sec.68 Purpose of division
This division provides a framework for the recovery of costs associated with the hub transmission network for a regional energy hub incurred by the transmission network service provider or AEMO. The framework provides for the costs to be recovered from the participants for the regional energy hub in the first instance. s 68 sub 2025 No. 30 s 45 (sec.68-ssec.1) This division provides a framework for the recovery of costs associated with the hub transmission network for a regional energy hub incurred by the transmission network service provider or AEMO. (sec.68-ssec.2) The framework provides for the costs to be recovered from the participants for the regional energy hub in the first instance.