1.8). The Plan identifies land use zones (cl 2.1), provides a Land Use Table with permitted, consent and prohibited development for each zone (cl 2.3 and the Land Use Table), prescribes minimum lot sizes for subdivision (cl 4.1 and Lot Size Map), and creates subject‑specific controls (for example biodiversity protection cl 6.1; water protection cl 6.3; earthworks cl 6.5; heritage cl 5.10).
Mechanically, the Plan distinguishes three consent regimes. First, exempt development as specified in Schedule 2 and cl 3.1 of the Plan (subject to Building Code and other statutory constraints) may be undertaken without development consent. Second, complying development listed in Schedule 3 and cl 3.2 may proceed under a complying development certificate in certain circumstances. Third, development not falling into the exempt or complying categories requires development consent from the Council, with mandatory assessments under particular clauses (for example heritage cl 5.10, flood planning cl 5.21, aquaculture cl 5.19). The Plan also contains provisions dealing with subdivision (cl 2.6), demolition (cl 2.7), temporary use (cl 2.8), and a specific prohibition on canal estate development (cl 2.9).
The Plan interfaces with State instruments. It is subject to State environmental planning policies that prevail under section 3.28 of the Environmental Planning and Assessment Act as noted at cl 1.9(1). It expressly authorises a limited power to suspend some private covenants or agreements to allow development consistent with the Plan (cl 1.9A). The Plan delegates particular administrative matters: classification and reclassification of public land (cl 5.2 and Schedule 4), and designates the relevant State acquisition authority for land reserved for public purposes (cl 5.1 and Land Reservation Acquisition Map).
Current sections
Direct links to the current provisions in Gundagai Local Environmental Plan 2011.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Aquaculture; Dwelling houses; Extractive industries; Farm buildings; Function centres; Intensive livestock agriculture; Local distribution premises; Open cut mining; Roads; Roadside stalls; Any other development not specified in item 2 or 4
4
Prohibited
4 Prohibited
4 Prohibited
Amusement centres; Attached dwellings; Business premises; Cemeteries; Centre-based child care facilities; Community facilities; Dual occupancies; Eco-tourist facilities; Entertainment facilities; Exhibition homes; Exhibition villages; Hardware and building supplies; Health services facilities; Home occupation (sex services); Industrial retail outlets; Industrial training facilities; Marinas; Mooring pens; Mortuaries; Multi dwelling housing; Office premises; Public administration buildings; Registered clubs; Residential flat buildings; Respite day care centres; Restricted premises; Semi-detached dwellings; Seniors housing; Service stations; Sex services premises; Shop top housing; Specialised retail premises; Storage premises; Timber yards; Vehicle body repair workshops; Vehicle sales or hire premises; Wharf or boating facilities; Wholesale supplies
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Part 6
Additional local provisions
Part 6 Additional local provisions
Part 6 Additional local provisions
6
Biodiversity protection
6 Biodiversity protection
6.1 Biodiversity protection
(1) The objective of this clause is to maintain terrestrial and aquatic biodiversity, including the following—
(a) protecting native fauna and flora,
(b) protecting the ecological processes necessary for their continued existence,
(c) encouraging the recovery of native fauna and flora and their habitats.
(3) Before determining a development application for development on land to which this clause applies, the consent authority must consider any adverse impact of the proposed development on the following—
(a) native ecological communities,
(b) the habitat of any threatened species, populations or ecological community,
(c) regionally significant species of fauna and flora or habitat,
(d) habitat elements providing connectivity.
(4) Development consent must not be granted to development on land to which this clause applies unless the consent authority is satisfied that—
(a) the development is designed, sited and will be managed to avoid any adverse environmental impact, or
(b) if that impact cannot be avoided—the development is designed, sited and will be managed to minimise that impact, or
(c) if that impact cannot be minimised—the development will be managed to mitigate that impact.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
(When this Plan was made this Schedule was blank.)
(c) land within a wetland of international significance declared under the Ramsar Convention on Wetlands.
Note.
Nothing in this clause affects any requirement under an Act relating to land specified in this clause to obtain a licence or other authority under that Act for development of the land.
8
Flood liability
8 Flood liability
8 Flood liability
Must be designed or constructed on land so that it will not be inundated by the discharge of a 1:100 ARI (average recurrent interval) flood event.
9
Species selection
9 Species selection
9 Species selection
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Gundagai Local Environmental Plan 2011.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in that part of the Cootamundra-Gundagai Regional local government area to which this Plan applies (in this Plan referred to as Gundagai) in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to retain the distinctive character of Gundagai town in its riparian setting,
(b) to protect Gundagai’s crop and pasture lands and vineyards from adverse environmental impacts,
(c) to protect environmentally sensitive land and important fauna and flora,
(d) to protect, conserve and enhance Gundagai’s rich indigenous and non-indigenous cultural heritage,
(e) to encourage economic growth, employment creation and business opportunities in the rural, village and urban areas of Gundagai,
(f) to maintain Sheridan Street as Gundagai town’s primary area for business, civic and cultural uses and visitor services,
(g) to encourage the renewal and consolidation of older residential areas close to the Gundagai town centre to provide appropriate housing that meets the needs of the community,
(h) to ensure that all development in Gundagai is required to comply with the principles of ecologically sustainable development.
