53Occupation certificates for partially completed buildings—the Act, s 6.33(1)
Start here
Get a plain-English read of 53
Turn the raw legal text into a practical explanation grounded in Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021.
#### 53 Occupation certificates for partially completed buildings—the Act, s 6.33(1)
53 Occupation certificates for partially completed buildings—the Act, s 6.33(1)
> It is a condition of an occupation certificate issued for the first completed stage of a partially completed building (the partial occupation certificate) that an occupation certificate must be obtained for the whole building within 5 years after the partial occupation certificate is issued.