Environmental Management and Pollution Control Act 1994
42KGrant of licence by Board
Start here
Get a plain-English read of 42K
Turn the raw legal text into a practical explanation grounded in Environmental Management and Pollution Control Act 1994.
42K Grant of licence by Board
(1) In this section –
relevant application means an application, in relation to an EL activity, that –
(a) is an application, or relates to an activity, referred to the Board –
(i) under section 25 or 27AA ; or
(ii) under section 42I(2) ; and
(b) is not a relevant application within the meaning of section 42Q(1) ;
relevant project means a project that –
(a) [Section 42K Subsection (1) amended by No. 21 of 2020, s. 34, Applied:28 Oct 2020] is a project, in relation to an EL activity, in relation to which a notice of intent is lodged under section 27B ; and
(b) is not a relevant project within the meaning of section 42Q(1) .
(2) The Board may –
(a) [Section 42K Subsection (2) amended by No. 21 of 2020, s. 34, Applied:28 Oct 2020] within 28 days after a relevant application, or a relevant project, in relation to an EL activity is referred to the Board under section 25 , section 27AA or section 42I(2) ; or
(b) after a notice of intent in relation to a relevant project, in relation to an EL activity, is lodged under section 27B –
refuse, on a ground referred to in section 42L(1) or (2) , to grant an environmental licence in relation to the activity.
(3) [Section 42K Subsection (3) amended by No. 21 of 2020, s. 34, Applied:28 Oct 2020] As soon as practicable after the Board has completed under , or an assessment in relation to an EL activity, the Board must –