This Local Environmental Plan (LEP) sets the zoning, permitted/prohibited uses, subdivision rules and site-specific controls for land in Greater Hume (land shown on the Land Application Map). It also identifies exempt and complying development and special controls for biodiversity, waterways, heritage and riverfronts.
The Plan affects landowners, developers and the Council (the consent authority (cl 1.6)). It matters because it determines when development consent is required, what uses are allowed, and what environmental and heritage conditions must be met, creating compliance obligations and decision‑making discretion.
This instrument is a local environmental plan (LEP) for the Greater Hume local government area. It sets the statutory framework that governs what land uses are permitted, allowed with consent, or prohibited across the mapped area, prescribes minimum lot sizes and a number of development controls and locational overlays, identifies heritage items and public land classifications, and records consequential repeal of earlier local instruments.
Mechanically, the Plan:
Commences seven days after publication on the NSW legislation website (cl 1.1AA).
Repeals prior local environmental plans and deemed instruments applying to the area (cl 1.8 and the associated note listing Culcairn LEP 1998, Hume LEP 2001, Interim Development Order No 1,Shire of Holbrook).
Declares the consent authority for the Plan as the Council, subject to the Environmental Planning and Assessment Act 1979 (cl 1.6).
Zones land by reference to a Land Zoning Map and prescribes zone objectives and a Land Use Table setting out permitted without consent, permitted with consent and prohibited development for each zone (cls 2.1, 2.2, 2.3).
Requires development consent for subdivision (cl 2.6) and for demolition except where exempt under an environmental planning instrument or SEPP (cl 2.7).
Provides for exempt and complying development regimes by cross-reference to Schedules 2 and 3 (Part 3, cls 3.1-3.3) and to State SEPPs (notably the State Exempt and Complying Development Codes SEPP).
Prescribes principal development standards about minimum lot sizes and a number of targeted subdivision and dwelling controls (Part 4, cls 4.1, 4.1AA, 4.1A, 4.1B, 4.2, 4.2AA, 4.2A).
Contains local overlay controls and assessment matters for environmental values: terrestrial biodiversity, riparian land and watercourses, wetlands, river front areas and riverbeds/banks (cls 6.2-6.6).
Current sections
Direct links to the current provisions in Greater Hume Local Environmental Plan 2012.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Agritourism; Air transport facilities; Airstrips; Animal boarding or training establishments; Aquaculture; Bed and breakfast accommodation; Boat building and repair facilities; Boat launching ramps; Boat sheds; Camping grounds; Caravan parks; Cellar door premises; Cemeteries; Charter and tourism boating facilities; Correctional centres; Crematoria; Depots; Dual occupancies; Dwelling houses; Environmental facilities; Extractive industries; Farm stay accommodation; Flood mitigation works; Freight transport facilities; Function centres; Heavy industrial storage establishments; Helipads; Highway service centres; Home-based child care; Home businesses; Home occupations (sex services); Hotel or motel accommodation; Industrial training facilities; Industries; Information and education facilities; Intensive livestock agriculture; Jetties; Marinas; Mooring pens; Moorings; Open cut mining; Passenger transport facilities; Recreation areas; Recreation facilities (major); Recreation facilities (outdoor); Roadside stalls; Rural industries; Rural workers’ dwellings; Signage; Truck depots; Veterinary hospitals; Water recreation structures; Water supply systems; Wharf or boating facilities
4
Prohibited
4 Prohibited
4 Prohibited
Any development not specified in item 2 or 3
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
Note.
When this Plan was made it did not include Zone RE1 Public Recreation.
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Part 6
Additional local provisions
Part 6 Additional local provisions
Part 6 Additional local provisions
6
Earthworks
6 Earthworks
6.1 Earthworks
(1) The objective of this clause is to ensure that earthworks for which development consent is required will not have a detrimental impact on environmental functions and processes, neighbouring uses, cultural or heritage items or features of the surrounding land.
(2) Development consent is required for earthworks unless—
(a) the earthworks are exempt development under this Plan or another applicable environmental planning instrument, or
(b) the earthworks are ancillary to development that is permitted without consent under this Plan or to development for which development consent has been given.
(3) Before granting development consent for earthworks (or for development involving ancillary earthworks), the consent authority must consider the following matters—
(a) the likely disruption of, or any detrimental effect on, drainage patterns and soil stability in the locality of the development,
(b) the effect of the development on the likely future use or redevelopment of the land,
(c) the quality of the fill or the soil to be excavated, or both,
(d) the effect of the development on the existing and likely amenity of adjoining properties,
(e) the source of any fill material and the destination of any excavated material,
(f) the likelihood of disturbing relics,
(g) the proximity to, and potential for adverse impacts on, any waterway, drinking water catchment or environmentally sensitive area,
(h) any appropriate measures proposed to avoid, minimise or mitigate the impacts of the development.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
(c) land within a wetland of international significance declared under the Ramsar Convention on Wetlands.