Finally, the Plan contains several entries noted as not adopted (for example height controls cl 4.3, floor space ratio cl 4.4) and specific local additions (Schedule 1 permits health consulting rooms at 236 Punch Street with development consent). It cross‑references a number of other Acts and guidelines (for example the Heritage Act 1977 in cl 5.10, the Considering Flooding guideline in cl 5.21), so the mechanical operation of the Plan often depends on external instruments and maps (cl 1.7; cl 1.3).
Main concepts
The Plan organises land use regulation around zoning, consent categorisation, mapped controls, and site‑specific standards. The zoning taxonomy identifies rural, residential, employment, mixed use, special purpose, recreation, conservation and waterways zones (cl 2.1; cl 2.2). Each zone is accompanied by objectives, a list of development permitted without consent, development permitted with consent, and development prohibited, found in the Land Use Table that accompanies Part 2 (cl 2.3). The consent authority must have regard to zone objectives when determining applications (cl 2.3(2)).
Consent categorisation is central. The Plan identifies exempt development (cl 3.1; Schedule 2), complying development (cl 3.2; Schedule 3), and development requiring full development consent from the Council. Exempt or complying development is excluded from environmentally sensitive areas as defined (cl 3.3). The Plan requires development consent for demolition (cl 2.7), subdivision (cl 2.6), and many works in heritage areas (cl 5.10). Complying development certificates are subject to conditions referenced in Schedule 3 and the State SEPP provisions (cl 3.2(4); sch.3‑sec).
Maps are a material part of the Plan. The Land Zoning Map, Lot Size Map, Heritage Map and various Natural Resources Sensitivity maps are referenced repeatedly (for example cl 1.7; cl 2.2; cl 4.1(2); cl 6.1(2); cl 6.2(2); cl 6.3(2)). The Plan treats those maps as adopted, amendable and authoritative for determining which provisions apply to particular parcels (cl 1.7).
Site and activity‑specific regimes are another main concept. Notable examples include:
Minimum subdivision lot sizes and exceptions for R1 where lots can be below map minimums if certain service connections and floor size minima are met (cl 4.1(3A)); community title specific minimums (cl 4.1AA); rural subdivision flexibilities and limitations (cl 4.2; cl 4.2A; cl 4.2B).
Heritage controls requiring consent for demolition, excavation and alteration of heritage items and Aboriginal places, with mandatory notification to Heritage Council or local Aboriginal communities in some cases (cl 5.10(2), (7), (8), (9)).
Biodiversity, land protection and water protection clauses that apply to land identified as “sensitive” on Natural Resources Sensitivity maps and that impose threshold tests on consent (cl 6.1-6.3).
Aquaculture controls in cl 5.19 and Schedule 6 that set siting and operational requirements and allow certain extensive pond‑based aquaculture without consent in specified rural zones (cl 5.19(4); Schedule 6).
Flood planning requirements that condition consent on compatibility with flood function, impacts, evacuation, and climate change considerations and that direct the consent authority to the Considering Flooding in Land Use Planning Guideline (cl 5.21).
Rules about statutory primacy and interaction are explicit. The Plan is subject to SEPPs that prevail under the Act (cl 1.9(1)). Clause 1.9A provides an express power to suspend private covenants where necessary to enable development permitted by the Plan, subject to enumerated exceptions and approval under s 3.16 of the Act.
Finally, the Plan sets out controls limiting local decision making in particular policy areas, for example the prohibition on refusing applications for licensed premises based on the character or noise of music, provided noise can be managed to an acceptable level (cl 5.20). This creates a discrete substantive rule protecting certain forms of entertainment use from refusal on specific grounds.
Who it affects
Primary decision‑maker and regulator
The Council is the designated consent authority for the Plan (cl 1.6). Council officers, planning staff and councillors will therefore bear the administrative and discretionary responsibilities associated with determining development applications, enforcing conditions, and applying the Plan’s zone objectives and site‑specific clauses.
Developers and landowners
All landowners within the Plan area are affected. Permissible uses and prohibited uses are defined by zone (cl 2.3; Land Use Table). Landowners seeking development that is not specified as exempt or complying must obtain development consent and satisfy the Council’s requirements, including those in Part 4 and Part 6 (for example cl 4.1 subdivision standards; cl 6.1 biodiversity; cl 6.5 earthworks).
Prospective purchasers must check the Land Zoning Map, Lot Size Map, Heritage Map and the Natural Resources Sensitivity maps (cl 1.7; cl 2.2; cl 4.1(2); cl 6.1(2)) to understand permitted uses and constraints.
Neighbours and local community
The Plan shapes amenity, local economic opportunities and environmental quality. For example, cl 5.20 restricts the grounds on which Council can refuse licensed premises based on music and related factors, which affects neighbours’ ability to object on those particular grounds. Heritage and biodiversity protections (cl 5.10; cl 6.1‑6.3) impose conservational duties that protect communal cultural and environmental assets.
Sectoral interests and industry
Agriculture, forestry and aquaculture sectors are directly regulated. Zones RU1, RU3 and RU4 list agricultural and forestry uses and specify where aquaculture is permitted and when consent is required (cl 2.1; cl 5.19). Schedule 6 sets operational and site location requirements for pond‑ and tank‑based aquaculture (Schedule 6 Part 1 and Part 2).
