Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021
45BASIX completion receipt
Start here
Get a plain-English read of 45
Turn the raw legal text into a practical explanation grounded in Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021.
45 BASIX completion receipt
45 BASIX completion receipt
(1) This section applies to an occupation certificate for BASIX development if a relevant BASIX certificate requires a certifier to monitor fulfilment of a commitment listed in the certificate in relation to a building.
(2) A certifier must not issue an occupation certificate for the building unless the certifier has a receipt from the Planning Secretary (a BASIX completion receipt) for the building.
Maximum penalty (subsection (2))—
(a) for a corporation—100 penalty units, or
(b) for an individual—50 penalty units.
(3) An application for a BASIX completion receipt must—
(a) be made in the approved form, and
(b) contain the following information—
(i) the number of each relevant BASIX certificate for the building or part of the building,
(ii) the postcode of the address of the building,
(iii) the date of the final inspection.
(4) The Planning Secretary may issue a BASIX completion receipt—
(a) by an approved BASIX system, or
(b) in another way approved by the Planning Secretary from time to time.
(5) A BASIX completion receipt must—
(a) be in the approved form, and
(b) confirm that the information required under subsection (3)(b) has been received.
(6) This section does not apply to an occupation certificate to commence occupation or use of a partially completed building.