Note.
Nothing in this clause affects any requirement under an Act relating to land specified in this clause to obtain a licence or other authority under that Act for development of the land.
8
Flood liability
8 Flood liability
8 Flood liability
Must be designed or constructed on land so that it will not be inundated by the discharge of a 1:100 ARI (average recurrent interval) flood event.
9
Species selection
9 Species selection
9 Species selection
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Greater Hume Local Environmental Plan 2012.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences 7 days after it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Greater Hume in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to encourage sustainable economic growth and development in Greater Hume,
(b) to protect and retain productive agricultural land,
(c) to protect, conserve and enhance natural assets,
(d) to protect built and cultural heritage assets,
(e) to provide opportunities for the growth of townships.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
Contains targeted development-specific controls: aquaculture (cl 5.19 and Schedule 6), intensive livestock agriculture (cl 5.18), heritage conservation (cl 5.10 and Schedule 5), flood planning (cl 5.21), earthworks (cl 6.1), eco-tourist facilities (cl 5.13), and a noise/music protection provision for licensed premises (cl 5.20).
Lists local heritage items and archaeological sites in Schedule 5 and land to be reclassified or classified as operational/community land in Schedule 4.
Includes a savings provision: development applications made before commencement that are not finally determined must be determined as if the Plan had not commenced (cl 1.8A).
The Plan also records its relationship to State environmental planning policies (SEPPs) and other Acts (for example the Crown Land Management Act 2016, National Parks and Wildlife Act 1974, Land Acquisition (Just Terms Compensation) Act 1991, Local Government Act 1993), including a specific suspension-of-covenants provision to enable development in accordance with the Plan (cl 1.9A).
All mapping referenced in the Plan (Land Zoning Map, Lot Size Map, Terrestrial Biodiversity Map, Riparian Lands and Watercourses Map, Wetlands Map, Heritage Map, Land Reservation Acquisition Map) is declared part of the Plan and is to be made available on the NSW Planning Portal (cl 1.7, cl 1.3).
Main concepts
The Plan implements a classical zoning and instrument-based approach to local land-use regulation. Key concepts appearing throughout the instrument are zoning, development consent, exempt and complying development, overlay-based environmental constraints, mapped lot sizes, heritage listing, and the allocation of decision‑making to the local council as consent authority.
Zoning and Land Use Table
The Plan sets out discrete land-use zones (cl 2.1) and assigns permitted uses, uses requiring consent and prohibited uses through the Land Use Table (cl 2.3). The consent authority must have regard to the zone objectives in determining development applications (cl 2.3(2)).
Maps and Mapping as Operative Controls
The Plan repeatedly ties standards to maps: zoning (cl 2.2), lot size minima (cl 4.1(3)), heritage areas (cl 5.10 note and Schedule 5), and overlay maps for biodiversity, riparian areas and wetlands (cls 6.2-6.4). The maps are declared part of the Plan and must be available to the public (cl 1.7).
Development consent and alternatives
Some development is “permitted without consent” (no development consent required) but remains subject to Part 5 environmental assessment requirements (cl 2.3 note). Exempt development and complying development are governed by Schedule 2 and Schedule 3 respectively and by cross-reference to the State Exempt and Complying Development Codes SEPP (Part 3, cls 3.1-3.2).
Minimum lot sizes and subdivision
The Plan prescribes minimum lot sizes on the Lot Size Map and generally prohibits creation of lots below those minima (cl 4.1). It contains targeted exceptions (clauses 4.1AA, 4.1A, 4.1B, 4.2, 4.2AA) to allow particular rural, strata and split-zone subdivisions subject to conditions.
Environmental overlays and assessment matters
The Plan requires the consent authority to consider specific environmental matters before granting consent in mapped areas: terrestrial biodiversity (cl 6.2), riparian land and watercourses (cl 6.3), wetlands (cl 6.4), and river front/riverbed development with bespoke permitted purposes and criteria (cls 6.5-6.6). These clauses embody mandatory “must not grant consent unless satisfied” thresholds.
Heritage
The Plan requires development consent for demolition, alteration, subdivision and erection of buildings affecting heritage items, Aboriginal objects or items within heritage conservation areas (cl 5.10(2)). It sets notification obligations to the Heritage Council and to local Aboriginal communities in specified circumstances (cl 5.10(7) and (8)).
