Environmental Planning and Assessment (Savings, Transitional and Other Provisions) Regulation 2017
111Lapsing of consent
Start here
Get a plain-English read of 111
Turn the raw legal text into a practical explanation grounded in Environmental Planning and Assessment (Savings, Transitional and Other Provisions) Regulation 2017.
111 Lapsing of consent
111 Lapsing of consent
A development consent granted before the commencement of section 95(6), as inserted by the amending Act, that is subject to a deferred commencement condition under section 80(3), lapses if the applicant fails to satisfy the consent authority as to the matter specified in the condition within—
(a) 5 years after the date consent was granted, or
(b) 2 years after the date of the commencement of section 95(6),
whichever is the later.