Tourism and retail operators will look to the SP3 Tourist and E1 Local Centre/MU1 Mixed Use zones for permitted uses and constraints.
State and Crown bodies
Several provisions affect Crown and State entities: clause 5.12 confirms that the Plan does not restrict development carried out under State SEPPs and does not prevent Crown use of existing Crown buildings; clause 1.9A(3) preserves public authority registered instrument rights; clause 5.1 designates relevant State authorities for owner‑initiated acquisition (Land Reservation Acquisition Map).
Owners of instruments and covenants
The suspension of covenants provision (cl 1.9A) means private land covenants and agreements may be rendered inoperative to the extent necessary to permit development consistent with the Plan, subject to explicit exclusions such as covenants imposed by Council, conservation agreements under the National Parks and Wildlife Act, biobanking agreements, and planning agreements (cl 1.9A(2)). This affects parties to private instruments and may alter the legal position and expectations in land contracts.
Heritage and Aboriginal interests
Owners of heritage items and land within heritage conservation areas are affected by strict consent requirements (cl 5.10). Developers proposing works that may impact Aboriginal places must notify local Aboriginal communities and take responses into account (cl 5.10(8)). Archaeological sites trigger mandatory notification to the Heritage Council in some circumstances (cl 5.10(7)).
Utilities and infrastructure providers
Clause 6.6 requires essential services to be available or arranged, which requires coordination with water, sewer, power and roads authorities. The Plan also identifies Transport for NSW as the relevant acquisition authority for classified roads on the Land Reservation Acquisition Map (cl 5.1(2)).
Legal and compliance advisers
Practitioners advising on development applications must factor in multiple cross‑references with other statutes and guidelines cited in the Plan (for example the Environmental Planning and Assessment Regulation 2021 as noted in cl 4.6; the Considering Flooding guideline in cl 5.21), and must check the Plan’s maps and Schedules for parcel‑specific constraints.
Who pays and who decides
Developers and applicants pay application fees, the cost of preparing environmental assessments, heritage assessments and other supporting materials required by the consent authority (e.g. heritage management documents under cl 5.10(5)). The Council decides on consent applications, subject to statutory obligations and the Plan’s clauses (cl 1.6; cl 2.3(2)). State authorities decide on acquisitions designated by the Land Reservation Acquisition Map (cl 5.1).
Key duties and rights
Primary duties
Obtain consent where required: The Plan requires development consent for a broad range of activities including subdivision (cl 2.6), demolition (cl 2.7), most development listed as being “permitted with consent” in the Land Use Table (cl 2.3(1)), and site‑specific triggers such as works affecting heritage items (cl 5.10(2)) and earthworks except where exempt or ancillary (cl 6.5(2)).
Compliance with exempt/compliant standards: Exempt development must meet the standards in Schedule 2 and cl 3.1, including Building Code compliance and avoidance of designated development and State Heritage Register items (cl 3.1(2)‑(4)). Complying development must meet the standards in Schedule 3 and be permissible in the relevant zone (cl 3.2(2)‑(3)).
Site‑specific obligations for sensitive land: Where land is identified as “sensitive” on Natural Resources Sensitivity maps, the consent authority must consider specific impacts and must be satisfied that development avoids, minimises or mitigates harm (cl 6.1(3)‑(4); cl 6.2(3)‑(4); cl 6.3(3)‑(4)). These are mandatory pre‑conditions to consent.
Essential services: Before granting consent, the Council must be satisfied that essential services are, or will be, available (cl 6.6). This places an evidentiary burden on applicants to demonstrate water, power, sewage and access arrangements.
Heritage process obligations: Applicants proposing works affecting heritage items, heritage conservation areas, archaeological sites or Aboriginal places must follow the notification and assessment processes stated in cl 5.10, including potential Heritage Council notification (cl 5.10(7), (9)) and local Aboriginal community consultation (cl 5.10(8)). The consent authority may require heritage management documents or conservation management plans (cl 5.10(5)‑(6)).
Discretion and record‑keeping duties
Exceptions to development standards: The consent authority may grant consent that contravenes a development standard only if the applicant demonstrates compliance is unreasonable or unnecessary and there are sufficient environmental planning grounds (cl 4.6(2)‑(3)). The consent authority must keep a record of its assessment under cl 4.6(4). That creates a record‑keeping duty and requires reasoning to be captured.
Development near zone boundaries: The consent authority can grant consent for uses permissible in an adjoining zone within 20 metres where satisfied compatibility and desirability tests are met (cl 5.3). This is a discretionary flex provision but requires consideration against stated objectives.
Rights and entitlements
Right to apply for consent: The Plan does not limit who may apply for development consent; applicants retain the right to submit applications and to seek compliance with the Plan’s exception provisions (for example cl 4.6).
Right for certain small aquaculture and intensive livestock ventures to proceed without consent when they meet the thresholds and siting restrictions in cl 5.18(4)‑(5) and cl 5.19(4); Schedule 6 respectively.