Flexibility and constraints
Clause 4.6 provides a mechanism for consent authorities to grant consent despite contravention of development standards, provided the applicant demonstrates compliance is unreasonable or unnecessary and there are sufficient environmental planning grounds; it also records limits to that flexibility (4.6(2)-(8)).
Special targeted controls
The Plan contains objective-led, prescriptive regimes for aquaculture (cl 5.19 together with the technical site and operational requirements in Schedule 6), intensive livestock agriculture (cl 5.18), eco-tourist facilities (cl 5.13), and flood planning (cl 5.21). Each regime couples environmental safeguards with developer obligations.
Relationship with State law and other instruments
The Plan is explicitly subject to SEPPs that prevail under the Act (cl 1.9(1)). It also suspends private covenants and similar instruments to the extent necessary to enable development in accordance with the Plan, except where specific classes of instrument are excluded (cl 1.9A).
Administrative and land ownership consequences
The Plan identifies the “relevant acquisition authority” for land reservation acquisition (cl 5.1), provides for classification/reclassification of public land under the Local Government Act (cl 5.2 and Schedule 4), and records where certain public land ceases to be a reserve if described in Schedule 4 (cl 5.2(5)).
Who it affects
Owners and occupiers of land within the Greater Hume local government area
The Plan applies to all land identified on the Land Application Map (cl 1.3). Landowners and occupiers will be directly affected by zoning, permitted uses, minimum lot sizes and overlay constraints, and by the heritage listings in Schedule 5.
Developers and applicants for development consent
All persons proposing subdivision, new buildings, demolition, or change of use must comply with the Plan’s zone rules, lot size minima, overlay requirements, and the thresholds for exempt or complying development (Part 2; Part 3; Part 4). The Plan prescribes matters the consent authority must be satisfied of before granting consent for specific forms of development (for example, aquaculture cl 5.19(2), flood‑plain development cl 5.21(2), heritage cl 5.10(2)).
The Council as consent authority
The consent authority under the Plan is the Council, subject to the Act (cl 1.6). Council is the decision maker for development applications, for imposing conditions of consent, and for classifying community land (cl 5.2). The Plan also requires Council to keep records where the exceptions to development standards are invoked (cl 4.6(4)).
State agencies and other public authorities
The Plan names state authorities in particular contexts: Transport for NSW for classified roads (cl 5.1(2) table), the Minister administering the National Parks and Wildlife Act for national park land (cl 5.1(2) table), and the corporation constituted under section 2.5 of the Act for regional open space. It preserves the rights and interests of public authorities under registered instruments (cl 1.9A(3)).
Primary producers and agricultural industries
Zone RU1 Primary Production, RU3 Forestry, RU4 Primary Production Small Lots and zone-specific agriculture rules, plus clauses on intensive livestock agriculture (cl 5.18) and farm stay/farm gate premises (cls 5.24-5.25), affect primary producers. The Plan permits many agricultural uses without consent in rural zones (see land use table entries).
Heritage owners, Aboriginal communities and proponents affecting archaeological sites
Owners of listed heritage items must obtain consent for demolition, exterior alteration or works affecting items and may be required to prepare heritage management documents or conservation management plans (cl 5.10(2),(5),(6)). The consent authority must notify the Heritage Council about certain archaeological site consents and notify local Aboriginal communities when development affects Aboriginal places of heritage significance (cl 5.10(7)-(8)).
Businesses with licensed premises (music/entertainment)
Licensed premises are explicitly protected from refusal on the basis of the genre, live/amplified nature, or performance characteristics of music provided the consent authority is satisfied noise can be managed and minimised to an acceptable level (cl 5.20).
Owners of land near mapped environmental constraints
Land identified on the Terrestrial Biodiversity Map, Riparian Lands and Watercourses Map, Wetlands Map, Lot Size Map and Heritage Map is subject to additional assessment criteria and prohibitions set out in cls 6.2-6.4, 4.1 etc., which will affect development potential and assessment requirements for owners.
Public land and councils managing land tenure
Schedule 4 sets out land to be classified or reclassified as operational or community land and records particular interests not to be discharged (cl 5.2 and Schedule 4). These provisions affect trust and reserve statuses and the administrative processes of the Council.
Prospective purchasers, financiers and surveyors
The Plan’s zoning, lot size minima, heritage listings and overlay maps are material constraints on property value, permitted future uses and lending risk. The Plan makes mapping available on the Planning Portal (cl 1.7) but purchasers must verify the specific maps and schedules applying to a parcel.
Key duties and rights
Duties of the consent authority (Council)
Consider zone objectives when determining development applications (cl 2.3(2)).
Be satisfied of specific matters before granting consent in many provisions, for example:
Minimum lot sizes and strata/community subdivision exceptions: verify compliance with cl 4.1 and exceptions in cls 4.1AA, 4.1A, 4.1B.
