47 Energy Safe Victoria may request submission of revised safety case
S. 47(1) amended by No. 39/2005 s. 52(Sch. 2 item 1).
(1) Energy Safe Victoria may at any time request a gas company to submit a revised safety case for a facility of the gas company.
(2) The request must—
(b) set out—
(i) the matters to be addressed by the required revision; and
(ii) the proposed date of effect of the revision; and
(iii) the grounds for the request.
S. 47(3) amended by No. 39/2005 s. 52(Sch. 2 item 2).
(3) The gas company to whom the request is given may make a submission to Energy Safe Victoria on all or any of the following grounds—
(a) that the revision should not occur;
(b) that the revision should be in different terms from the proposed terms;
(c) that the revision should take effect on a later date than the proposed date of effect.
(4) The submission must—
(b) state the gas company's reasons for the submission; and
S. 47(4)(c) amended by No. 39/2005 s. 52(Sch. 2 item 2).
(c) be made within 21 days, or such later period as Energy Safe Victoria in writing allows, after the request is received.
S. 47(5) amended by No. 39/2005 s. 52(Sch. 2 item 2).
(5) If a gas company makes a submission under this section, Energy Safe Victoria must decide—
(a) to accept the submission or part of the submission and vary or withdraw the request accordingly; or
(b) to reject the submission.
S. 47(6) amended by No. 39/2005 s. 52(Sch. 2 item 1).
(6) Energy Safe Victoria must give the gas company notice in writing of its decision on the submission and the reasons for that decision.