Right to conservation incentives: The consent authority may grant consent to otherwise prohibited development on heritage items or Aboriginal places where it is satisfied that conservation is facilitated and the conditions in cl 5.10(10) are met. This is an explicitly instrumented right to seek trade‑offs between conservation outcomes and alternate development uses.
Right to exempt development where Schedule 2 standards are met, subject to limitations such as not affecting items on the State Heritage Register (cl 3.1(3)(d)).
Constraints on private contracts
Suspension of covenants: Clause 1.9A provides that, to enable development in accordance with the Plan, a private agreement, covenant or similar instrument that restricts carrying out that development does not apply to the extent necessary to serve the purpose, with express exclusions (cl 1.9A(1)‑(2)). This is a statutory limitation on private restrictive instruments, altering the practical enforceability of certain covenants where they would block development permissible under the Plan, except for those outlined in cl 1.9A(2).
Procedural duties
Notification and consultation duties: For archaeological sites, the consent authority must notify the Heritage Council and consider its response (cl 5.10(7)). For Aboriginal places of heritage significance, the consent authority must notify local Aboriginal communities and consider any responses within 28 days (cl 5.10(8)). These impose statutory consultation obligations which can delay determination timetables if not anticipated.
Record of approvals and maps
Maps and published materials: The Plan requires the keeping and public availability of maps in accordance with Ministerial arrangements (cl 1.7(3)). The Land Use Table expressly requires regard to zone objectives when assessing applications (cl 2.3(2)), so applicants should align proposals with zone objectives.
Taken together, the Plan creates a duty‑laden consent environment for most development in its area, with statutory rights to pursue exempt or complying pathways where the controlling standards are met, and procedural duties for the consent authority to notify specific heritage and environmental stakeholders.
Penalties and enforcement
The Plan itself does not set out a schedule of monetary penalties or criminal offences. Enforcement and penalties for breaches of development control operate through the Environmental Planning and Assessment Act and its regulations, and through local government enforcement mechanisms, as implied by the Plan’s requirement for development consent and by references to the Act. Practitioners should therefore read the Plan in conjunction with the enforcement provisions of the Act and associated Regulations.
Mechanisms of enforcement and regulatory consequence set out or implied in the Plan include:
Consent requirement as gateway: Many activities are permitted only with development consent (for example subdivision cl 2.6; demolition cl 2.7; many items listed in the Land Use Table cl 2.3). Carrying out development without required consent exposes the proponent to enforcement actions under the Act, including orders to cease work, remediation notices and penalties under the Act rather than the Plan itself.
Conditions, certificates and compliance: Complying development certificates under Schedule 3 are subject to conditions (sch.3‑sec). Compliance certificates and conditions are enforceable through the Act and the Building Code.
Record and justification obligations: The consent authority must keep records where it grants consent under the exceptions to development standards (cl 4.6(4)). Failure to document the exercise of discretion could expose the authority to judicial review challenges under the Act.
Heritage enforcement pathways: The Plan requires consent for demolition or alteration of heritage items and imposes procedural duties such as Heritage Council notification (cl 5.10). Unauthorised demolition or disturbance of heritage items or archaeological sites will attract enforcement under the Heritage Act 1977 and the Act, where the Plan makes the activity consent‑triggered.
Planning agreements and covenants: Clause 1.9A(3) preserves the rights or interests of public authorities under registered instruments. Enforcement of those registered rights remains available to public authorities through registration and other statutory channels.
Flood and environment protections: Clauses such as 5.21 (flood planning) and 6.1-6.3 (biodiversity/land/water protection) make consent conditional on compatibility with flood function and environmental protection. Approvals granted contrary to those clauses without proper assessment could be vulnerable to review and lead to enforcement actions, required remediation or revocation under the Act.
Who enforces
The Council, as consent authority, is primarily responsible for day‑to‑day regulation, decisions on compliance and enforcement within the Plan area (cl 1.6). State agencies such as the Heritage Council or the Minister administering the National Parks and Wildlife Act have specific roles where the Plan refers to them (for example cl 5.1(2); cl 5.10(7), (9)).
Evidence and procedural implications
Many Plan clauses require satisfaction or assessment by the consent authority before consent can be granted (for example cl 6.6 essential services; cl 5.19 aquaculture and Schedule 6 site requirements). This creates evidentiary duties on applicants; failure to provide adequate information can be a lawful reason for refusal. Conversely, showing compliance with the Plan’s site‑specific requirements will reduce enforcement risk.
Practical note
Because the Plan cross‑references other Acts and guidelines, enforcement often involves multiple regimes. For example, contravening a heritage protection provision may attract enforcement under both this Plan (as a breach of development consent requirements) and the Heritage Act 1977. Practitioners should therefore plan for administrative, civil and potentially criminal enforcement pathways available under the statute and implementing regulations rather than expecting penalty schedules within the Plan itself.
How it interacts with other laws
The Plan is expressly designed to operate within a web of State legislation, regulations and policies. It repeatedly cross‑references and defers to State instruments, and in some cases preserves the operation of other Acts. The key interactions and the operative mechanisms are:
Primacy of State environmental planning instruments
Clause 1.9(1) states the Plan is subject to any State environmental planning policy (SEPP) that prevails over the Plan under section 3.28 of the Act. That sets the hierarchy where SEPPs will override inconsistent local provisions. Practitioners must therefore test local provisions against applicable SEPPs.