Eco‑tourist facilities: satisfied about connection to site values and management strategy content (cl 5.13(3)(a)-(k)).
Heritage matters: consider effect on heritage significance and request heritage management documents or conservation plans where necessary; notify Heritage Council or local Aboriginal communities in defined circumstances (cl 5.10(4)-(9)).
Biodiversity, riparian and wetlands overlays: ensure development is designed and managed to avoid, minimise or mitigate significant adverse environmental impacts (cls 6.2-6.4).
Flood planning: must be satisfied development is compatible with flood function and will not adversely affect flood behaviour, evacuation routes or the environment (cl 5.21(2)-(3)).
Aquaculture: must be satisfied proposed pond/tank aquaculture complies with Schedule 6 site and operational requirements (cl 5.19(2)-(3)).
Duties of applicants
Where applying for development that would contravene a standard, applicants must provide supporting documentation addressing cl 4.6(3)(a)-(b) (grounds that compliance is unreasonable or unnecessary and environmental planning grounds for the contravention); the Regulation requires a document to accompany such an application (cl 4.6 note).
For exempt/compliant development: satisfy the standards in Schedule 2 or Schedule 3 and the Building Code of Australia deemed-to-satisfy provisions where applicable (cls 3.1-3.2).
For heritage or archaeological proposals: prepare heritage management documents or conservation management plans if required by the consent authority (cl 5.10(5)-(6)); notify and consult where required (cl 5.10(7)-(9)).
For aquaculture and intensive livestock developments: meet the operational/site criteria set out in cl 5.18 and Schedule 6 and not be located in the excluded conservation zones or within specified buffer distances (cl 5.18(4)-(5); Schedule 6 Div 1).
Ensure essential services will be available or adequate arrangements made before consent is granted (cl 6.7).
Rights preserved or constrained by the Plan
Right to carry out development permitted without consent or exempt development, subject to compliance with the Plan and the Building Code of Australia (cl 3.1(2)-(5)).
Rights under earlier development applications are preserved: an application made before the Plan’s commencement that has not been finally determined must be determined as if the Plan had not commenced (cl 1.8A).
The Plan suspends private covenants and similar instruments to the extent necessary to permit development in accordance with the Plan, subject to listed exceptions and public authority rights preserved (cl 1.9A).
The Plan does not displace State SEPPs that prevail (cl 1.9(1)).
Record-keeping and procedural duties
The consent authority must keep a record of its assessment where development standards are contravened under cl 4.6(4).
Where an archaeological site or nominated State heritage item is affected, the consent authority must notify the Heritage Council and consider any response within 28 days (cl 5.10(7) and (9)).
Administrative duties relating to public land
The Council may classify or reclassify public land as operational or community land under the Local Government Act, and Schedule 4 records specific land that is to be so classified or reclassified (cl 5.2; Schedule 4). Reclassification may discharge reserves except where Column 3 specifies trusts not discharged (cl 5.2(5)).
Limits on decision-making
Clause 4.6 sets limits to the exercise of discretion to contravene standards: certain development standards (for example for complying development or BASIX commitments) cannot be overridden (cl 4.6(8)).
Penalties and enforcement
The Plan itself does not set out offence or penalty provisions in the text provided. Enforcement mechanisms and penalties for non-compliance with planning controls are governed by the Environmental Planning and Assessment Act 1979 and associated regulations; the Plan operates within that Act’s decision-making and enforcement framework (the Plan repeatedly refers to the Act, e.g. cl 1.6, cl 1.2 and notes across Parts). The Plan:
Establishes circumstances in which development consent is required (for example subdivision cl 2.6, demolition cl 2.7, heritage cl 5.10(2)). Carrying out development without required consent or contrary to conditions of consent will engage the enforcement provisions of the Act and the Regulation (though those penalty provisions are not reproduced in the Plan).
Requires consent authority action in particular circumstances (for example notification duties to the Heritage Council and Aboriginal communities under cl 5.10(7)-(8)); failure to comply with procedural notification requirements may be relevant to lawful grant of consent and to subsequent challenge or enforcement, although the Plan itself does not list sanctions.
Imposes “must not grant consent unless satisfied” thresholds (for instance cl 5.21 flood planning, cl 6.2 terrestrial biodiversity). If a consent authority breaches those statutory duties, that may form the basis of administrative review or judicial challenge under the Act. The Plan requires the consent authority to keep records where cl 4.6 is used (cl 4.6(4)), which will be material in any review or enforcement context.
