Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021
59Notice of intention to commence erection of building or subdivision work
Start here
Get a plain-English read of 59
Turn the raw legal text into a practical explanation grounded in Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021.
59 Notice of intention to commence erection of building or subdivision work
59 Notice of intention to commence erection of building or subdivision work
(1) A person required to give a notice under the Act, section 6.6(2)(e) or 6.12(2)(c) must ensure the notice contains the following information—
(a) the name and address of the person,
(b) a description of the work to be carried out,
(c) the address of the land on which the work will be carried out,
(d) the registered numbers and date of issue of the development consent and construction certificate,
(e) a statement signed by or on behalf of the principal certifier that all conditions of the consent that must be satisfied before the work commences have been satisfied,
(f) the date on which the work is intended commence.
(2) The notice must be lodged on the NSW planning portal.