Links with the Environmental Planning and Assessment Act and Regulation
The Plan repeatedly refers to procedural and substantive requirements under the Act. For example cl 1.2 states the Plan’s aim is to make local provisions in accordance with the relevant standard environmental planning instrument under s 3.20 of the Act. Clause 4.6(3) explicitly refers to the Environmental Planning and Assessment Regulation 2021 requiring an accompanying document for proposed contraventions of development standards. The Plan thus operates within the Act’s procedural and merits framework.
Heritage law
The Plan incorporates Heritage Act processes by requiring notification of the Heritage Council for archaeological sites and State heritage items (cl 5.10(7), (9)). That creates an interaction where both the Plan and the Heritage Act guide decision‑making and consultation steps.
Native vegetation, biobanking and Crown land
The suspension of covenants clause (cl 1.9A) excludes various instruments tied to conservation or Crown land management, including relevant instruments under the Crown Land Management Act 2016 (cl 1.9A(2)(b)), conservation agreements under the National Parks and Wildlife Act 1974 (cl 1.9A(2)(c)), property vegetation plans under the Native Vegetation Act 2003 (cl 1.9A(2)(e)), and biobanking agreements under the Threatened Species Conservation Act 1995 (cl 1.9A(2)(f)). This shows that the Plan deliberately preserves other statutory conservation instruments from suspension.
Land acquisition and public land law
Clause 5.1 identifies the relevant State acquisition authority for land shown on the Land Reservation Acquisition Map, tying the Plan to the Land Acquisition (Just Terms Compensation) Act 1991 for owner‑initiated acquisition. Clause 5.2 deals with classification and reclassification of public land under the Local Government Act 1993, including discharge of trusts and the need for Governor’s approval for some reclassifications (cl 5.2(5) note).
Fisheries and aquaculture legislation
Aquaculture provisions refer to the Fisheries Management Act 1994 and aquaculture industry development plans (cl 5.19). Schedule 6 also references the Fisheries Management (Aquaculture) Regulation 2017. These references mean aquaculture proposals must also comply with fisheries law and industry development plans.
Flood and climate guidance
Clause 5.21 requires the consent authority to consider projected changes to flood behaviour as a result of climate change and directs the authority to the Considering Flooding in Land Use Planning Guideline (cl 5.21(3)‑(4)). The Plan thus operationalises a specific guideline within its consent tests.
Building Code and BASIX
Exempt and complying development provisions require adherence to the Building Code of Australia (cl 3.1(3)(a); cl 3.2(3)(b)). Clause 4.6(8) prevents use of the exceptions clause to contravene development standards relevant to BASIX commitments set out in regulations.
Local Government and Crown use
Clause 5.12 confirms that the Plan does not restrict or prohibit (and does not enable restricting) development authorised under State SEPP Chapter 2 (Transport and Infrastructure) and does not limit Crown use of existing buildings. Clause 5.2 further brings the Local Government Act into play for public land classification.
Regulatory gaps and “not adopted” entries
Several potentially important local standards are marked as “[Not adopted]” (for example cl 4.3 height of buildings; cl 4.4 floor space ratio; cl 4.5 calculation of FSR). Where local numeric standards are not adopted, state legislation and SEPPs will fill the gap, or development assessment must rely on zone objectives and other applicable guidelines. Practitioners must therefore assess which State instruments apply to fill absent local controls.
Practical effect
The Plan functions as local detail within the broader State planning framework. It delegates to and preserves obligations under other statutes where necessary, for example heritage and fisheries, while asserting local regulation on topics like lot sizes, heritage items and aquaculture operational standards. In every instance where the Plan references another law, applicants must obtain and rely on the relevant licences, approvals or compliance under those laws in addition to Plan compliance (for example cl 3.1 note that exempt development is not exempt from other Acts).
Amendment history
The Plan text carries embedded amendment annotations that identify changes made at particular times. Using only the amendment notes contained in the instrument, the following history can be drawn from the Plan’s annotations. These are the amendments as recorded in the Plan text; practitioners should still confirm the consolidated version on the NSW legislation website for exact dates and instrument numbers.
2015 amendments: Clause 4.1 was amended in 2015, recorded as "cl 4.1: Am 2015 (703), cl 4 (3)". The Land Use Table also shows amendments over 2015 (Land Use tbl: Am 2015 (703), cl 4 (1) (2)).
2016 amendments: Clause 1.2 (Aims of Plan) shows an amendment: "cl 1.2: Am 2016 (703), cl 5 (1)". Land Use Table and other entries show amendments in 2016 (2016 (168), Sch 1 [1] [2]; 2016 (703), cl 5 (2)).
2017 amendments: The Land Use Table indicates an amendment in 2017 (2017 (493), Sch 1.1 [1]).
2018 amendments: Clause 5.4 (controls relating to miscellaneous permissible uses) notes amendments in 2018 and 2023: "cl 5.4: Am 2018 (406), Sch 1.58 [1] [2]; 2023 (458), Sch 1[1]". The Land Use Table also lists 2018 changes (2018 (488), Sch 1.1 [1]).