Practical enforcement mechanisms available under the Act (not detailed in the Plan) include stop-work orders, penalties for unauthorised development, injunctions and orders to remove unauthorised works, and the capacity for third parties to seek merits review or challenge decision‑making. The Plan’s repeated cross-references to the Act and to State SEPPs signal that enforcement and penalties are to be found in those higher‑order legislative and regulatory instruments rather than in the Plan text.
How it interacts with other laws
Direct cross-references
The Plan operates subordinate to State environmental planning policies. Clause 1.9(1) expressly makes the Plan subject to SEPPs that prevail under section 3.28 of the Act. It therefore defers in any inconsistency to State policy instruments.
The Plan repeatedly cross-references other Acts and instruments and incorporates their substantive effects by reference. Examples include the Crown Land Management Act 2016, National Parks and Wildlife Act 1974 (heritage and reserve matters), Land Acquisition (Just Terms Compensation) Act 1991 (owner-initiated acquisition and identification of relevant acquisition authorities in cl 5.1), Local Government Act 1993 (classification of public land cl 5.2), Fisheries Management Act 1994 (aquaculture development plans referenced in cl 5.19), the Building Code of Australia (deemed-to-satisfy requirements for exempt and complying development cls 3.1-3.2), and the Rural Fires Act 1997 (cl 5.11).
Suspension of covenants
Clause 1.9A suspends private agreements, covenants and similar instruments to the extent necessary to enable development carried out in accordance with the Plan or with a consent granted under the Act. That suspension, however, does not apply to a number of specifically listed instruments, including covenants imposed by the Council, relevant Crown instruments, conservation agreements, Trust agreements under the Nature Conservation Trust Act 2001, property vegetation plans under the Native Vegetation Act 2003, biobanking agreements under the former Threatened Species Conservation Act 1995, and planning agreements under the Act (cl 1.9A(2)). The clause also preserves rights and interests of public authorities under registered instruments (cl 1.9A(3)).
Heritage and Aboriginal laws
Heritage protections in cl 5.10 interact directly with the Heritage Act 1977: the Plan excludes exempt/compliant development where the item is on the State Heritage Register or subject to an interim heritage order under the Heritage Act (cl 3.1(3)(d)). The Plan requires notification of the Heritage Council in a variety of circumstances, and requires consultation with local Aboriginal communities where Aboriginal places of heritage significance are affected (cl 5.10(7)-(9)).
Environmental and biodiversity law
The Plan’s biodiversity, wetland, riparian and river corridor provisions are mapped and form assessment thresholds (cls 6.2-6.5). The Plan cross-references the Biodiversity Conservation Act 2016 in Schedule 6 Division 1 and elsewhere; it excludes development from areas declared as outstanding biodiversity value (Schedule 6, Div 1, item 1). The Plan also cross-references the Considering Flooding in Land Use Planning Guideline and the Flood Risk Management Manual for flood-related definitions and guidance (cl 5.21(4)-(5)).
Agreements on acquisition and public land
The Plan specifies the “relevant acquisition authority” for particular reserved land under the owner-initiated acquisition provisions of the Land Acquisition (Just Terms Compensation) Act 1991 (cl 5.1). Schedule 4 and cl 5.2 deal with classification/reclassification and with the discharge of trusts when public land is reclassified, and record where Governor approval is required to affect those trusts (cl 5.2(5) note).
SEPP cross-coverage and the Exempt and Complying Codes
The Plan delegates detail for some exempt and complying development to the State SEPPs, particularly the Exempt and Complying Development Codes SEPP (cl 3.1 note and cl 3.2 note). Users must reconcile the Plan’s local schedules with the State SEPPs where both apply.
Building law and BASIX
The Plan requires development to meet Building Code of Australia deemed-to-satisfy provisions for exempt and complying development (cls 3.1(3)(a), 3.2(3)(b)). Clause 4.6(8) expressly prevents the clause’s exceptions being used to contravene development standards that arise from BASIX commitments or development standards for complying development.
Regulatory interface limits
Where the Plan is silent or records “[Not adopted]” for a control (for example cl 4.3 Height of buildings, cl 4.4 Floor space ratio, cl 4.5 Calculation of FSR), applicable State legislation, SEPPs or development control plans may supply the missing controls. The Plan makes those omissions explicit and therefore invites users to check the broader statutory and policy framework.
Amendment history
The Plan’s text records numerous amendments and insertions. The instrument annotates many provisions with amendment notes; these notes indicate the sequence of later local or State changes that altered particular clauses. Items expressly shown in the provided text include the following amendments and insertions (quoted by clause and recorded amendment note where present):
Clause 1.9A: Amended in 2019 (621), Sch 5[2]-[4] (this is recorded at the end of cl 1.9A).
Clause 2.1 (Land use zones): Amended 2021 (426), Sch 1[1]; and 2022 (829), Sch 1.9[1].
