38A Statutory restrictions for purposes of Land Title Act 2000
(1) The Minister cannot consent under section 38(1A) to the
commencement of operations in relation to a pipeline unless the
licensee has provided to the Minister:
(a) detailed drawings of the pipeline as constructed, indicating
where the pipeline is located and the 25 m wide corridor
referred to in section 66 in relation to the pipeline, that are
suitable for incorporation into a memorandum to be given by
the Minister under subsection (2); and
(b) evidence that the licensee has given notice to each person
whose operations on or interest in the land shown in the
detailed drawings may be affected by the operation of
section 66 of the nature of the restrictions that are placed on
the use or occupation or any dealing with the land.
(2) The Minister must, within 60 days after receiving information
supplied under subsection (1), lodge with the Registrar-General a
memorandum under section 35 of the Land Title Act 2000 in
relation to the land referred to in subsection (1)(a).