86 Notice to be given before operation carried out on any land
(1) A person must not carry out any geothermal energy operation on any land unless the person gives the owner, occupier or person or body responsible for the management of the land a written notice outlining the proposed operation at least 21 days before the activity starts.
(2) The owner, occupier or person or body may waive all or part of the 21 day notice period.
(3) In the case of unrestricted Crown land, the notice required by this section must be given to the Minister responsible for controlling or managing the land.
Division 4—Other matters