Land Use Table: cumulative amendments recorded in annotations: Am 2013 (711), Sch 1[1][2]; 2017 (493), Sch 1.1[1][2]; 2019 (137), Sch 6[1]; 2021 (426), Sch 1[2]; 2022 (314), Sch 1; 2022 (829), Sch 1.9[2]; 2023 (458), Sch 2.35.
Clause 4.1B (Exceptions to minimum subdivision lot sizes for certain split zones): Inserted 2025 (543), Sch 1.
Clause 4.6 (Exceptions to development standards): Amended 2022 (829), Sch 1.9[3].
Clause 4.1AA, 4.1A, 4.1B and other subdivision-related clauses contain amendment or insertion notes (for example cl 4.1A refers to later notes about strata subdivisions and 2013/2021 changes elsewhere).
Clause 1.9A carries an express notation that the Governor approved the subclauses under s 3.16 of the Act before its making (cl 1.9A(4)).
Schedule 4 has recorded amendments: Am 2020 (53), cl 4(1)(2); 2024 (26), Sch 1[1].
Clause 6.8 (Subdivision of certain land in Jindera): Inserted 2024 (25), Sch 1.
Clause 6.9 (Development in Jindera requiring preparation of development control plan): Inserted 2025 (41), Sch 1.
Clause 4.2AA (Exceptions to minimum lot sizes for certain rural subdivisions): Inserted 2013 (711), Sch 1[3].
Clause 4.6 shows repealed paragraphs and later amendments (cl 4.6: Am 2022 (829), Sch 1.9[3]).
The Plan also records repeals effected by its commencement: the earlier local instruments listed in cl 1.8 and its note were repealed when this Plan took effect.
The amendment annotations in the instrument identify the year and the statutory instrument (for example “Am 2022 (829), Sch 1.9[3]”), which signals amendments made by subsequent parliamentary instruments or Gazette notices. The Plan text as provided should be read with these amendment notes in mind and users should consult the consolidated online version or register of amendments on the NSW legislation/Planning Portal for the full legislative history and the operative dates of each amendment.
Litigation history
The Plan itself contains no record of litigation, judicial determinations or case law. The schedules, clauses and notes do not cite judgments or record disputes. Where the Plan prescribes duties, mandatory considerations or procedural steps (for example the “must be satisfied” thresholds in cls 5.13, 5.19, 5.21, 6.2-6.4 and the requirement to keep records under cl 4.6(4)), those are the statutory benchmarks that parties and a court or tribunal would use in review or enforcement proceedings under the Environmental Planning and Assessment Act 1979.
Practical implications for potential litigation risks (based on the Plan’s text)
Areas likely to generate disputes under the Plan include heritage (cl 5.10), biodiversity and riparian overlays (cls 6.2-6.3), floodplain development where the Plan imposes “must not grant consent unless satisfied” conditions (cl 5.21), and applications that rely on cl 4.6 to contravene development standards. These clauses create identifiable discretionary decision points and procedural duties (for example notification and consultation obligations) that can be challenged on administrative law grounds if not correctly applied.
The Plan’s savings provision for existing development applications (cl 1.8A) and its specific suspension of covenants (cl 1.9A) may feature in disputes where parties claim reliance on pre-commencement rights or on private covenants.
Heritage consultation duties (cl 5.10(7)-(9)) and the Plan’s documentary requirements (heritage management documents and conservation plans at cl 5.10(5)-(6)) are procedural requirements that can be material in merits review or judicial review in the event the consent authority fails to follow mandated steps.
Because the Plan does not record decisions or case law, practitioners and researchers should check the Land and Environment Court and other appellate decisions for litigation that interprets or challenges decisions made under this LEP; those sources are external to the Plan and not summarised in the instrument’s text.
Gotchas
Maps drive many outcomes , check them before relying on textual zone descriptions
Minimum lot sizes, biodiversity overlays, riparian/wetlands designations, heritage areas and rezoning are all map‑driven (cls 1.3, 1.7, 4.1(3), 6.2-6.4; Schedule 5). If a land parcel sits over mapped constraints, the corresponding clauses impose “must not grant consent unless satisfied” thresholds. Practitioners must view the current Land Zoning Map, Lot Size Map, Terrestrial Biodiversity Map, Riparian Lands and Watercourses Map and Wetlands Map on the Planning Portal, rather than rely on general descriptions.
Applications lodged before commencement may avoid the Plan’s rules
A development application made before the Plan’s commencement and not finally determined must be determined as if this Plan had not commenced (cl 1.8A). That can be decisive for projects caught between regimes.
