sec.85 General obligations in carrying out work
The distributor must— complete the work as soon as practicable; and restore, as nearly as practicable, the relevant part of the place to the condition it was in before the work started; and remove any rubbish or surplus earth caused by the work; and comply with— conditions the public entity has imposed on any approval it has given to carry out the work; and any relevant provisions of the Petroleum and Gas (Production and Safety) Act and any other relevant law. If, in carrying out the work, the distributor causes damage to the place, the distributor must fix the damage as soon as practicable. s 85 amd 2004 No. 25 s 973 (sec.85-ssec.1) The distributor must— complete the work as soon as practicable; and restore, as nearly as practicable, the relevant part of the place to the condition it was in before the work started; and remove any rubbish or surplus earth caused by the work; and comply with— conditions the public entity has imposed on any approval it has given to carry out the work; and any relevant provisions of the Petroleum and Gas (Production and Safety) Act and any other relevant law. (sec.85-ssec.2) If, in carrying out the work, the distributor causes damage to the place, the distributor must fix the damage as soon as practicable.
- (a) complete the work as soon as practicable; and
- (b) restore, as nearly as practicable, the relevant part of the place to the condition it was in before the work started; and
- (c) remove any rubbish or surplus earth caused by the work; and
- (d) comply with— (i) conditions the public entity has imposed on any approval it has given to carry out the work; and (ii) any relevant provisions of the Petroleum and Gas (Production and Safety) Act and any other relevant law.
- (i) conditions the public entity has imposed on any approval it has given to carry out the work; and
- (ii) any relevant provisions of the Petroleum and Gas (Production and Safety) Act and any other relevant law.
- (i) conditions the public entity has imposed on any approval it has given to carry out the work; and