Gas Supply (Safety and Network Management) Regulation 2022
16Lodgement of safety and operating plans
Start here
Get a plain-English read of 16
Turn the raw legal text into a practical explanation grounded in Gas Supply (Safety and Network Management) Regulation 2022.
16 Lodgement of safety and operating plans
16 Lodgement of safety and operating plans
(1) A network operator must lodge with the Secretary a safety and operating plan for its gas network that complies with this Regulation.
Maximum penalty—
(a) for a corporation—10,000 penalty units, or
(b) for an individual—5,000 penalty units.
(2) The safety and operating plan must be lodged—
(a) within 6 months after the date of the grant of the authorisation or licence to operate the gas network to which the plan relates, or