Broad “must be satisfied” gates create evidentiary burdens
Many clauses require the consent authority to be satisfied about specific environmental or management outcomes before granting consent (for example cl 5.13 eco‑tourist facilities, cl 5.19 aquaculture, cl 5.21 flood planning, cls 6.2-6.4). Those clauses put the onus on applicants to supply robust evidence and on the consent authority to make express findings; failure to document the assessment can expose decisions to review.
Suspension of covenants is not universal
Clause 1.9A suspends private covenants and similar instruments to the extent necessary to permit development under the Plan, but it expressly excludes a list of instruments (cl 1.9A(2)) and preserves public authority rights (cl 1.9A(3)). Do not assume a private covenant is automatically overridden.
“Not adopted” entries mean local blank spots
Several controls are labelled as “[Not adopted]” (for example cl 4.3 Height of buildings, cl 4.4 Floor space ratio, cl 4.5 Calculation of FSR, cl 5.5, cl 5.6). Where a local control is “not adopted”, applicants must look to State policies, development control plans or other instruments for rules. This can produce uncertainty unless ancillary controls are located and checked.
Clause 4.6 flexibility has caps
The exceptions to development standards in cl 4.6 allow discretion but specifically exclude development standards for complying development and BASIX commitments and apply quantitative limits for subdivisions creating multiple undersized lots (cl 4.6(6), (8)). If you seek a standards variation, ensure the proposed contravention is not one of the excluded standards and document the environmental planning grounds required by cl 4.6(3).
Heritage procedures are prescriptive
Heritage consent triggers documentation (heritage management documents or conservation management plans) and mandatory notifications to the Heritage Council or local Aboriginal communities in specified circumstances (cl 5.10(5)-(9)). Failure to follow these steps may invalidate or lead to review of approvals.
Aquaculture and intensive livestock exclusions and buffers
Clauses 5.18 and 5.19 set capacity thresholds, exclusion zones and buffer distances for intensive livestock and aquaculture. For example, certain poultry farm buffer distances and capacities are specified in cl 5.18(4)-(5), and Schedule 6 excludes development from areas of outstanding biodiversity value and other reserved areas. Applicants must check both the Plan and relevant fisheries/industry development plans.
Licensed premises music protection is conditional
Clause 5.20 prohibits refusal of consent for licensed premises on the grounds listed (genre, live/amplified, dance floor, etc.) but only if the consent authority is satisfied noise may be managed and minimised to an acceptable level (cl 5.20(2)). The protection is therefore not absolute; evidence of noise management may be required.
Localised requirements in Jindera
Clauses 6.8 and 6.9 impose specific requirements for land in Jindera, including the prior preparation of development control plans for certain subdivisions and development. These targeted controls may impose pre-development obligations that differ from the general regime.
How to comply
A practical, clause‑anchored checklist for applicants and advisers:
Confirm the correct maps and zoning
Retrieve and confirm the current Land Zoning Map, Lot Size Map, Terrestrial Biodiversity Map, Riparian Lands and Watercourses Map, Wetlands Map, Heritage Map and Land Reservation Acquisition Map via the NSW Planning Portal as referenced (cl 1.7, cl 1.3). The maps determine permitted uses, minimum lot sizes, overlay constraints and acquisition/categorisation of public land.
Identify whether the proposed development is permitted without consent, exempt, complying or requires consent
Consult the Land Use Table for the zone (cl 2.3) to determine the category of development.
If exempt or complying, check Schedule 2 (exempt) and Schedule 3 (complying) and the Building Code of Australia provisions required by cl 3.1 and cl 3.2.
If the proposal is in an “environmentally sensitive area for exempt or complying development” it will not qualify for exempt/compliant status (cl 3.3).
Check lot size and subdivision controls
For subdivisions, verify the minimum lot size on the Lot Size Map and whether any exceptions in cl 4.1AA, 4.1A, 4.1B, 4.2, or 4.2AA apply. If a strata/community subdivision or split-zone lot is involved, apply the specific exception provisions carefully (cls 4.1AA, 4.1A, 4.1B).
Prepare required technical studies and documents keyed to the Plan’s mandatory matters
Biodiversity overlay (cl 6.2): prepare an ecological assessment addressing condition, habitat importance, fragmentation risks and connectivity; propose avoidance/minimisation/mitigation measures.
Riparian/wetlands (cls 6.3-6.4): supply water quality, bank stability, habitat and flow impact assessments; propose mitigation and compensation measures.
Flood planning (cl 5.21): provide flood risk assessment, evacuation and life-safety measures and consider climate change projections in line with the Guideline and the Flood Risk Management Manual references.
Heritage (cl 5.10): if the site contains a heritage item, Aboriginal place or archaeological site, prepare a heritage management document or conservation management plan if requested; be prepared for notification to Heritage Council and Aboriginal communities and allow 28 days for responses where required (cl 5.10(7)-(9)).
