111Exemption from fire safety standards
Start here
Get a plain-English read of 111
Turn the raw legal text into a practical explanation grounded in Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021.
#### 111 Exemption from fire safety standards
111 Exemption from fire safety standards
> > (1) This section applies to development the subject of—
> >
> > > (a) a development application or an application for a complying development certificate for a change of building use for an existing building, if the application does not seek an alteration of the building, or
> >
> > > (b) an application for a construction certificate for building work, other than building work associated with a change of building use referred to in paragraph (a).
>
> > (2) The applicant may lodge an objection with the Fire Commissioner that compliance with a specified Category 3 fire safety provision, as applied by a relevant provision, is unreasonable or unnecessary in the circumstances.
>
> > (3) The objection must—
> >
> > > (a) specify the grounds of the objection, and
> >
> > > (b) for proposed building work—include a copy of the building work plans and specifications.
>
> > (4) If the Fire Commissioner is satisfied the objection is well-founded, the Fire Commissioner may exempt the development, either conditionally or unconditionally, from a specified Category 3 fire safety provision, as applied by a relevant provision.
>
> > (5) If the Fire Commissioner grants an exemption subject to a condition, the applicant must include the condition in the building work plans and specifications by—
> >
> > > (a) redrawing the plans and specifications, or
> >
> > > (b) annotating the relevant part of the plans and specifications, including by inserting, deleting or altering matter.
>
> > (6) Subsection (5) applies only if the condition can be given effect to by being included in the building work plans and specifications.
>
> > (7) If the condition cannot be included in the building work plans and specifications—
> >
> > > (a) the consent authority or certifier must, if granting development consent for development referred to in subsection (1)(a), grant development consent subject to the condition, or
> >
> > > (b) the certifier must, if issuing a construction certificate for development referred to in subsection (1)(b), issue the construction certificate subject to the condition.
>
> > (8) In this section—
> >
> > relevant provision means the [Environmental Planning and Assessment Regulation 2021](/view/html/inforce/current/sl-2021-0759), section 69 or 146.
>
> Maximum penalty (subsections (5) and (7)(b))—
>
> > (a) for a corporation—150 penalty units, or
>
> > (b) for an individual—75 penalty units.
>
> **s 111:** Am 2022 (40), Sch 2\[8\].