#### 77 Conditions for ancillary aspects of development
77 Conditions for ancillary aspects of development
> > (1) If a consent authority grants development consent subject to a condition referred to in the Act, section 4.17(2) in relation to an ancillary aspect of the development, the consent authority may specify the period within which the ancillary aspect must be carried out to the satisfaction of the consent authority or a person specified by the consent authority.
>
> > (2) The applicant may produce evidence to the consent authority, or to the person specified by the consent authority, sufficient to enable the consent authority or the person to be satisfied in relation to the ancillary aspect of the development.
>
> > (3) For the purposes of the Act, section 4.17(3), the relevant period is the period of 28 days after the applicant’s evidence is produced to the consent authority or a person specified by the consent authority.