2019 amendments: Clause 1.8A (savings provision relating to development applications) was added/amended: "cl 1.8A: Am 2019 (621), Sch 5[1]". Clause 1.9A (suspension of covenants) was amended in 2019: "cl 1.9A: Am 2019 (621), Sch 5[2]-[4]". The Land Use Table contains 2019 amendments (2019 (137), Sch 6 [1]).
2020 amendments: Schedule 1 (Additional permitted uses) was amended in 2020, recorded as "sch 1: Am 2020 (21), cl 4(1)". That change added the specific permitted use at 236 Punch Street (Schedule 1, Item 1).
2021 amendments: Schedule 5 (Environmental heritage) was amended in 2021: "sch 5: Am 2021 (437), Sch 1[3]-[21]". Clause 3.3 references changes; clause 6.4 was repealed in 2021: "cl 6.4: Rep 2021 (225), Sch 1."
2022 amendments: Clause 2.1 zoning list was amended in 2022: "cl 2.1: Am 2022 (832), Sch 1.8[1]". Clause 4.2A and related clauses show 2022 amendments: "cl 4.2A: Am 2022 (832), Sch 1.8[3] [4]". The Land Use Table also records 2022 amendments (2022 (314), Sch 1; 2022 (832), Sch 1.8[1A]).
2023 amendments: Clause 2.1 indicates insertion by 2023 in at least one instance (ins 2023 (82), Sch 1.1[13]) as annotated in the Land Use Table. Clause 5.4 shows 2023 amendment as above.
How the Plan records amendments
The Plan’s margin notes and bracketed annotations identify the amending instrument numbers and schedule/clause references where the change occurred. The Plan itself does not include consolidated historical explanatory materials beyond the marginal amendment notes. Practitioners should consult the NSW legislation website for the consolidated text and full instrument details.
Limitations of this summary
The annotations in the Plan reflect the changes recorded in the document provided. For precise chronology, exact wording of each amending instrument, commencement dates and transitional arrangements, refer to the official consolidated Plan and the published amending instruments on the NSW legislation website.
Litigation history
The Plan text as provided does not include or reference any judicial decisions, appeal determinations or litigation history. There are no cases named in the instrument. The Plan does set out processes and record‑keeping obligations (for example cl 4.6(4) requires the consent authority to keep a record when granting consent that contravenes a development standard) that create administrative decision records which can be subject to merits review or judicial review under the Environmental Planning and Assessment Act and relevant judicial review principles, but the instrument itself does not record any past litigation or appeal outcomes.
Practical implications for practitioners
Absence of litigation history in the Plan means there is no Plan‑specific precedent recorded within the instrument. Advisers should therefore:
Search case law databases, tribunal decisions and Court records for litigation involving the Plan, the Council, or particular clauses (for example cl 4.6 exceptions to development standards, cl 5.10 heritage procedural obligations, cl 1.9A covenant suspension) to identify how courts or tribunals have interpreted comparable provisions elsewhere.
Review any administrative appeal records (for example merits review to the Land and Environment Court) and relevant published decisions that engage the same statutory provisions referenced by the Plan (for example s 3.28 SEPP primacy, or s 3.20 standard environmental planning instruments).
Consider that the Plan’s exceptions clause (cl 4.6) could be a likely locus for legal challenge because it involves the consent authority exercising discretion to permit contraventions of development standards.
If a user requires a litigation search, that must be done against external case law and tribunal databases; the Plan does not itself supply litigation references.
Gotchas
Map dependency and the necessity to check maps
Many Plan provisions are map‑triggered. The Land Zoning Map, Lot Size Map, Heritage Map, Natural Resources Sensitivity maps and Land Reservation Acquisition Map determine whether particular clauses apply (cl 1.7; cl 2.2; cl 4.1(2); cl 6.1(2); cl 5.1(2)). Failure to check the correct maps for a parcel is a common practical trap. Clause 1.7 emphasises that named maps are authoritative and may be amended, and are to be made publicly available.
Savings provision for pending applications
Clause 1.8A provides that a development application made before the Plan’s commencement and not finally determined must be determined as if the Plan had not commenced. This means timing of application lodgement relative to Plan commencement can determine which instrument applies. The Plan includes a note on the Act’s Division 3.5 transitional arrangements. Practitioners must confirm the dates.
Suspension of private instruments
Clause 1.9A permits suspension of covenants, agreements or similar instruments to the extent necessary to enable development carried out in accordance with the Plan or with consent. This will surprise parties relying on private covenants. The provision contains important exceptions, for example covenants imposed by the Council, conservation agreements under National Parks and Wildlife Act, biobanking agreements, and planning agreements (cl 1.9A(2)(a)‑(g)). Three practical consequences follow: (a) do not assume an old restrictive covenant will block a consentable development; (b) check whether the covenant is of the excluded types; (c) consider the potential for disputes where beneficiaries of covenants rely on continued enforceability.
Secondary dwelling and subdivision traps
Clause 2.6(2) prohibits subdivision that would separate principal and secondary dwellings unless minimum lot sizes on the Lot Size Map are met. The definition of secondary dwelling (in the Dictionary) requires the secondary dwelling to be on the same lot as the principal dwelling. Additionally, cl 5.4(9) caps secondary dwelling floor areas outside rural zones at either 60 sqm or 50 percent of the principal dwelling, whichever is greater. This combination can frustrate attempts to subdivide around secondary dwellings.
