Future Made in Australia (Guarantee of Origin) Act 2024
88Grounds of suspension or cancellation
Start here
Get a plain-English read of 88
Turn the raw legal text into a practical explanation grounded in Future Made in Australia (Guarantee of Origin) Act 2024.
88 Grounds of suspension or cancellation
(1) This section applies to a registered renewable electricity facility if:
(a) the Regulator reasonably believes that a condition imposed on the registration of the facility under Subdivision B has been contravened; or
(b) both of the following apply:
(i) a component is added to, or removed from, the facility;
(ii) the Regulator is satisfied that the Regulator would not have registered the facility under Subdivision B if the component had not been included, or had been included, as the case may be, in the application to register the facility; or
(c) the Regulator is no longer satisfied:
(i) if the facility is an electricity generation system that is registered under section 79—that the facility meets the criteria in subsection (2) of that section; or
(ii) if the facility is an energy storage system that is registered under section 80—that the facility meets the criteria in subsection (2) of that section; or
(iii) if the facility is an aggregated system that is registered under section 81—that the facility meets the criteria in subsection (4) of that section.
(2) This section also applies to a registered renewable electricity facility in the circumstances prescribed by the rules.