#### 281 Notice of development control orders
281 Notice of development control orders
> > (1) If a consent authority, other than a council, proposes to give a development control order that relates to building work or subdivision work for which the consent authority is not the principal certifier, the consent authority must give the principal certifier notice of its intention to give the order.
>
> > (2) A notice required to be given by a consent authority under this section or by a council under the Act, Schedule 5, clause 9(2) must be given within 7 days after the notice of intention to give the order is given under the Act, Schedule 5, clause 8.