Minimum lot size exceptions and services
Clause 4.1(3A) permits lots in R1 General Residential below the Lot Size Map minimum if they are not less than 450 sqm and are capable of connection to Council water and sewer. That creates a discrete services-based exception; applicants must demonstrate capacity to connect to Council infrastructure. For community title schemes cl 4.1AA preserves minimum sizes in defined zones and applies despite cl 4.1.
“Not adopted” clauses leave gaps
Height (cl 4.3), floor space ratio (cl 4.4) and some other locally normative controls are noted as “[Not adopted]”. Where local numerical standards are not adopted, assessment must proceed by reference to other statutory instruments, zone objectives and state policies. This creates uncertainty for applicants expecting local quantitative standards.
Heritage triggers are broad and procedural
Clause 5.10 requires consent for demolition, moving or altering heritage items, Aboriginal objects and works within heritage conservation areas, and it allows the consent authority to require heritage management documents and conservation management plans (cl 5.10(2), (5), (6)). It also mandates notification of Heritage Council for archaeological sites (cl 5.10(7)) and consultation with local Aboriginal communities for Aboriginal places (cl 5.10(8)). These steps can add assessment time and cost and may produce binding remediation or conservation conditions (cl 5.10(10)).
Exempt/complying development exclusions for environmentally sensitive areas
Clause 3.3 excludes environmentally sensitive areas from exempt or complying development. The Plan’s definition of such areas includes coastal waters, Ramsar wetlands, land of high Aboriginal cultural significance and land identified in any environmental planning instrument as high biodiversity significance (cl 3.3(2)(g)). If your site lies within or near these areas (including within 100 m of some), the simpler exempt/compliant pathways will not be available.
Music and entertainment protection
Clause 5.20 prevents the consent authority from refusing licensed premises on various grounds relating to music, performance and dancing, and it limits refusals on noise grounds if noise can be managed to an acceptable level. For neighbours and amenity concerns, this narrows the grounds available for objection and creates evidentiary issues about what constitutes acceptable noise management.
Aquaculture and intensive livestock thresholds
Clause 5.18 sets out capacity thresholds under which intensive livestock agriculture may be undertaken without consent, but also sets stringent siting restrictions (for example distances from other farms and dwellings). Schedule 6 sets pond design, discharge and screening requirements for aquaculture. Failure to meet those thresholds or siting requirements means consent will be required and the Council will test operational and environmental metrics.
Flood and climate obligations
Clause 5.21 requires the consent authority to consider projected flood behaviour as a result of climate change and the Considering Flooding guideline. If a site is within a flood planning area, development consent must not be granted unless the development satisfies multiple flood safety and environmental tests (cl 5.21(2)). This can materially affect developable area, design and evacuation planning.
Record keeping for exceptions to standards
When a consent authority permits contraventions of development standards under cl 4.6, it must keep a record of its assessment (cl 4.6(4)). Practitioners relying on the exceptions provision must prepare robust documentation demonstrating the cl 4.6(3)(a) and (b) tests (that compliance is unreasonable or unnecessary and there are sufficient environmental planning grounds).
Specific local addenda and schedules
Schedule 1 contains a site‑specific additional permitted use for health consulting rooms at 236 Punch Street subject to consent. Small, parcel‑specific entries in schedules can create concentrated rights and exceptions that are easily missed.
How to comply
Step 1: Identify zoning, overlays and maps
Check the Land Zoning Map to identify the zone applying to the parcel (cl 2.2). Check the Lot Size Map for minimum subdivision sizes and the Heritage Map for heritage items or conservation areas (cl 4.1(2); cl 5.10 note). Check the Natural Resources Sensitivity maps for biodiversity, land and water sensitivity (cl 6.1(2); cl 6.2(2); cl 6.3(2)). Confirm whether the parcel appears on the Land Reservation Acquisition Map for acquisition implications (cl 5.1(2)).
Step 2: Confirm whether the proposal is exempt, complying or consent development
Compare the proposal against Schedule 2 exempt development clauses and Schedule 3 complying development items (cl 3.1; cl 3.2; schs 2-3). If the development meets exempt or complying criteria, ensure compliance with the Building Code of Australia and other statutory approvals required by other Acts (cl 3.1(3)(a); cl 3.2(3)(b)). Remember cl 3.3 excludes environmentally sensitive areas from exempt or complying pathways.
Step 3: Check zone‑specific permissibility and local quantitative limits
Consult the Land Use Table for the zone (cl 2.3). If the use is listed as “permitted with consent”, prepare a development application. For uses listed as “permitted without consent”, ensure the activity still meets exempt/compliant tests and other statutory approvals. Note zone‑specific quantitative caps such as bed limits for bed and breakfast (cl 5.4(1)), floor area limits for home industry/business (cl 5.4(2)‑(3)), and retail area caps for industrial retail or artisan food uses (cl 5.4(4), (10)). For secondary dwellings, ensure floor area limits are observed (cl 5.4(9)).
