#### 75 Signs on development sites
75 Signs on development sites
> > (1) The principal certifier and the principal contractor for building work, subdivision work or demolition work authorised to be carried out on a site by a development consent must ensure a sign that complies with this section is—
> >
> > > (a) erected in a prominent position on the site before the commencement of the work, and
> >
> > > (b) maintained at all times while the work is being carried out and while the person remains the principal certifier or principal contractor, and
> >
> > > (c) removed when the work has been completed.
> >
> > Maximum penalty (subsection (1))—55 penalty units.
>
> > (2) The sign must be rigid and durable and show the following information—
> >
> > > (a) the name, address and telephone number of the principal certifier, and
> >
> > > (b) if there is a principal contractor—the principal contractor’s name and address and a telephone number on which the principal contractor may be contacted outside working hours.
>
> > (3) The information required under subsection (2) must be able to be read easily by a person on a public road or in another public place adjacent to the site.
>
> > (4) This section does not—
> >
> > > (a) require the erection of more than one sign on a site, or
> >
> > > (b) prevent the use of an appropriate sign that has already been erected on a site.