For eco-tourist facilities (cl 5.13): prepare a management strategy addressing the specific matters listed (connection to site values, minimal infrastructure, waste, biodiversity protection, design to avoid visibility above ridgelines, ISO 14000 type monitoring).
For proposals that would contravene a development standard, compile a cl 4.6 justification
If a development standard would be contravened, prepare a document demonstrating that compliance is unreasonable or unnecessary in the circumstances and setting out environmental planning grounds justifying the contravention (cl 4.6(3)). Note that the Regulation requires such a document to accompany the application (cl 4.6 note). Ensure the contravention is not one of the excluded standards in cl 4.6(8).
Check specific use limits and floor/area caps
Observe local caps for certain uses: bed and breakfast accommodation limited to 5 bedrooms (cl 5.4(1)); home business limited to 30 square metres (cl 5.4(2)); home industry to 100 square metres (cl 5.4(3)); industrial retail and artisan food and drink retail area caps in cl 5.4(4) and (10); kiosks, roadside stalls and neighbourhood shops floor area caps (cl 5.4(6)-(8)(7AA)). Secondary dwellings outside rural zones have size caps (cl 5.4(9)).
Ensure essential services will be available
Demonstrate availability or adequate arrangements for water, electricity, sewerage, stormwater, and vehicular access (cl 6.7).
For aquaculture or intensive livestock proposals, meet operational and locational criteria
For aquaculture, comply with Schedule 6 site and operational requirements: conservation exclusion zones, pond/tank design, screening outlets, no freshwater discharges to natural waterbodies for intensive systems except where open flow-through is used (Schedule 6 Div 1 and 2). For intensive livestock, respect capacity thresholds and buffer distances and avoid environmentally sensitive areas (cl 5.18(4)-(5)).
Heritage and Aboriginal consultation
If development affects an Aboriginal place of heritage significance or archaeological site, give the notices required by cl 5.10(7)-(8) and allow 28 days for the Heritage Council’s response or for replies from notified Aboriginal communities. Factor in time for preparation of heritage management documents or conservation plans where the consent authority requires them (cl 5.10(5)-(6)).
Special constraints and local DCP requirements
For land in Jindera covered by cls 6.8-6.9, ensure a development control plan has been prepared where required and that any required DCP content (staging, transport hierarchy, landscaping, stormwater, infrastructure sequencing) is addressed (cl 6.8-6.9).
Check for pre-existing approvals and savings
If the development application predates the Plan’s commencement and was not finally determined, that application will be assessed under the previous instrument (cl 1.8A). Verify the status of any such applications.
Pre-lodgement engagement and record-keeping
Engage with the Council early for pre-lodgement advice on mapped overlays and documentary requirements. Where a standards variation under cl 4.6 is sought, obtain clear written reasons and ensure the consent authority records its assessment in accordance with cl 4.6(4).
Consider rights, covenants and public authority interests
If the development relies on the Plan suspending private covenants, check cl 1.9A carefully for the limited scope of the suspension and the listed exclusions. Verify public authority rights under registered instruments are preserved (cl 1.9A(3)).
Where in doubt, confirm applicable State instruments
The Plan is subject to SEPPs where they prevail (cl 1.9(1)). If a State SEPP is applicable, reconcile any differences and confirm whether the State instrument provides additional or overriding rules.
Following these steps, keyed to the clauses cited above, will reduce the risk of procedural error, evidentiary insufficiency or missed notifications. Where complex environmental, heritage, flood or biodiversity matters arise, commission the specialist reports the Plan requires and allow time for the consent authority to consult the Heritage Council or local Aboriginal communities where the Plan mandates those steps.
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Culcairn Local Environmental Plan 1998
Hume Local Environmental Plan 2001
Interim Development Order No 1—Shire of Holbrook
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to development applications
1 Savings provision relating to development applications
1.8A Savings provision relating to development applications
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 4B of Part 3 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
cl 1.9A: Am 2019 (621), Sch 5[2]–[4].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate may exceed the maximum number of days specified in that subclause.
(5) Subclause (3)(d) does not apply to the temporary use of a dwelling as a sales office mentioned in subclause (4).
2 Canal estate development prohibited
2 Canal estate development prohibited
2.9 Canal estate development prohibited
(1) Canal estate development is prohibited on land to which this Plan applies.
(2) In this Plan, canal estate development means development that involves—
(a) a constructed canal, or other waterway or waterbody, that—
(i) is inundated by surface water or groundwater movement, or
(ii) drains to a waterway or waterbody by surface water or groundwater movement, and
This is an opening excerpt, not the complete document.