Step 4: Prepare technical assessments required by Plan clauses
Heritage: If the proposal affects a heritage item or is within a heritage conservation area, prepare a heritage management document or conservation management plan if required, and be ready to notify the Heritage Council for archaeological sites or to consult local Aboriginal communities for Aboriginal places (cl 5.10(4)‑(9)). Demonstrate how the proposal will conserve heritage significance or, where conservation incentives are sought, how conservation works will be secured by condition (cl 5.10(10)).
Biodiversity, land and water: For land marked as “sensitive”, provide ecological assessments, habitat impact statements, riparian and hydrological assessments and mitigation/offsetting proposals to show the development avoids, minimises or mitigates impacts per cl 6.1‑6.3.
Flooding: If within a flood planning area, prepare a flood risk assessment that addresses compatibility with flood function, evacuation and climate change projections, and refer to the Considering Flooding guideline (cl 5.21(2)‑(4)).
Earthworks and fill: For earthworks, provide geotechnical reports, fill quality information, drainage impact assessments and erosion control measures (cl 6.5(3)(a)‑(g)). Identify sources and destinations of fill (cl 6.5(3)(e)).
Essential services: Demonstrate availability or arrangements for water, electricity, sewage disposal, stormwater and road access (cl 6.6).
Step 5: Address statutory interactions and approvals
Identify other Acts that require approvals or licences (for example Fisheries Management Act for aquaculture cl 5.19; Heritage Act for State heritage items cl 5.10; Local Government Act for public land classification cl 5.2). Obtain or concurrently apply for any required State licences.
Step 6: If seeking an exception to a development standard, prepare the required justification
For development that would contravene a development standard, prepare the document required by the Environmental Planning and Assessment Regulation 2021 and demonstrate cl 4.6(3)(a) and (b): that compliance is unreasonable or unnecessary in the circumstances and that sufficient environmental planning grounds justify the contravention. Ensure the consent authority’s assessment will be recorded (cl 4.6(4)).
Step 7: For proposed developments that rely on suspension of private covenants, test the covenant type
If a restrictive covenant is an obstacle, check cl 1.9A: the Plan can render covenants unenforceable to the extent necessary to permit development, but not if the covenant is one of the excluded types listed in cl 1.9A(2). Document the extent of necessity and whether the covenant is excluded.
Step 8: Prepare community and statutory consultation packages
For heritage and Aboriginal places consult and notify as required by cl 5.10. For other sensitive proposals, prepare neighbour and community consultation strategies, but note cl 5.20 limits the grounds on which licensed premises may be refused regarding music and performance.
Step 9: Lodge the application with thorough documentation
Include the planning statement addressing zone objectives (cl 2.3(2)), technical assessments derived from the Plan’s mandatory tests (heritage, biodiversity, water, flood, services), and, if applicable, the cl 4.6 contravention justification. Where complying development is sought, ensure conformity with Schedule 3 conditions and any relevant State‑level complying codes.
Step 10: Prepare for conditions and post‑consent obligations
Expect conditions securing conservation works where conservation incentives are granted (cl 5.10(10)(c)). Be prepared for conditions relating to floodproofing, evacuation and possible future modification or relocation of buildings in flood‑affected areas (cl 5.21(3)(d)). Compliance with conditions is enforced under the Act.
Practical checklist items
Confirm up‑to‑date maps on the NSW Planning Portal as the Plan requires maps to be maintained and published (cl 1.7(3)).
Verify whether any local additional permitted use (Schedule 1) applies to the site.
For aquaculture and intensive livestock, check Schedule 6 and cl 5.18 capacity and siting restrictions; ensure outlet screening and pond design requirements are addressed (Schedule 6 Division 2).
If in doubt about whether a proposed work is exempt, comply or requires consent, seek a preliminary meeting with Council and obtain written advice where possible. Where a proposal intends to rely on an exception to a standard (cl 4.6), early engagement with Council will shorten the formal assessment process.
This stepwise compliance pathway aligns the Plan’s mapped and clause‑specific requirements with the documentation and consultation practices expected by the consent authority, and it records the evidentiary material the Council will rely on when making decisions under the Plan.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
cl 1.8A: Am 2019 (621), Sch 5[1].
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
cl 1.9A: Am 2019 (621), Sch 5[2]–[4].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
Rural Zones
RU1 Primary Production
RU3 Forestry
RU4 Primary Production Small Lots
RU5 Village
Residential Zones
R1 General Residential
R3 Medium Density Residential
R5 Large Lot Residential
Employment Zones
E1 Local Centre
E4 General Industrial
Mixed Use Zones
MU1 Mixed Use
Special Purpose Zones
SP1 Special Activities
SP3 Tourist
Recreation Zones
RE1 Public Recreation
RE2 Private Recreation
Conservation Zones
C1 National Parks and Nature Reserves
Waterway Zones
W1 Natural Waterways
cl 2.1: Am 2022 (832), Sch 1.8[1].
2 Zoning of land to which Plan applies
2 Zoning of land to which Plan applies
2.2 Zoning of land to which Plan applies
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 182 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate may exceed the maximum number of days specified in that subclause.
(5) Subclause (3)(d) does not apply to the temporary use of a dwelling as a sales office mentioned in subclause (4).
This is an opening excerpt, not the complete document.